| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 3 CONCRETE PAVEMENT | | |
|
0001 0001.08 | 0.50 | 3,850.000 | 1,925.00
|
BARRICADE, TYPE II | BDAY | 3,850.000 | 1,925.00
|
| | 4,209.000 | 2,104.50
|
| | 661.000 | 330.50
|
| | |
|
0002 0001.10 | 3.00 | 275.000 | 825.00
|
BARRICADE, TYPE III | BDAY | 275.000 | 825.00
|
| | 728.000 | 2,184.00
|
| | 137.000 | 411.00
|
| | |
|
0003 0001.75 | 3.00 | 420.000 | 1,260.00
|
TEMPORARY SIGN DAY | EACH | 420.000 | 1,260.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0004 0001.90 | 0.50 | 1,320.000 | 660.00
|
SIGN DAY | EACH | 1,320.000 | 660.00
|
| | 1,367.000 | 683.50
|
| | 36.000 | 18.00
|
| | |
|
0005 0002.44 | 0.05 | 25,000.000 | 1,250.00
|
TEMPORARY PAVEMENT MARKING, TYPE PAINT | LF | 25,000.000 | 1,250.00
|
| | 9,545.000 | 477.25
|
| | 0.000 | 0.00
|
| | |
|
0006 0002.97 | 100.00 | 35.000 | 3,500.00
|
FLASHING ARROW PANEL | DAY | 35.000 | 3,500.00
|
| | 54.000 | 5,400.00
|
| | 0.000 | 0.00
|
| | |
|
0007 0030.30 | 27,500.00 | 1.000 | 27,500.00
|
MOBILIZATION | LS | 1.000 | 27,500.00
|
| | 1.000 | 27,500.00
|
| | 0.000 | 0.00
|
| | |
|
0008 3008.20 | 8.96 | 495.000 | 4,435.20
|
CROSS STITCHING | EACH | 495.000 | 4,435.20
|
| | 495.000 | 4,435.20
|
| | 0.000 | 0.00
|
| | |
|
0009 3010.43 | 35.00 | 39.000 | 1,365.00
|
CONCRETE CLASS 47B-3625 CURB REPAIR | LF | 39.000 | 1,365.00
|
| | 72.900 | 2,551.50
|
| | 0.000 | 0.00
|
| | |
|
0010 3040.11 | 137.53 | 10.300 | 1,416.56
|
CONCRETE PAVEMENT REPAIR, TYPE A, FULL DEPTH | SY | 10.300 | 1,416.56
|
| | 13.000 | 1,787.89
|
| | 0.000 | 0.00
|
| | |
|
0011 3040.12 | 104.91 | 149.000 | 15,631.59
|
CONCRETE PAVEMENT REPAIR, TYPE B, FULL DEPTH | SY | 149.000 | 15,631.59
|
| | 102.140 | 10,715.51
|
| | 0.000 | 0.00
|
| | |
|
0012 3040.13 | 88.11 | 304.700 | 26,847.12
|
CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH | SY | 304.700 | 26,847.12
|
| | 583.810 | 51,439.50
|
| | 0.000 | 0.00
|
| | |
|
0013 3040.16 | 230.97 | 7.600 | 1,755.37
|
CONCRETE PAVEMENT REPAIR, TYPE B, PARTIAL DEPTH | SY | 7.600 | 1,755.37
|
| | 0.720 | 166.30
|
| | 0.000 | 0.00
|
| | |
|
0014 3040.18 | 230.69 | 71.200 | 16,425.13
|
CONCRETE PAVEMENT REPAIR, TYPE A, PARTIAL DEPTH | SY | 71.200 | 16,425.13
|
| | 106.660 | 24,605.39
|
| | 0.000 | 0.00
|
| | |
|
0015 3210.10 | 2.66 | 27,434.300 | 72,975.24
|
DIAMOND GRINDING AND TEXTURING CONCRETE PAVEMENT | SY | 27,434.300 | 72,975.24
|
| | 27,434.300 | 72,975.24
|
| | 5,486.840 | 14,594.99
|
| | |
|
0016 3211.25 | 2.50 | 607.000 | 1,517.50
|
SEALING CRACKS | LF | 607.000 | 1,517.50
|
| | 783.000 | 1,957.50
|
| | 0.000 | 0.00
|
| | |
|
0017 3211.30 | 0.80 | 45,539.000 | 36,431.20
|
SEALING JOINTS | LF | 45,539.000 | 36,431.20
|
| | 47,371.000 | 37,896.80
|
| | 0.000 | 0.00
|
| | |
|
0018 3221.05 | 107.00 | 58.100 | 6,216.70
|
CONCRETE PAVEMENT, CLASS PR-3625 | SY | 58.100 | 6,216.70
|
JOINT REPAIR | | 111.070 | 11,884.49
|
| | 0.000 | 0.00
|
| | |
|
0019 3300.50 | 3,100.00 | 1.000 | 3,100.00
|
PORTLAND CEMENT CONCRETE SMOOTHNESS TESTING | LS | 1.000 | 3,100.00
|
| | 1.000 | 3,100.00
|
| | 0.000 | 0.00
|
| | |
|
0020 6004.50 | 81.73 | 446.600 | 36,500.62
|
EXPANSION JOINT | LF | 446.600 | 36,500.62
|
| | 446.600 | 36,500.62
|
| | 0.000 | 0.00
|
| | |
|
0021 6030.00 | 3,835.40 | 1.000 | 3,835.40
|
PREPARATION OF BRIDGE | EACH | 1.000 | 3,835.40
|
AT STA. 732+08.45 | | 1.000 | 3,835.40
|
| | 0.000 | 0.00
|
| | |
|
0022 6030.01 | 3,835.40 | 1.000 | 3,835.40
|
PREPARATION OF BRIDGE | EACH | 1.000 | 3,835.40
|
AT STA. 740+67.00 | | 1.000 | 3,835.40
|
| | 0.000 | 0.00
|
| | |
|
0023 7502.14 | 2.25 | 13,500.000 | 30,375.00
|
4" WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED | LF | 13,500.000 | 30,375.00
|
| | 14,565.000 | 32,771.25
|
| | 0.000 | 0.00
|
| | |
|
0024 7503.14 | 2.25 | 10,560.000 | 23,760.00
|
4" YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED | LF | 10,560.000 | 23,760.00
|
| | 11,222.000 | 25,249.50
|
| | 6,521.000 | 14,672.25
|
| | |
|
4001 0003.10 | 225.00 | 0.000 | 0.00
|
FLAGGING | DAY | 14.000 | 3,150.00
|
Flagging | | 16.000 | 3,600.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 3 CONCRETE PAVEMENT | | Contracted | 323,343.02
|
| | Current | 326,493.02
|
| | In place | 367,656.74
|
| | This Estimate | 30,026.74
|
| | |
|
Totals for contract | | Contracted | 323,343.02
|
---|
| | Current | 326,493.02
|
---|
| | In place | 367,656.74
|
---|
| | This Estimate | 30,026.74
|
---|