Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:1344 DOBSON BROTHERS CONSTRUCTION COMPANY
Contract ID:3021
Estimate Number:0041
Pay Period End Date:03.29.2003
Contract Location:
NORFOLK EASTEstimate Type:PROG
Contractor:
DOBSON BROTHERS CONSTRUCTION COMPANYDate Let:07.12.2001
410 SOUTH 7THDate Awarded:07.18.2001
PO BOX 81409Date Contract Executed:07.20.2001
Date Notice to Proceed:07.20.2001
LINCOLN NE 68501Date Work Began:07.30.2001
Phone:Date Physical Work Completed:
(402)474-5115Date Accepted:
Escrow Agent:
Surety Co:
NATIONAL FIRE INSURANCE COMPANY OF HARTFORD
Counties
STANTON
Project Number PCT Fed State Project Number Description
32021 000  0.000 F-275-6(1020)  GRAD, CONC PAVE, CULV, SEED, ELEC
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$12,452,057.88$12,361,701.67$90,356.21
$18,519,172.08Stockpiled Materials$203,192.95$203,250.28$-57.33
Original Contract AmtGross Earnings$12,655,250.83$12,564,951.95$90,298.88
$18,274,985.53Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
67.24%Net Earnings$12,630,250.83$12,539,951.95$90,298.88
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-5,562.92$-6,632.43$1,069.51
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$5,562.92-$6,632.43$1,069.51
Payment$12,624,687.91$12,533,319.52$91,368.39
Project ManagerDiv. Head/Dist. Eng.
Davis, Rob04.01.2003Boyle, Pat04.02.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve04.02.2003
Controller Div. Processed
Burling, Laurie04.02.2003
Detailed breakdown of stockpiled materials
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0097P150.72 1800 mm CULVERT PIPE, TYPE 5
S.P. Initial Payment807.0881-10-0012
1800mm pipe
0102P200.48 1200 mm CULVERT PIPE, TYPE 2 OR 5
S.P. Initial Payment3,382.4781-10-0012
1200mm Pipe, 2 or 5
0105P400.24 600 mm CULVERT PIPE, TYPE 2,5,7 OR 8
S.P. Initial Payment1,612.1981-09-0025
600mm pipe
01664310.24 600 mm FLARED-END SECTION
S.P. Initial Payment762.0081-09-0025
600mm FES
01684310.36 900 mm FLARED-END SECTION
S.P. Initial Payment489.7281-09-0142
900mm FES
01704310.48 1200 mm FLARED-END SECTION
S.P. Initial Payment1,485.5681-10-0012
1200mm FES
01714310.72 1800 mm FLARED-END SECTION
S.P. Initial Payment1,611.2081-10-0012
1800mm FES
Total for estimate 0011:10,150.22
Est Nbr:0012
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0100P200.36 900 mm CULVERT PIPE, TYPE 2 OR 5
S.P. Initial Payment244.8281-10-0005
900mm pipe,2 or 5
0107P400.36 900 mm CULVERT PIPE, TYPE 2,5,7 OR 8
S.P. Initial Payment4,036.1181-10-0005
900mm pipe
Total for estimate 0012:4,280.93
Est Nbr:0017
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00723075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment70,741.8236246
fine aggregate
S.P. Initial Payment124,757.51742
coarse aggregate
Total for estimate 0017:195,499.33
Est Nbr:0020
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0107P400.36 900 mm CULVERT PIPE, TYPE 2,5,7 OR 8
S.P. Adjustment-1,000.2881-10-0005
900mm pipe
01684310.36 900 mm FLARED-END SECTION
S.P. Adjustment-122.4381-09-0142
900mm FES
Total for estimate 0020:-1,122.71
Est Nbr:0021
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0097P150.72 1800 mm CULVERT PIPE, TYPE 5
S.P. Adjustment-807.0881-10-0012
1800mm pipe
0105P400.24 600 mm CULVERT PIPE, TYPE 2,5,7 OR 8
S.P. Adjustment-723.2581-09-0025
600mm pipe
01664310.24 600 mm FLARED-END SECTION
S.P. Adjustment-457.2081-09-0025
600mm FES
01714310.72 1800 mm FLARED-END SECTION
S.P. Adjustment-1,611.2081-10-0012
1800mm FES
Total for estimate 0021:-3,598.73
Est Nbr:0022
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0102P200.48 1200 mm CULVERT PIPE, TYPE 2 OR 5
S.P. Adjustment-1,433.2581-10-0012
1200mm Pipe, 2 or 5
01704310.48 1200 mm FLARED-END SECTION
S.P. Adjustment-742.7881-10-0012
1200mm FES
Total for estimate 0022:-2,176.03
Est Nbr:0023
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00723075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment132,192.9336246
fine aggregate
S.P. Initial Payment327,096.90742
coarse aggregate
0100P200.36 900 mm CULVERT PIPE, TYPE 2 OR 5
S.P. Adjustment-244.8281-10-0005
900mm pipe,2 or 5
0102P200.48 1200 mm CULVERT PIPE, TYPE 2 OR 5
S.P. Adjustment114.6681-10-0012
1200mm Pipe, 2 or 5
0105P400.24 600 mm CULVERT PIPE, TYPE 2,5,7 OR 8
S.P. Adjustment13.1581-09-0025
600mm pipe
01684310.36 900 mm FLARED-END SECTION
S.P. Adjustment-122.4381-09-0142
900mm FES
Total for estimate 0023:459,050.39
Est Nbr:0024
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0105P400.24 600 mm CULVERT PIPE, TYPE 2,5,7 OR 8
S.P. Adjustment13.1581-09-0025
600mm pipe
Total for estimate 0024:13.15
Est Nbr:0025
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00723075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-27,366.2736246
fine aggregate
S.P. Adjustment-26,177.67742
coarse aggregate
Total for estimate 0025:-53,543.94
Est Nbr:0026
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00723075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-43,375.5536246
fine aggregate
S.P. Adjustment-79,387.9036246
fine aggregate
S.P. Adjustment-98,579.85742
coarse aggregate
S.P. Adjustment-18,851.59742
coarse aggregate
Total for estimate 0026:-240,194.89
Est Nbr:0027
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00723075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-52,805.0336246
fine aggregate
S.P. Adjustment-126,811.19742
coarse aggregate
Total for estimate 0027:-179,616.22
Est Nbr:0028
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00723075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-533.37742
coarse aggregate
Total for estimate 0028:-533.37
Est Nbr:0030
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00723075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-520.78742
coarse aggregate
Total for estimate 0030:-520.78
Est Nbr:0031
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00723075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-0.24742
coarse aggregate
Total for estimate 0031:-0.24
Est Nbr:0034
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00723075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment21,053.958425
Dowel Basket Assemblies
0102P200.48 1200 mm CULVERT PIPE, TYPE 2 OR 5
S.P. Adjustment-2,006.5581-10-0012
1200mm Pipe, 2 or 5
0105P400.24 600 mm CULVERT PIPE, TYPE 2,5,7 OR 8
S.P. Adjustment-915.2481-09-0025
600mm pipe
0107P400.36 900 mm CULVERT PIPE, TYPE 2,5,7 OR 8
S.P. Adjustment-1,384.3181-10-0005
900mm pipe
01664310.24 600 mm FLARED-END SECTION
S.P. Adjustment-304.8081-09-0025
600mm FES
01684310.36 900 mm FLARED-END SECTION
S.P. Adjustment-122.4381-09-0142
900mm FES
01704310.48 1200 mm FLARED-END SECTION
S.P. Adjustment-742.7881-10-0012
1200mm FES
Total for estimate 0034:15,577.84
Est Nbr:0038
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00723075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-8.23742
coarse aggregate
S.P. Adjustment-6.448425
Dowel Basket Assemblies
Total for estimate 0038:-14.67
Est Nbr:0041
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0102P200.48 1200 mm CULVERT PIPE, TYPE 2 OR 5
S.P. Adjustment-57.3381-10-0012
1200mm Pipe, 2 or 5
Total for estimate 0041:-57.33
Total remaining for contract:203,192.95
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 126.2585.00010,731.25
COVER CROP SEEDING ha 85.00010,731.25
44.1865,578.50
0.0000.00

0002                          L020.00 1.2986,046.000110,999.34
EROSION CONTROL m2 86,046.000110,999.34
30,420.26639,242.14
0.0000.00

0003                          L020.01 5.0525,783.000130,204.15
EROSION CONTROL, TYPE A m2 25,783.000130,204.15
10,201.59551,518.07
0.0000.00

0004                          L020.03 1.82305.000555.10
EROSION CONTROL, TYPE C m2 305.000555.10
0.0000.00
0.0000.00

0005                          L020.08 5.159,902.00050,995.30
EROSION CONTROL, TYPE AA m2 9,902.00050,995.30
6,188.40031,870.27
0.0000.00

0006                          L020.09 11.411,136.00012,961.76
EROSION CONTROL, TYPE AAA m2 1,136.00012,961.76
505.4805,767.53
0.0000.00

0007                          L020.10 1.3435,350.00047,369.00
EROSION CONTROL, TYPE HV m2 35,350.00047,369.00
25,726.08534,472.96
0.0000.00

0008                          L021.01 15.912,395.00038,104.45
EROSION CHECKS, TYPE A BALE2,395.00038,104.45
811.00012,903.01
0.0000.00

0009                          L021.03 10.1028.000282.80
EROSION CHECKS, TYPE C BALE28.000282.80
0.0000.00
0.0000.00

0010                          L021.06 11.111,205.00013,387.55
EROSION CHECKS, TYPE HV BALE1,205.00013,387.55
469.0005,210.59
0.0000.00

0011                          L021.11 15.91350.0005,568.50
EROSION CHECKS, TYPE ST-A BALE350.0005,568.50
86.0001,368.26
0.0000.00

0012                          L021.15 15.151,526.00023,118.90
EROSION CHECKS, TYPE ST-HV BALE1,526.00023,118.90
210.0003,181.50
0.0000.00

0013                          L021.21 15.91903.00014,366.73
EROSION CHECKS, TYPE AA BALE903.00014,366.73
515.0008,193.65
0.0000.00

0014                          L022.11 6.576,116.40040,184.75
FABRIC SILT FENCE-LOW POROSITY m 6,116.40040,184.75
6,724.02044,176.84
0.0000.00

0015                          L022.12 7.5818.600140.99
FABRIC SILT FENCE-HIGH POROSITY m 18.600140.99
239.7001,816.93
0.0000.00

0016                          L022.25 15.1578.0001,181.70
FABRIC SILT FENCE, TYPE COIR FIBER m 78.0001,181.70
0.0000.00
0.0000.00

0017                          L022.75 16.503,781.00062,386.50
TEMPORARY SILT CHECK m 1,081.00017,836.50
323.0705,330.66
0.0000.00

0018                          P310.42 101.0030.5003,080.50
1050 mm CULVERT PIPE, TYPE 2,4 OR 5 m 30.5003,080.50
0.0000.00
0.0000.00

0019                          P400.18 45.11930.00041,952.30
450 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 930.00041,952.30
530.50023,930.86
0.0000.00

0020                          P500.18 45.1167.0003,022.37
450 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 67.0003,022.37
177.0007,984.47
0.0000.00

0021                          P500.30 70.7014.000989.80
750 mm CULVERT PIPE, TYPE 2,4,5,7 or 8 m 14.000989.80
0.0000.00
0.0000.00

0022                          0030.10 300,000.001.000300,000.00
MOBILIZATION LS 1.000300,000.00
1.000300,000.00
0.0000.00

0023                          1009.00 101,000.001.000101,000.00
GENERAL CLEARING AND GRUBBING LS 1.000101,000.00
0.80080,800.00
0.0000.00

0024                          1010.00 1.252,679,523.0003,349,403.75
EXCAVATION m3 2,649,523.0003,311,903.75
2,134,638.8962,668,298.61
17,707.18622,133.98

0025                          1010.01 2.0236,600.00073,932.00
EXCAVATION (ESTABLISHED QUANTITY) m3 36,600.00073,932.00
26,015.70052,551.72
0.0000.00

0026                          1010.50 2.021,560.0003,151.20
REMOVAL OF UNSUITABLE MATERIAL m3 1,560.0003,151.20
761.8501,538.93
0.0000.00

0027                          1011.00 1.0139,375.00039,768.75
WATER kL 39,375.00039,768.75
5,282.7815,335.61
0.0000.00

0028                          1012.00 53.53276.00014,774.28
RIGHT-OF-WAY MARKERS EACH276.00014,774.28
240.00012,847.20
0.0000.00

0029                          1017.00 60,600.001.00060,600.00
CONSTRUCTION STAKING AND SURVEYING LS 1.00060,600.00
0.40024,240.00
0.0000.00

0030                          1030.00 1.0139,526.00039,921.26
EARTHWORK MEASURED IN EMBANKMENT m3 39,526.00039,921.26
0.0000.00
0.0000.00

0031                          1041.00 0.3819,452.0007,391.76
SALVAGING AND PLACING TOPSOIL m2 19,452.0007,391.76
0.0000.00
0.0000.00

0032                          1090.00 505.002.0001,010.00
ABANDON WELLS EACH2.0001,010.00
2.0001,010.00
0.0000.00

0033                          1102.00 3.243,337.00010,811.88
REMOVE ASPHALT SURFACE m2 3,337.00010,811.88
6,546.07021,209.27
3,738.59012,113.03

0034                          1106.00 3.031,196.0003,623.88
REMOVE DRIVEWAY m2 1,196.0003,623.88
734.5502,225.68
0.0000.00

0035                          1109.00 10.10180.0001,818.00
REMOVE CURB m 180.0001,818.00
360.0003,636.00
0.0000.00

0036                          1120.00 505.002.0001,010.00
REMOVE DISCHARGE STRUCTURE EACH2.0001,010.00
1.000505.00
0.0000.00

0037                          1122.01 4.04125.000505.00
REMOVE CONCRETE MEDIAN SURFACING m2 125.000505.00
103.841419.52
0.0000.00

0038                          1124.00 101.001.000101.00
REMOVE BUILDING EACH1.000101.00
AT STA. 164+40 RT. 1.000101.00
0.0000.00

0039                          1124.01 101.001.000101.00
REMOVE BUILDING EACH1.000101.00
AT STA. 164+74 RT 1.000101.00
0.0000.00

0040                          1124.02 101.001.000101.00
REMOVE BUILDING EACH1.000101.00
AT STA. 165+07.4 RT 1.000101.00
0.0000.00

0041                          1124.03 101.001.000101.00
REMOVE BUILDING EACH1.000101.00
AT STA. 226+81.63 RT 1.000101.00
0.0000.00

0042                          1124.04 101.001.000101.00
REMOVE BUILDING EACH1.000101.00
AT STA. 227+00 LT 1.000101.00
0.0000.00

0043                          1125.00 1,515.001.0001,515.00
CLEAR TRACT EACH1.0001,515.00
AT STA. 164+20 TO 165+20 RT. 1.0001,515.00
0.0000.00

0044                          1125.01 1,515.001.0001,515.00
CLEAR TRACT EACH1.0001,515.00
AT STA. 226+65 TO 227+10 LT & RT 1.0001,515.00
0.0000.00

0045                          1128.50 5.05270.0001,363.50
REMOVE SLAB m2 270.0001,363.50
268.8031,357.46
0.0000.00

0046                          1701.24 50.50350.50017,700.25
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 350.50017,700.25
190.2009,605.10
0.0000.00

0047                          1701.36 75.7543.0003,257.25
900 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 43.0003,257.25
42.0003,181.51
0.0000.00

0048                          3001.00 2.397,518.00017,968.02
BREAK CONCRETE PAVEMENT m2 7,518.00017,968.02
7,445.63017,795.05
0.0000.00

0049                          3017.50 116.5854.0006,295.32
INTERLOCKING CONCRETE PAVER BLOCK m2 54.0006,295.32
68.0407,932.10
0.0000.00

0050                          4035.00 50.504.000202.00
REMOVE FLARED-END SECTION EACH4.000202.00
2.000101.00
0.0000.00

0051                          4050.01 9.8930.000296.70
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 30.000296.70
0.0000.00
0.0000.00

0052                          4105.59 807.1721.60017,434.87
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 21.60017,434.87
0.0000.00
0.0000.00

0053                          4155.50 1.47972.0001,428.84
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 972.0001,428.84
0.0000.00
0.0000.00

0054                          4310.18 165.0133.0005,445.33
450 mm FLARED-END SECTION EACH33.0005,445.33
21.0003,465.21
0.0000.00

0055                          4670.05 75.7510.000757.50
CULVERT SANDFILL m3 10.000757.50
14.3901,090.05
0.0000.00

0056                          4900.24 413.9239.00016,142.88
AREA INLET SEDIMENT FILTER EACH39.00016,142.88
0.0000.00
0.0000.00

0057                          7017.00 8.591,738.70014,935.43
REMOVE GUARDRAIL m 1,738.70014,935.43
1,979.50017,003.91
0.0000.00

0058                          9110.01 60.75150.0009,112.50
RENTAL OF LOADER, FULLY OPERATED HOUR150.0009,112.50
520.00031,590.04
30.5001,852.88

0059                          9110.02 60.60150.0009,090.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR150.0009,090.00
146.5008,877.90
24.0001,454.40

0060                          9110.07 36.49150.0005,473.50
RENTAL OF SKID LOADER, FULLY OPERATED HOUR150.0005,473.50
2.00072.98
0.0000.00

401                           9110.15 99.750.0000.00
RENTAL OF CRAWLER TRACTOR, FULLY OPERATED HOUR30.0002,992.50
82.0008,179.51
-6.000-598.50

404                           9110.06 157.500.0000.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR30.0004,725.00
183.75028,940.63
48.0007,560.00

405                           1043.00 0.730.0000.00
COHESIVE SOIL COVER m2 11,250.0008,212.50
20,503.79014,967.77
0.0000.00

406                           8023.50 1.210.0000.00
SELECT MATERIAL m3 2,250.0002,722.50
cohesive material for capping road top 1,204.8751,457.90
0.0000.00

407                           8091.00 31.470.0000.00
GRANULAR BACKFILL m3 2,500.00078,675.00
1,777.54555,939.34
0.0000.00

411                           9110.03 138.310.0000.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR20.0002,766.20
off- road 6x6 truck 175.00024,204.26
0.0000.00

412                           9110.03 55.130.0000.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR35.0001,929.55
77.0004,245.03
42.5002,343.03

413                           1990.06 690.620.0000.00
EQUIPMENT RENTAL LS 1.000690.62
trencher with frost teeth 1.000690.62
0.0000.00

414                           L022.75 11.420.0000.00
TEMPORARY SILT CHECK m 2,700.00030,834.00
Excelsior log 42.000479.64
0.0000.00

415                           L022.70 6.300.0000.00
SILT TRAP EACH200.0001,260.00
92.000579.60
0.0000.00

417                           9110.12 197.050.0000.00
RENTAL OF SCRAPER, FULLY OPERATED HOUR25.0004,926.25
627 42.0008,276.10
0.0000.00

418                           9110.12 221.030.0000.00
RENTAL OF SCRAPER, FULLY OPERATED HOUR138.00030,502.14
631 140.00030,944.20
2.000442.06

419                           9110.12 290.340.0000.00
RENTAL OF SCRAPER, FULLY OPERATED HOUR25.0007,258.50
637 58.00016,839.72
0.0000.00

420                           9110.15 83.550.0000.00
RENTAL OF CRAWLER TRACTOR, FULLY OPERATED HOUR25.0002,088.75
Challenger 14.5001,211.48
0.0000.00

421                           9110.20 83.550.0000.00
RENTAL OF SELF-PROPELLED ROLLER, FULLY OPERATED HOUR30.0002,506.50
815F 34.5002,882.48
0.0000.00

422                           9110.02 122.330.0000.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR62.0007,584.46
14H 100.00012,233.02
2.500305.83

423                           9110.11 137.950.0000.00
RENTAL OF BULLDOZER, FULLY OPERATED HOUR35.0004,828.25
D9 Cat 34.5004,759.28
0.0000.00

430                           6960.02 983.080.0000.00
ADDITIONAL WORK LS 1.000983.08
for extra pipes 1.000983.08
0.0000.00

433                           3900.20 2,020.200.0000.00
ADDITIONAL COST LS 1.0002,020.20
for temp pipe at 154+ 1.0002,020.20
0.0000.00

436                           4325.18 535.500.0000.00
450 mm SAFETY SLOPED END SECTION EACH2.0001,071.00
0.0000.00
0.0000.00

439                           9110.36 73.500.0000.00
RENTAL OF TRUCK/TRAILER, FULLY OPERATED HOUR25.0001,837.50
38.5002,829.75
38.5002,829.75

603                           1010.50 2.500.0000.00
REMOVAL OF UNSUITABLE MATERIAL m3 1,000.0002,500.00
5,310.62013,276.56
0.0000.00

GROUP 1 GRADINGContracted4,750,744.39
Current4,871,608.89
In place3,798,711.26
This Estimate50,436.46

GROUP 3 CONCRETE PAVEMENT
0061                          0002.39 4.04500.0002,020.00
TEMPORARY PAVEMENT MARKING, TYPE II m 500.0002,020.00
0.0000.00
0.0000.00

0062                          0002.44 1.013,600.0003,636.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT m 3,600.0003,636.00
7,157.0007,228.57
0.0000.00

0063                          0030.30 600,000.001.000600,000.00
MOBILIZATION LS 1.000600,000.00
1.000600,000.00
0.0000.00

0064                          1020.01 15.15324.0004,908.60
DELINEATOR, TYPE I EACH324.0004,908.60
0.0000.00
0.0000.00

0065                          2001.00 20.202,842.00057,408.40
GRAVEL SURFACE COURSE m3 2,842.00057,408.40
1,986.48240,126.92
0.0000.00

0066                          2010.00 35.35277.0009,791.95
CRUSHED ROCK SURFACE COURSE m3 277.0009,791.95
1,360.21048,083.43
0.0000.00

0067                          2021.00 50.5022.0001,111.00
MAILBOX POST EACH22.0001,111.00
3.000151.50
0.0000.00

0068                          3012.06 38.56180.0006,940.80
CONCRETE CLASS 47B-25 MEDIAN CURB m 180.0006,940.80
83.0003,200.48
0.0000.00

0069                          3017.40 40.5364.0002,593.92
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 64.0002,593.92
61.8802,508.00
0.0000.00

0070                          3075.41 32.411,415.00045,860.15
230 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 1,415.00045,860.15
1,598.00051,791.18
0.0000.00

0071                          3075.51 36.27607.00022,015.89
255 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 607.00022,015.89
292.38010,604.62
0.0000.00

0072                          3075.55 27.41235,630.0006,458,618.30
255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 235,630.0006,458,618.30
115,441.1303,164,241.38
0.0000.00

0073                          3089.25 17.6010,870.000191,312.00
TEMPORARY SURFACING m2 10,870.000191,312.00
200mm 5,976.968105,194.63
0.0000.00

0074                          3275.20 4.63125,758.000582,259.54
CRUSH CONCRETE PAVEMENT m2 125,758.000582,259.54
116,231.210538,150.50
0.0000.00

0075                          3275.21 9.4618,000.000170,280.00
CRUSH CONCRETE Mg 18,000.000170,280.00
49,015.800463,689.47
0.0000.00

0076                          3300.50 13,464.941.00013,464.94
PORTLAND CEMENT CONCRETE SMOOTHNESS TESTING LS 1.00013,464.94
0.5006,732.47
0.0000.00

0077                          4763.26 141.414.000565.64
UNDERDRAIN HEADWALL EACH4.000565.64
0.0000.00
0.0000.00

0078                          4764.35 19.5649.500968.22
100 mm PERFORATED PIPE UNDERDRAIN m 49.500968.22
162.4643,177.79
0.0000.00

0079                          7550.03 1.2626,000.00032,760.00
100 mm YELLOW EPOXY PAVEMENT MARKING m 26,000.00032,760.00
0.0000.00
0.0000.00

0080                          7550.04 1.2632,400.00040,824.00
100 mm WHITE EPOXY PAVEMENT MARKING m 32,400.00040,824.00
0.0000.00
0.0000.00

0081                          8029.10 5.0058,953.000294,765.00
AGGREGATE FOUNDATION COURSE-D 100 mm m2 58,953.000294,765.00
0.0000.00
0.0000.00

0082                          8029.84 1.528,000.00012,160.00
BITUMINOUS FOUNDATION COURSE 100 mm m2 8,000.00012,160.00
0.0000.00
0.0000.00

0083                          8032.04 1.10210,279.000231,306.90
CRUSHED CONCRETE FOUNDATION COURSE 100 mm m2 210,279.000231,306.90
137,460.330151,206.37
0.0000.00

0084                          8060.05 46.71250.00011,677.50
GRANULAR SUBDRAIN EACH250.00011,677.50
100.0004,671.00
0.0000.00

0085                          9009.86 12.0966,148.000799,729.32
SURFACING 150mm m2 66,148.000799,729.32
23,194.100280,416.67
0.0000.00

0086                          9009.87 17.55257.0004,510.35
SURFACING 200mm m2 257.0004,510.35
526.0709,232.53
0.0000.00

0087                          9030.00 7.05327.0002,305.35
CONSTRUCTING ASPHALTIC CONCRETE CURB m 327.0002,305.35
0.0000.00
0.0000.00

0088                          9034.00 2.554,205.00010,722.75
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 4,205.00010,722.75
1,981.0005,051.55
0.0000.00

0089                          9111.00 3.215,944.00019,080.24
WATER kL 5,944.00019,080.24
1,715.9605,508.23
0.0000.00

0090                          9170.00 152.56573.67787,520.16
EARTH SHOULDER CONSTRUCTION StaM573.67787,520.16
131.74020,098.25
0.0000.00

0091                          9173.20 0.81310,543.000251,539.83
SUBGRADE PREPARATION m2 310,543.000251,539.83
139,070.680112,647.24
0.0000.00

0092                          9179.34 1.97131,624.000259,299.28
COLD MILLING, CLASS 4 m2 0.0000.00
0.0000.00
0.0000.00

0093                          9179.54 1.9655,125.000108,045.00
COLD MILLING, CLASS 4 m2 0.0000.00
A 0.0000.00
0.0000.00

0094                          9185.50 16.77109.0001,827.93
MILLING CONCRETE CURB m 109.0001,827.93
0.0000.00
0.0000.00

0095                          9185.77 132.51457.74060,655.13
RUMBLE STRIPS, CONCRETE StaM457.74060,655.13
183.00024,249.33
0.0000.00

425                           3900.22 19.400.0000.00
ADDITIONAL COST m3 150.0002,910.00
for 8-sack concrete 48.960949.82
48.960949.82

426                           4976.05 2,471.340.0000.00
ADDITIONAL WORK LS 1.0002,471.34
for pipes and fill in 135+ area 1.0002,471.34
0.0000.00

427                           0030.01 1,500.000.0000.00
ADDITIONAL MOBILIZATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

431                           4764.34 28.880.0000.00
100 mm NONPERFORATED PIPE UNDERDRAIN m 7.000202.16
7.000202.16
0.0000.00

432                           4763.38 36.750.0000.00
100 mm RODENT GUARD EACH2.00073.50
2.00073.50
0.0000.00

437                           9179.34 2.620.0000.00
COLD MILLING, CLASS 4 m2 131,624.000344,854.88
Revised 122,317.510320,471.88
0.0000.00

438                           9179.54 2.510.0000.00
COLD MILLING, CLASS 4 m2 55,125.000138,363.75
Revised 57,290.680143,799.61
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted10,402,484.09
Current10,525,515.44
In place6,127,430.42
This Estimate949.82

GROUP 4 CULVERTS
0096                          P129.48 296.94131.00038,899.14
1200 mm CULVERT PIPE, TYPE 2 CLASS V m 70.00020,785.80
70.00020,785.80
0.0000.00

0097                          P150.72 456.524.0001,826.08
1800 mm CULVERT PIPE, TYPE 5 m 4.0001,826.08
4.0001,826.08
0.0000.00

0098                          P200.24 95.95163.00015,639.85
600mm CULVERT PIPE, TYPE 2 OR 5 m 163.00015,639.85
172.40016,541.79
0.0000.00

0099                          P200.30 119.18103.00012,275.54
750 mm CULVERT PIPE, TYPE 2 OR 5 m 103.00012,275.54
103.20012,299.38
0.0000.00

0100                          P200.36 140.3959.0008,283.01
900 mm CULVERT PIPE, TYPE 2 OR 5 m 59.0008,283.01
59.5008,353.21
0.0000.00

0101                          P200.42 180.7952.0009,401.08
1050 mm CULVERT PIPE, TYPE 2 OR 5 m 52.0009,401.08
53.1859,615.32
0.0000.00

0102                          P200.48 214.12118.00025,266.16
1200 mm CULVERT PIPE, TYPE 2 OR 5 m 118.00025,266.16
116.80025,009.22
47.50010,170.70

0103                          P200.60 251.4915.0003,772.35
1500 mm CULVERT PIPE, TYPE 2 OR 5 m 15.0003,772.35
0.0000.00
0.0000.00

0104                          P400.18 303.003.000909.00
450 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 3.000909.00
4.8201,460.46
0.0000.00

0105                          P400.24 95.95102.5009,834.88
600 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 102.5009,834.88
107.00010,266.65
0.0000.00

0106                          P400.30 119.18267.00031,821.06
750 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 267.00031,821.06
210.49025,086.20
0.0000.00

0107                          P400.36 140.39114.50016,074.66
900 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 114.50016,074.66
71.96610,103.30
0.0000.00

0108                          P402.15 55.55109.0006,054.95
375 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 109.0006,054.95
74.0004,110.70
0.0000.00

0109                          P402.24 60.6029.5001,787.70
600 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 29.5001,787.70
31.0001,878.60
0.0000.00

0110                          P600.24 60.6027.0001,636.20
600 mm CULVERT PIPE, TYPE 2,3,4,5,7 OR 8 m 27.0001,636.20
26.5001,605.90
0.0000.00

0111                          0030.40 150,000.001.000150,000.00
MOBILIZATION LS 1.000150,000.00
1.000150,000.00
0.0000.00

0112                          1043.50 1.874,261.0007,968.07
RIPRAP FILTER FABRIC m2 4,261.0007,968.07
3,501.7566,548.28
0.0000.00

0113                          4005.00 2.63308.000810.04
CAST IRON RING AND COVER kg 308.000810.04
0.0000.00
0.0000.00

0114                          4013.00 1,090.801.0001,090.80
TRASH GRATE EACH1.0001,090.80
2.0002,181.60
0.0000.00

0115                          4016.00 18,382.001.00018,382.00
MANHOLE EACH1.00018,382.00
AT STA. 134+55.50 0.0000.00
0.0000.00

0116                          4016.01 11,493.801.00011,493.80
MANHOLE EACH1.00011,493.80
AT STA. 135+06 0.0000.00
0.0000.00

0117                          4035.00 126.2516.0002,020.00
REMOVE FLARED-END SECTION EACH16.0002,020.00
7.000883.75
0.0000.00

0118                          4040.00 151.502.000303.00
REMOVE HEADWALLS FROM CULVERTS EACH2.000303.00
0.0000.00
0.0000.00

0119                          4041.00 3,030.001.0003,030.00
CULVERT CLEANOUT EACH1.0003,030.00
AT STA. 11701+22.0 0.0000.00
0.0000.00

0120                          4043.00 32.32131.0004,233.92
REMOVE CULVERT PIPE m 70.0002,262.40
71.8002,320.57
0.0000.00

0121                          4044.00 1,616.001.0001,616.00
PREPARATION OF STRUCTURE EACH1.0001,616.00
AT STA. 134+65.47 1.0001,616.00
0.0000.00

0122                          4044.01 3,636.001.0003,636.00
PREPARATION OF STRUCTURE EACH1.0003,636.00
AT STA. 145+91.64 1.0003,636.00
0.0000.00

0123                          4044.02 454.501.000454.50
PREPARATION OF STRUCTURE EACH1.000454.50
AT STA. 152+73.88 1.000454.50
0.0000.00

0124                          4044.03 909.001.000909.00
PREPARATION OF STRUCTURE EACH1.000909.00
AT STA. 154+20.22 1.000909.00
0.0000.00

0125                          4044.04 1,616.001.0001,616.00
PREPARATION OF STRUCTURE EACH1.0001,616.00
AT STA. 154+72.34 0.0000.00
0.0000.00

0126                          4044.05 3,636.001.0003,636.00
PREPARATION OF STRUCTURE EACH1.0003,636.00
AT STA. 170+33.18 1.0003,636.00
0.0000.00

0127                          4044.06 1,262.501.0001,262.50
PREPARATION OF STRUCTURE EACH1.0001,262.50
AT STA. 174+92.60 1.0001,262.50
0.0000.00

0128                          4044.07 454.501.000454.50
PREPARATION OF STRUCTURE EACH1.000454.50
AT STA. 176+62.94 1.000454.50
0.0000.00

0129                          4044.08 1,010.001.0001,010.00
PREPARATION OF STRUCTURE EACH1.0001,010.00
AT STA. 221+57.31 1.0001,010.00
0.0000.00

0130                          4044.09 1,010.001.0001,010.00
PREPARATION OF STRUCTURE EACH1.0001,010.00
AT STA. 231+09.59 0.0000.00
0.0000.00

0131                          4044.10 631.251.000631.25
PREPARATION OF STRUCTURE EACH1.000631.25
AT STA. 233+37.95 1.000631.25
0.0000.00

0132                          4044.11 631.251.000631.25
PREPARATION OF STRUCTURE EACH1.000631.25
AT STA. 247+02.75 1.000631.25
0.0000.00

0133                          4044.12 1,262.501.0001,262.50
PREPARATION OF STRUCTURE EACH1.0001,262.50
AT STA. 250+58.69 1.0001,262.50
0.0000.00

0134                          4045.00 7,070.001.0007,070.00
REMOVE STRUCTURE EACH1.0007,070.00
AT STA. 125+58.18 LT. 1.0007,070.00
0.0000.00

0135                          4045.01 6,060.001.0006,060.00
REMOVE STRUCTURE EACH1.0006,060.00
AT STA. 131+20.00 LT. 1.0006,060.00
0.0000.00

0136                          4045.02 3,838.001.0003,838.00
REMOVE STRUCTURE EACH1.0003,838.00
AT STA. 138+56.64 LT. 1.0003,838.00
0.0000.00

0137                          4045.03 2,525.001.0002,525.00
REMOVE STRUCTURE EACH1.0002,525.00
AT STA. 141+24.80 LT. 1.0002,525.00
0.0000.00

0138                          4045.04 1,818.001.0001,818.00
REMOVE STRUCTURE EACH1.0001,818.00
AT STA. 144+03.80 0.0000.00
0.0000.00

0139                          4045.05 12,120.001.00012,120.00
REMOVE STRUCTURE EACH1.00012,120.00
AT STA. 154+72.34 1.00012,120.00
0.0000.00

0140                          4045.06 5,656.001.0005,656.00
REMOVE STRUCTURE EACH1.0005,656.00
AT STA. 163+65.40 1.0005,656.00
0.0000.00

0141                          4045.07 7,070.001.0007,070.00
REMOVE STRUCTURE EACH1.0007,070.00
AT STA. 168+27.40 LT. 1.0007,070.00
0.0000.00

0142                          4045.08 2,525.001.0002,525.00
REMOVE STRUCTURE EACH1.0002,525.00
AT STA. 194+78.76 0.5001,262.50
0.0000.00

0143                          4045.09 4,545.001.0004,545.00
REMOVE STRUCTURE EACH1.0004,545.00
AT STA. 196+75.68 1.0004,545.00
0.0000.00

0144                          4045.10 1,818.001.0001,818.00
REMOVE STRUCTURE EACH1.0001,818.00
AT STA. 201+25.36 LT. 1.0001,818.00
0.0000.00

0145                          4045.11 3,838.001.0003,838.00
REMOVE STRUCTURE EACH1.0003,838.00
AT STA. 205+28.98 LT. 0.0000.00
0.0000.00

0146                          4045.12 8,736.501.0008,736.50
REMOVE STRUCTURE EACH1.0008,736.50
AT STA. 210+38.71 LT. 0.0000.00
0.0000.00

0147                          4045.13 5,555.001.0005,555.00
REMOVE STRUCTURE EACH1.0005,555.00
AT STA. 215+71.59 1.0005,555.00
1.0005,555.00

0148                          4045.14 17,170.001.00017,170.00
REMOVE STRUCTURE EACH1.00017,170.00
AT STA. 219+48.81 LT. 0.3005,151.00
0.0000.00

0149                          4045.15 6,565.001.0006,565.00
REMOVE STRUCTURE EACH1.0006,565.00
AT STA. 227+61.00 0.0000.00
0.0000.00

0150                          4045.16 3,030.001.0003,030.00
REMOVE STRUCTURE EACH1.0003,030.00
AT STA. 239+31.58 LT. 1.0003,030.00
0.0000.00

0151                          4045.17 4,040.001.0004,040.00
REMOVE STRUCTURE EACH1.0004,040.00
AT STA. 242+05.25 LT. 1.0004,040.00
1.0004,040.00

0152                          4045.18 1,868.501.0001,868.50
REMOVE STRUCTURE EACH1.0001,868.50
AT STA. 243+49.72 LT. 1.0001,868.50
0.0000.00

0153                          4045.19 3,838.001.0003,838.00
REMOVE STRUCTURE EACH1.0003,838.00
AT STA. 244+65.81 LT. 0.3571,370.17
0.0000.00

0154                          4045.20 1,010.001.0001,010.00
REMOVE STRUCTURE EACH1.0001,010.00
AT STA. 249+12.37 LT. 1.0001,010.00
0.0000.00

0155                          4045.21 3,030.001.0003,030.00
REMOVE STRUCTURE EACH1.0003,030.00
AT STA. 11500+01.14 1.0003,030.00
0.0000.00

0156                          4050.01 8.086,728.00054,362.24
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 4,601.00037,176.08
3,381.14627,319.66
593.5004,795.48

0157                          4051.01 12.1213,147.000159,341.64
EXCAVATION FOR BOX CULVERTS m3 10,824.000131,186.88
10,528.506127,605.50
1,060.66412,855.25

0158                          4054.60 1,727.1020.00034,542.00
TEMPORARY SHORING m 0.0000.00
0.0000.00
0.0000.00

0159                          4101.06 307.042,725.880836,954.20
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 2,605.680800,047.99
2,466.077757,184.27
0.0000.00

0160                          4105.59 757.504.6003,484.50
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 4.6003,484.50
4.6003,484.51
0.0000.00

0161                          4107.07 626.2012.1407,602.07
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 15.0009,393.00
12.3007,702.25
0.0000.00

0162                          4151.00 1.21170,362.000206,138.02
REINFORCING STEEL FOR BOX CULVERT kg 164,947.900199,586.96
151,552.198183,378.16
0.0000.00

0163                          4155.50 2.22170.000377.40
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 170.000377.40
170.000377.40
0.0000.00

0164                          4157.00 2.5322.00055.66
REINFORCING STEEL FOR COLLARS kg 88.000222.64
133.000336.49
0.0000.00

0165                          4310.15 151.5010.0001,515.00
375 mm FLARED-END SECTION EACH10.0001,515.00
6.000909.00
0.0000.00

0166                          4310.24 202.0020.0004,040.00
600 mm FLARED-END SECTION EACH20.0004,040.00
20.0004,040.00
0.0000.00

0167                          4310.30 292.909.0002,636.10
750 mm FLARED-END SECTION EACH9.0002,636.10
8.0002,343.20
0.0000.00

0168                          4310.36 353.508.0002,828.00
900 mm FLARED-END SECTION EACH8.0002,828.00
6.0002,121.00
0.0000.00

0169                          4310.42 626.203.0001,878.60
1050 mm FLARED-END SECTION EACH3.0001,878.60
3.0001,878.60
0.0000.00

0170                          4310.48 676.706.0004,060.20
1200 mm FLARED-END SECTION EACH6.0004,060.20
6.0004,060.20
1.000676.70

0171                          4310.72 1,212.002.0002,424.00
1800 mm FLARED-END SECTION EACH2.0002,424.00
2.0002,424.00
0.0000.00

0172                          4670.05 106.0564.0006,787.20
CULVERT SANDFILL m3 64.0006,787.20
65.0006,893.25
0.0000.00

0173                          4885.48 836.28122.000102,026.16
JACKING 1200 mm CULVERT PIPE, TYPE 2 CLASS V m 61.00051,013.08
70.00058,539.60
0.0000.00

0174                          6105.01 35.15277.0009,736.55
ROCK RIPRAP, TYPE A Mg 277.0009,736.55
176.3526,198.78
0.0000.00

0175                          6105.02 35.152,825.00099,298.75
ROCK RIPRAP, TYPE B Mg 2,825.00099,298.75
2,702.05094,977.06
0.0000.00

0176                          6105.03 38.38565.00021,684.70
ROCK RIPRAP, TYPE C Mg 565.00021,684.70
583.48822,394.27
0.0000.00

402                           6990.01 2,600.850.0000.00
MODIFY LS 1.0002,600.85
Box Culvert at Sta 134+65.47 1.0002,600.85
0.0000.00

408                           4850.60 1,997.100.0000.00
JACKING 1500 mm CULVERT PIPE, TYPE m 61.000121,823.10
Galvanized Steel (Supplied) 61.000121,823.10
0.0000.00

409                           A970.00 3,175.200.0000.00
ENGINEERING EACH1.0003,175.20
for design of Temp Shoring 1.0003,175.20
0.0000.00

410                           0025.10 33,740.960.0000.00
VALUE ENGINEERING ADJUSTMENT LS 1.00033,740.96
1.00033,740.96
0.0000.00

416                           0096.00 -1,346.090.0000.00
DEDUCTION LS 1.000-1,346.09
For drainage work by State forces 0.0000.00
0.0000.00

428                           3900.20 1,328.250.0000.00
ADDITIONAL COST LS 1.0001,328.25
mobilization and freight at 154+80 1.0001,328.25
0.0000.00

429                           P120.60 672.000.0000.00
1500 mm CULVERT PIPE, TYPE 2 m 9.7506,552.00
9.7506,552.00
0.0000.00

434                           4300.84 577.500.0000.00
2100 mm CULVERT PIPE m 15.5008,951.25
14.9208,616.30
0.0000.00

435                           4310.84 1,548.750.0000.00
2100 mm FLARED END SECTION EACH2.0003,097.50
2.0003,097.50
0.0000.00

440                           P120.48 -29.530.0000.00
1200 mm CULVERT PIPE, TYPE 2 m 70.000-2,067.10
sold to contractor 0.0000.00
0.0000.00

601                           4051.12 30.700.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 100.0003,070.00
771.15623,674.49
0.0000.00

602                           4050.10 30.700.0000.00
GRANULAR BACKFILL FOR PIPE AND PIPE-ARCH CULVERT m3 100.0003,070.00
135.6304,163.84
0.0000.00

GROUP 4 CULVERTSContracted2,076,441.76
Current2,067,957.47
In place1,926,339.17
This Estimate38,093.13

GROUP 4A CONCRETE BOX CULVERT AT STA. 187+25.74
0177                          0030.40 50,000.001.00050,000.00
MOBILIZATION LS 1.00050,000.00
0.98749,350.00
0.0000.00

0178                          4045.00 12,871.331.00012,871.33
REMOVE STRUCTURE EACH1.00012,871.33
AT STA. 187+22.55 LT. 1.00012,871.33
0.0000.00

0179                          4051.01 9.971,909.00019,032.73
EXCAVATION FOR BOX CULVERTS m3 1,909.00019,032.73
2,076.37420,701.45
0.0000.00

0180                          4101.06 254.131,269.550322,630.74
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 1,269.550322,630.74
1,134.791288,384.43
0.0000.00

0181                          4151.00 1.3665,482.00089,055.52
REINFORCING STEEL FOR BOX CULVERT kg 65,482.00089,055.52
58,509.14179,572.44
0.0000.00

604                           4051.12 25.410.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 200.0005,082.00
271.8746,908.31
0.0000.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 187+25.74Contracted493,590.32
Current498,672.32
In place457,787.96
This Estimate0.00

GROUP 5 SEEDING
0182                          L001.01 1,696.8061.500104,353.20
SEEDING, TYPE A ha 61.500104,353.20
25.50743,280.28
0.0000.00

0183                          L001.02 999.9023.50023,497.65
SEEDING, TYPE B ha 23.50023,497.65
4.2894,288.58
0.0000.00

0184                          L010.00 6.06184.0001,115.04
SODDING m2 184.0001,115.04
0.0000.00
0.0000.00

0185                          L020.03 1.8269,727.000126,903.14
EROSION CONTROL, TYPE C m2 69,727.000126,903.14
0.0000.00
0.0000.00

0186                          L020.10 1.3436,607.00049,053.38
EROSION CONTROL, TYPE HV m2 36,607.00049,053.38
0.0000.00
0.0000.00

0187                          L032.75 70.70383.00027,078.10
MULCH Mg 383.00027,078.10
133.2459,420.43
0.0000.00

0188                          0030.50 1,000.001.0001,000.00
MOBILIZATION LS 1.0001,000.00
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted333,000.51
Current333,000.51
In place56,989.29
This Estimate0.00

GROUP 8B ELECTRICAL
0189                          A001.12 303.004.0001,212.00
PULL BOX, TYPE PB-5 EACH4.0001,212.00
0.0000.00
0.0000.00

0190                          A009.14 1,641.258.00013,130.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 EACH8.00013,130.00
0.0000.00
0.0000.00

0191                          A020.10 909.001.000909.00
LIGHTING CONTROL CENTER, TYPE D EACH1.000909.00
0.0000.00
0.0000.00

0192                          A020.30 1,515.001.0001,515.00
LIGHTING CONTROL CENTER, TYPE R EACH1.0001,515.00
0.0000.00
0.0000.00

0193                          A070.10 6.06170.0001,030.20
38 mm CONDUIT IN TRENCH m 170.0001,030.20
0.0000.00
0.0000.00

0194                          A074.12 40.40150.0006,060.00
38 mm CONDUIT, JACKED m 150.0006,060.00
0.0000.00
0.0000.00

0195                          A080.22 1.01320.000323.20
STREET LIGHTING CABLE, NO. 6 BARE m 320.000323.20
0.0000.00
0.0000.00

0196                          A080.24 2.02640.0001,292.80
STREET LIGHTING CABLE, NO. 6 USE m 640.0001,292.80
0.0000.00
0.0000.00

0197                          0030.81 1,010.001.0001,010.00
MOBILIZATION LS 1.0001,010.00
0.0000.00
0.0000.00

GROUP 8B ELECTRICALContracted26,482.20
Current26,482.20
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0198                          0001.08 0.5096,565.00048,282.50
BARRICADE, TYPE II BDAY96,565.00048,282.50
35,465.50017,732.75
1,277.500638.75

0199                          0001.10 0.20131,412.00026,282.40
BARRICADE, TYPE III BDAY131,412.00026,282.40
13,029.0002,605.80
338.00067.60

0200                          0001.30 0.304,527.0001,358.10
TYPE B HIGH INTENSITY WARNING LIGHT LDAY4,527.0001,358.10
690.000207.00
0.0000.00

0201                          0001.75 10.1072.000727.20
TEMPORARY SIGN DAY EACH72.000727.20
0.0000.00
0.0000.00

0202                          0001.90 0.15139,544.00020,931.60
SIGN DAY EACH139,544.00020,931.60
26,634.0003,995.10
665.00099.75

0203                          0002.97 10.101,195.00012,069.50
FLASHING ARROW PANEL DAY 1,195.00012,069.50
162.0001,636.20
7.00070.70

0204                          0003.10 181.80220.00039,996.00
FLAGGING DAY 220.00039,996.00
158.00028,724.40
0.0000.00

0205                          0003.35 1,212.006.0007,272.00
MOBILE TRAFFIC CONTROL OPERATION DAY 6.0007,272.00
0.0000.00
0.0000.00

0206                          0003.51 24.72405.00010,011.60
INSTALL CONCRETE PROTECTION BARRIER m 405.00010,011.60
0.0000.00
0.0000.00

0207                          0010.04 5,311.351.0005,311.35
FIELD OFFICE EACH1.0005,311.35
0.0000.00
0.0000.00

0208                          0030.00 20,000.001.00020,000.00
MOBILIZATION LS 1.00020,000.00
0.96019,200.00
0.0000.00

403                           1020.10 50.560.0000.00
DELINEATOR UNIT EACH50.0002,528.00
installation, maintenance, and removal 133.0006,724.48
0.0000.00

424                           0002.30 4.660.0000.00
PAVEMENT MARKING REMOVAL m 250.0001,165.00
852.8003,974.05
0.0000.00

GROUP 10 GENERAL ITEMSContracted192,242.25
Current195,935.25
In place84,799.78
This Estimate876.80

Totals for contractContracted18,274,985.53
Current18,519,172.08
In place12,452,057.88
This Estimate90,356.21