Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2817 MCC, L.L.C.
Contract ID:2929
Estimate Number:0014
Pay Period End Date:05.25.2002
Contract Location:
CAPEHART BRIDGEEstimate Type:PROG
Contractor:
MCC, L.L.C.Date Let:08.16.2001
6615 S 156TH STDate Awarded:08.29.2001
Date Contract Executed:09.07.2001
Date Notice to Proceed:09.07.2001
OMAHA NE 68135-2407Date Work Began:09.24.2001
Phone:Date Physical Work Completed:
(402)896-6790Date Accepted:
Escrow Agent:
Surety Co:
TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA
Counties
SARPY
Project Number PCT Fed State Project Number Description
21929 000  0.000 EACIM-80-9(811)  GRAD CULV BR GDRL BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$899,333.60$849,594.96$49,738.64
$908,154.45Stockpiled Materials$.00$815.55$-815.55
Original Contract AmtGross Earnings$899,333.60$850,410.51$48,923.09
$886,338.99Retainage$-8,993.34$-8,495.95$-497.39
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
99.03%Net Earnings$890,340.26$841,914.56$48,425.70
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-46.92$-46.92$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$46.92-$46.92$.00
Payment$890,293.34$841,867.64$48,425.70
Project ManagerDiv. Head/Dist. Eng.
Fox, Mike05.28.2002Lech, Marvin (Marv)05.28.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve05.28.2002
Controller Div. Processed
Burling, Laurie05.28.2002
Detailed breakdown of stockpiled materials
Est Nbr:0001
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00426131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment5,465.75ci100471
epoxy coated re-steel
Total for estimate 0001:5,465.75
Est Nbr:0003
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00426131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-3,528.00ci100471
epoxy coated re-steel
Total for estimate 0003:-3,528.00
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00426131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-1,934.52ci100471
epoxy coated re-steel
Total for estimate 0006:-1,934.52
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00426131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-3.23ci100471
epoxy coated re-steel
Total for estimate 0007:-3.23
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00426131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment12,697.56CI105395
EPOXY COATED RE-STEEL
Total for estimate 0008:12,697.56
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00293051.10 EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES
S.P. Initial Payment4,055.12ci106130
epoxy coated steel for pvmt.approach
Total for estimate 0009:4,055.12
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00293051.10 EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES
S.P. Adjustment-3,316.76ci106130
epoxy coated steel for pvmt.approach
00426131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-9,599.10CI105395
EPOXY COATED RE-STEEL
Total for estimate 0011:-12,915.86
Est Nbr:0012
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00426131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-1,862.49CI105395
EPOXY COATED RE-STEEL
Total for estimate 0012:-1,862.49
Est Nbr:0013
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00293051.10 EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES
S.P. Adjustment-738.36ci106130
epoxy coated steel for pvmt.approach
00426131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-420.42CI105395
EPOXY COATED RE-STEEL
Total for estimate 0013:-1,158.78
Est Nbr:0014
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00426131.50 EPOXY COATED REINFORCING STEEL
S.P. Closure-815.55CI105395
EPOXY COATED RE-STEEL
Total for estimate 0014:-815.55
Total remaining for contract:-0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L020.00 1.3114,400.00018,864.00
EROSION CONTROL SY 14,400.00018,864.00
18,220.60023,868.99
18,220.60023,868.99

0002                          L022.11 2.002,837.0005,674.00
FABRIC SILT FENCE-LOW POROSITY LF 2,837.0005,674.00
0.0000.00
0.0000.00

0003                          0030.10 7,500.001.0007,500.00
MOBILIZATION LS 1.0007,500.00
1.0007,500.00
0.0000.00

0004                          1000.00 300.002.000600.00
LARGE TREE REMOVAL EACH2.000600.00
2.000600.00
0.0000.00

0005                          1009.00 1,260.001.0001,260.00
GENERAL CLEARING AND GRUBBING LS 1.0001,260.00
1.0001,260.00
0.0000.00

0006                          1011.00 3.00110.000330.00
WATER MGAL110.000330.00
0.0000.00
0.0000.00

0007                          1012.00 73.5010.000735.00
RIGHT-OF-WAY MARKERS EACH10.000735.00
0.0000.00
0.0000.00

0008                          1030.00 4.8511,087.00053,771.95
EARTHWORK MEASURED IN EMBANKMENT CY 11,087.00053,771.95
11,087.00053,771.95
0.0000.00

0009                          1102.00 3.151,111.0003,499.65
REMOVE ASPHALT SURFACE SY 1,111.0003,499.65
1,111.0003,499.65
0.0000.00

0010                          7017.00 1.501,612.5002,418.75
REMOVE GUARDRAIL LF 1,612.5002,418.75
1,612.5002,418.75
0.0000.00

GROUP 1 GRADINGContracted94,653.35
Current94,653.35
In place92,919.34
This Estimate23,868.99

GROUP 1A MSE WALL
0011                          0030.10 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0012                          4095.00 17.853,877.00069,204.45
CONCRETE FACE PANELS SF 3,877.00069,204.45
3,877.00069,204.45
0.0000.00

0013                          4095.10 23.00306.0007,038.00
CONCRETE LEVELING PADS LF 306.0007,038.00
306.0007,038.00
0.0000.00

0014                          4095.20 60.00314.00018,840.00
COPING LF 314.00018,840.00
314.00018,840.00
0.0000.00

0015                          4350.24 12.25374.0004,581.50
24" CORRUGATED METAL PIPE LF 374.0004,581.50
374.0004,581.50
0.0000.00

0016                          8024.75 20.502,873.00058,896.50
SELECT GRANULAR BACKFILL FOR MSE WALL CY 2,873.00058,896.50
2,873.00058,896.50
0.0000.00

GROUP 1A MSE WALLContracted161,060.45
Current161,060.45
In place161,060.45
This Estimate0.00

GROUP 4 CULVERT
0017                          P402.18 26.00118.0003,068.00
18" CULVERT PIPE, TYPE 3,4,5 OR 6 LF 118.0003,068.00
118.0003,068.00
0.0000.00

0018                          0030.40 1,500.001.0001,500.00
MOBILIZATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0019                          4040.00 50.004.000200.00
REMOVE HEADWALLS FROM CULVERTS EACH4.000200.00
4.000200.00
0.0000.00

0020                          4043.50 10.0096.000960.00
REMOVE SEWER PIPE LF 96.000960.00
0.0000.00
0.0000.00

0021                          4050.01 2.50513.0001,282.50
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS CY 513.0001,282.50
513.0001,282.50
0.0000.00

0022                          4105.59 450.007.2003,240.00
CLASS 47B-3000 CONCRETE FOR INLET AND JUNCTION BOX CY 7.2003,240.00
7.2003,240.00
0.0000.00

0023                          4107.07 700.001.080756.00
CLASS 47B-3000 OR AX-3000 CONCRETE FOR CONCRETE COLLARS CY 1.080756.00
0.0000.00
0.0000.00

0024                          4155.50 1.00464.000464.00
REINFORCING STEEL FOR INLET AND JUNCTION BOX LB 464.000464.00
464.000464.00
0.0000.00

0025                          4157.00 1.0086.00086.00
REINFORCING STEEL FOR COLLARS LB 86.00086.00
0.0000.00
0.0000.00

0026                          4600.18 40.00114.0004,560.00
18" REINFORCED CONCRETE SEWER PIPE LF 114.0004,560.00
0.0000.00
0.0000.00

GROUP 4 CULVERTContracted16,116.50
Current16,116.50
In place9,754.50
This Estimate0.00

GROUP 6 BRIDGE AT STA. 103+08.12
0027                          0030.60 47,500.001.00047,500.00
MOBILIZATION LS 1.00047,500.00
1.00047,500.00
0.0000.00

0028                          3050.16 195.00128.30025,018.50
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-5000 CY 128.30025,018.50
128.30025,018.50
0.0000.00

0029                          3051.10 0.6014,840.0008,904.00
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES LB 14,840.0008,904.00
14,840.0008,904.00
0.0000.00

0030                          6000.10 2,600.001.0002,600.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,600.00
1.0002,600.00
0.0000.00

0031                          6000.11 2,600.001.0002,600.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,600.00
1.0002,600.00
0.0000.00

0032                          6000.20 7,000.001.0007,000.00
PIER NO.1 EXCAVATION LS 1.0007,000.00
1.0007,000.00
0.0000.00

0033                          6005.35 41.0062.7002,570.70
PRECOMPRESSED POLYURETHANE FOAM JOINT LF 62.7002,570.70
62.7002,570.70
0.0000.00

0034                          6005.78 555.008.0004,440.00
EXPANSION BEARING, TFE TYPE EACH8.0004,440.00
8.0004,440.00
0.0000.00

0035                          6005.83 92.008.000736.00
FIXED BEARING EACH8.000736.00
8.000736.00
0.0000.00

0036                          6010.22 340.00147.60050,184.00
CLASS 47B-3000 CONCRETE FOR BRIDGE CY 147.60050,184.00
147.60050,184.00
0.0000.00

0037                          6010.28 295.00250.50073,897.50
CLASS 47BD-5000 CONCRETE FOR BRIDGE CY 250.50073,897.50
250.50073,897.50
0.0000.00

0038                          6011.11 124,000.001.000124,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.000124,000.00
AT STA. 103+08.12 1.000124,000.00
0.0000.00

0039                          6040.00 35,000.001.00035,000.00
REMOVE STRUCTURE EACH1.00035,000.00
AT STA. 103+02.12 1.00035,000.00
0.0000.00

0040                          6080.00 1.05405.000425.25
STRUCTURAL STEEL FOR SUBSTRUCTURE LB 405.000425.25
405.000425.25
0.0000.00

0041                          6095.00 535.006.0003,210.00
STEEL DIAPHRAGM EACH6.0003,210.00
6.0003,210.00
0.0000.00

0042                          6131.50 0.6561,685.00040,095.25
EPOXY COATED REINFORCING STEEL LB 61,685.00040,095.25
63,995.00041,596.75
0.0000.00

0043                          6139.50 20.0054.5001,090.00
SUBSURFACE DRAINAGE MATTING SY 54.5001,090.00
54.5001,090.00
0.0000.00

0044                          6210.12 13.00960.00012,480.00
HP 10"X42# STEEL PILING LF 960.00012,480.00
940.00012,220.00
0.0000.00

0045                          6210.14 15.301,555.00023,791.50
HP 12"X53# STEEL PILING LF 1,555.00023,791.50
1,520.00023,256.00
0.0000.00

0046                          6251.00 3,000.003.0009,000.00
TEST PILE EACH3.0009,000.00
3.0009,000.00
0.0000.00

0047                          8091.00 13.50218.4002,948.40
GRANULAR BACKFILL CY 218.4002,948.40
218.4002,948.40
0.0000.00

GROUP 6 BRIDGE AT STA. 103+08.12Contracted477,491.10
Current477,491.10
In place478,197.10
This Estimate0.00

GROUP 7 GUARDRAIL
0069                          0003.58 3,360.002.0006,720.00
INERTIAL BARRIER SYSTEM EACH2.0006,720.00
2.0006,720.00
0.0000.00

0070                          0030.70 0.011.0000.01
MOBILIZATION LS 1.0000.01
1.0000.01
1.0000.01

0071                          7011.20 14.00312.5004,375.00
W-BEAM GUARDRAIL LF 312.5004,375.00
312.5004,375.00
312.5004,375.00

0072                          7020.00 1,200.004.0004,800.00
BRIDGE APPROACH SECTIONS EACH4.0004,800.00
4.0004,800.00
4.0004,800.00

0073                          7021.58 1,400.004.0005,600.00
GUARDRAIL END TREATMENT, SRT-75 EACH4.0005,600.00
4.0005,600.00
4.0005,600.00

4006                          7150.00 7.210.0000.00
REMOVE AND RESET R.O.W. FENCE LF 790.0005,695.90
Remove and Re-Set ROW Fence 800.0005,768.00
800.0005,768.00

GROUP 7 GUARDRAILContracted21,495.01
Current27,190.91
In place27,263.01
This Estimate20,543.01

GROUP 9 BITUMINOUS
0074                          0030.90 0.011.0000.01
MOBILIZATION LS 1.0000.01
1.0000.01
0.0000.00

0075                          1020.03 18.0088.0001,584.00
DELINEATOR, TYPE III EACH88.0001,584.00
95.0001,710.00
95.0001,710.00

0076                          1020.20 5.2524.000126.00
INSTALL CHEVRONS EACH24.000126.00
24.000126.00
24.000126.00

0077                          2001.03 11.00939.00010,329.00
GRAVEL SURFACE COURSE TON 0.0000.00
0.0000.00
0.0000.00

0078                          2009.10 105.0023.8902,508.45
GRAVEL EMBEDMENT STA 0.0000.00
0.0000.00
0.0000.00

0079                          9009.88 26.001,111.00028,886.00
SURFACING 10" SY 0.0000.00
0.0000.00
0.0000.00

4001                          9005.55 35.350.0000.00
ASPHALTIC CONCRETE, TYPE SP5(0.5) TON 0.0000.00
0.0000.00
0.0000.00

4002                          2010.03 14.770.0000.00
CRUSHED ROCK SURFACE COURSE TON 939.00013,869.03
1,127.00016,645.79
24.000354.48

4003                          2009.51 105.000.0000.00
CRUSHED ROCK EMBEDMENT STA 23.8902,508.45
23.8902,508.45
0.0000.00

4004                          9009.88 35.350.0000.00
SURFACING 10" SY 1,111.00039,273.85
1,111.00039,273.85
0.0000.00

GROUP 9 BITUMINOUSContracted43,433.46
Current57,361.34
In place60,264.10
This Estimate2,190.48

GROUP 10 GENERAL ITEMS
0080                          0001.08 0.502,860.0001,430.00
BARRICADE, TYPE II BDAY2,860.0001,430.00
2,850.0001,425.00
104.00052.00

0081                          0001.10 1.665,030.0008,349.80
BARRICADE, TYPE III BDAY5,030.0008,349.80
8,108.00013,459.28
282.000468.12

0082                          0001.30 1.342,668.0003,575.12
TYPE B HIGH INTENSITY WARNING LIGHT LDAY2,668.0003,575.12
1,944.0002,604.96
104.000139.36

0083                          0001.75 3.151,114.0003,509.10
TEMPORARY SIGN DAY EACH1,114.0003,509.10
740.0002,331.00
24.00075.60

0084                          0001.90 0.199,990.0001,898.10
SIGN DAY EACH9,990.0001,898.10
10,832.0002,058.08
532.000101.08

0085                          0002.30 0.254,500.0001,125.00
PAVEMENT MARKING REMOVAL LF 4,500.0001,125.00
5,000.0001,250.00
0.0000.00

0086                          0002.44 0.135,400.000702.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT LF 5,400.000702.00
6,000.000780.00
0.0000.00

0087                          0002.47 0.112,700.000297.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION LF 2,700.000297.00
2,000.000220.00
0.0000.00

0088                          0002.52 1.60180.000288.00
TEMPORARY PAVEMENT MARKING, TYPE RPM EACH0.0000.00
0.0000.00
0.0000.00

0089                          0002.97 100.0054.0005,400.00
FLASHING ARROW PANEL DAY 54.0005,400.00
107.00010,700.00
4.000400.00

0090                          0003.10 170.0020.0003,400.00
FLAGGING DAY 20.0003,400.00
0.0000.00
0.0000.00

0091                          0003.51 10.001,000.00010,000.00
INSTALL CONCRETE PROTECTION BARRIER LF 1,000.00010,000.00
1,000.00010,000.00
0.0000.00

0092                          0003.56 1.401,000.0001,400.00
RELOCATE CONCRETE PROTECTION BARRIER LF 1,000.0001,400.00
1,000.0001,400.00
0.0000.00

0093                          0003.58 3,360.004.00013,440.00
INERTIAL BARRIER SYSTEM EACH4.00013,440.00
4.00013,440.00
0.0000.00

0094                          0003.64 400.005.0002,000.00
REPLACEMENT MODULE EACH5.0002,000.00
0.0000.00
0.0000.00

0095                          0010.04 5,000.001.0005,000.00
FIELD OFFICE EACH1.0005,000.00
1.0005,000.00
0.0000.00

0096                          0020.00 0.801,000.000800.00
TRAINING HOUR1,000.000800.00
377.500302.00
0.0000.00

0097                          0030.00 525.001.000525.00
MOBILIZATION LS 1.000525.00
1.000525.00
0.0000.00

0098                          7320.60 950.002.0001,900.00
ROUTE MARKER ASSEMBLY EACH2.0001,900.00
2.0001,900.00
2.0001,900.00

0099                          9110.01 90.0030.0002,700.00
RENTAL OF LOADER, FULLY OPERATED HOUR30.0002,700.00
0.0000.00
0.0000.00

0100                          9110.03 55.0030.0001,650.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR30.0001,650.00
0.0000.00
0.0000.00

0101                          9110.07 90.0030.0002,700.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR30.0002,700.00
0.0000.00
0.0000.00

4005                          0002.61 25.830.0000.00
PLOWABLE PAVEMENT MARKER EACH96.0002,479.68
96.0002,479.68
0.0000.00

GROUP 10 GENERAL ITEMSContracted72,089.12
Current74,280.80
In place69,875.00
This Estimate3,136.16

Totals for contractContracted886,338.99
Current908,154.45
In place899,333.50
This Estimate49,738.64