Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0049 HAWKINS CONSTRUCTION COMPANY
Contract ID:2899
Estimate Number:0001
Pay Period End Date:09.13.2003
Contract Location:
WEST DODGE ROAD 132nd STREET - 120th STREETEstimate Type:PROG
Contractor:
HAWKINS CONSTRUCTION COMPANYDate Let:07.31.2003
2512 DEER PARK BLVDDate Awarded:08.08.2003
PO BOX 9008 STA CDate Contract Executed:08.18.2003
Date Notice to Proceed:08.18.2003
OMAHA NE 68109Date Work Began:09.02.2003
Phone:Date Physical Work Completed:
(402)342-1607Date Accepted:
Escrow Agent:
Surety Co:
ST. PAUL FIRE & MARINE INSURANCE COMPANY
Counties
DOUGLAS
Project Number PCT Fed State Project Number Description
21899 000  0.000 EACNH-6-7(164)  GR CP CULV ELEC SIGN
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$133,348.67$.00$133,348.67
$5,021,822.65Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$133,348.67$.00$133,348.67
$5,021,822.65Retainage$-1,333.49$.00$-1,333.49
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
2.66%Net Earnings$132,015.18$.00$132,015.18
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$1.45$.00$1.45
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$1.45$.00$1.45
Payment$132,016.63$.00$132,016.63
Project ManagerDiv. Head/Dist. Eng.
Zelensky, Rich09.16.2003Lech, Marvin (Marv)09.17.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.17.2003
Controller Div. Processed
Burling, Laurie09.17.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 47,870.001.00047,870.00
MOBILIZATION LS 1.00047,870.00
0.50023,935.00
0.50023,935.00

0002                          1009.00 11,041.001.00011,041.00
GENERAL CLEARING AND GRUBBING LS 1.00011,041.00
0.2002,208.20
0.2002,208.20

0003                          1010.01 7.2317,652.000127,623.96
EXCAVATION (ESTABLISHED QUANTITY) m3 17,652.000127,623.96
765.0005,530.95
765.0005,530.95

0004                          1011.00 2.00728.0001,456.00
WATER kL 728.0001,456.00
0.0000.00
0.0000.00

0005                          1021.10 6.0010.00060.00
REMOVE DELINEATOR UNITS EACH10.00060.00
0.0000.00
0.0000.00

0006                          1101.25 8.201,500.20012,301.64
SAWING PAVEMENT m 1,500.20012,301.64
241.6401,981.45
241.6401,981.45

0007                          1106.00 3.631,859.0006,748.17
REMOVE DRIVEWAY m2 1,859.0006,748.17
0.0000.00
0.0000.00

0008                          1107.00 3.631,268.0004,602.84
REMOVE WALK m2 1,268.0004,602.84
0.0000.00
0.0000.00

0009                          1109.00 18.111,416.00025,643.76
REMOVE CURB m 1,416.00025,643.76
1,416.00025,643.76
1,416.00025,643.76

0010                          1109.20 36.43113.1004,120.23
REMOVE CONCRETE BARRIER m 113.1004,120.23
92.1003,355.20
92.1003,355.20

0011                          1111.00 8.83502.5004,437.08
REMOVE FENCE m 502.5004,437.08
0.0000.00
0.0000.00

0012                          1114.10 22.08120.0002,649.60
REMOVE RETAINING WALL m 120.0002,649.60
0.0000.00
0.0000.00

0013                          1122.01 3.631,600.0005,808.00
REMOVE CONCRETE MEDIAN SURFACING m2 1,600.0005,808.00
1,495.2205,427.65
1,495.2205,427.65

0014                          1124.00 13,249.001.00013,249.00
REMOVE BUILDING EACH1.00013,249.00
AT STA. 520+41 LT. 0.0000.00
0.0000.00

0015                          1125.00 8,833.001.0008,833.00
CLEAR TRACT EACH1.0008,833.00
AT STA. 70+00 TO STA. 70+35 LT. 0.0000.00
0.0000.00

0016                          1136.01 166.002.000332.00
REMOVE EACH2.000332.00
DECORATIVE LIGHT 0.0000.00
0.0000.00

0017                          1136.11 6.6260.000397.20
REMOVE m2 60.000397.20
GROUTED LIMESTONE SLOPE PAVING 0.0000.00
0.0000.00

0018                          3275.20 6.9625,564.000177,925.44
CRUSH CONCRETE PAVEMENT m2 25,564.000177,925.44
5,070.21035,288.66
5,070.21035,288.66

0019                          7308.00 1,104.002.0002,208.00
REMOVE SIGN, STRUCTURE, AND FOUNDATION EACH2.0002,208.00
0.0000.00
0.0000.00

0020                          L020.00 1.665,024.0008,339.84
EROSION CONTROL m2 5,024.0008,339.84
0.0000.00
0.0000.00

0021                          L022.11 6.573,003.20019,731.02
FABRIC SILT FENCE-LOW POROSITY m 3,003.20019,731.02
332.6002,185.18
332.6002,185.18

0022                          L022.12 7.45408.4003,042.58
FABRIC SILT FENCE-HIGH POROSITY m 408.4003,042.58
0.0000.00
0.0000.00

GROUP 1 GRADINGContracted488,420.36
Current488,420.36
In place105,556.05
This Estimate105,556.05

GROUP 3 CONCRETE PAVEMENT
0023                          0030.30 309,005.001.000309,005.00
MOBILIZATION LS 1.000309,005.00
0.05918,231.30
0.05918,231.30

0024                          2021.05 304.002.000608.00
REMOVE AND RESET MAILBOX EACH2.000608.00
0.0000.00
0.0000.00

0025                          3008.05 3.74831.0003,107.94
TIE BARS EACH831.0003,107.94
0.0000.00
0.0000.00

0026                          3013.30 949.001.000949.00
CONCRETE CLASS 47BD-30 BARRIER TRANSITION SECTION EACH1.000949.00
HEIGHT 0.0000.00
0.0000.00

0027                          3013.32 659.002.0001,318.00
CONCRETE CLASS 47BD-30 BARRIER TRANSITION SECTION EACH2.0001,318.00
BARRIER TO CURB 0.0000.00
0.0000.00

0028                          3016.21 21.462,762.00059,272.52
CONCRETE CLASS 47B-20 SIDEWALKS m2 2,762.00059,272.52
0.0000.00
0.0000.00

0029                          3017.43 40.0010.000400.00
150 mm CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 10.000400.00
0.0000.00
0.0000.00

0030                          3017.46 48.02292.00014,021.84
150 mm CONCRETE CLASS 47B-20 IMPRINTED MEDIAN SURFACING m2 292.00014,021.84
0.0000.00
0.0000.00

0031                          3020.26 25.161,349.00033,940.84
CONCRETE CLASS 47B-25 DRIVEWAY m2 1,349.00033,940.84
0.0000.00
0.0000.00

0032                          3026.05 520.001.000520.00
CONCRETE CLASS 47BD-30 BARRIER END SECTION EACH1.000520.00
0.0000.00
0.0000.00

0033                          3027.00 2,672.002.0005,344.00
CONCRETE CLASS 47BD-30 MEDIAN BARRIER TRANSITION SECTION EACH2.0005,344.00
0.0000.00
0.0000.00

0034                          3075.52 29.3821,238.000623,972.44
255 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 21,238.000623,972.44
0.0000.00
0.0000.00

0035                          3075.56 34.4523,384.000805,578.80
255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 23,384.000805,578.80
0.0000.00
0.0000.00

0036                          3089.25 41.993,814.000160,149.86
TEMPORARY SURFACING m2 3,814.000160,149.86
250 mm 0.0000.00
0.0000.00

0037                          4015.00 211.001.000211.00
ADJUST MANHOLE TO GRADE EACH1.000211.00
0.0000.00
0.0000.00

0038                          4764.35 11.242,393.60026,904.06
100 mm PERFORATED PIPE UNDERDRAIN m 2,393.60026,904.06
0.0000.00
0.0000.00

0039                          6010.40 307.83895.410275,634.06
CLASS 47BD-30 CONCRETE FOR BARRIER m3 895.410275,634.06
0.0000.00
0.0000.00

0040                          6131.61 1.24173,826.000215,544.24
EPOXY COATED REINFORCING STEEL FOR BARRIER kg 173,826.000215,544.24
0.0000.00
0.0000.00

0041                          7019.50 20,439.002.00040,878.00
IMPACT ATTENUATOR EACH2.00040,878.00
0.0000.00
0.0000.00

0042                          7019.65 2,465.001.0002,465.00
RELOCATE IMPACT ATTENUATOR EACH1.0002,465.00
0.0000.00
0.0000.00

0043                          7110.05 36.43505.80018,426.29
1.5 METER CHAIN-LINK FENCE m 505.80018,426.29
0.0000.00
0.0000.00

0044                          7115.05 138.004.000552.00
END POST FOR 1.5 METER CHAIN-LINK FENCE EACH4.000552.00
0.0000.00
0.0000.00

0045                          7116.05 166.001.000166.00
CORNER POST FOR 1.5 METER CHAIN-LINK FENCE EACH1.000166.00
0.0000.00
0.0000.00

0046                          7117.05 166.004.000664.00
PULL POST FOR 1.5 METER CHAIN-LINK FENCE EACH4.000664.00
0.0000.00
0.0000.00

0047                          7121.05 883.001.000883.00
7.3 METER VEHICLE GATE FOR 1.5 METER CHAIN-LINK FENCE EACH1.000883.00
0.0000.00
0.0000.00

0048                          7500.32 248.001.000248.00
ARROW, PREFORMED PAVEMENT MARKING, TYPE 4 EACH1.000248.00
0.0000.00
0.0000.00

0049                          7500.38 331.001.000331.00
ONLY, PREFORMED PAVEMENT MARKING, TYPE 4 EACH1.000331.00
0.0000.00
0.0000.00

0050                          7502.14 9.88195.0001,926.60
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 195.0001,926.60
0.0000.00
0.0000.00

0051                          7503.14 9.883,850.00038,038.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 3,850.00038,038.00
0.0000.00
0.0000.00

0052                          8029.10 6.125,000.00030,600.00
AGGREGATE FOUNDATION COURSE-D 100 mm m2 5,000.00030,600.00
0.0000.00
0.0000.00

0053                          8032.04 2.7939,622.000110,545.38
CRUSHED CONCRETE FOUNDATION COURSE 100 mm m2 39,622.000110,545.38
308.720861.33
308.720861.33

0054                          9005.00 87.94100.0008,794.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0008,794.00
SP4(12.5) 0.0000.00
0.0000.00

0055                          9009.88 31.134,092.000127,383.96
SURFACING 250mm m2 4,092.000127,383.96
0.0000.00
0.0000.00

0056                          9031.00 1,994.004.0007,976.00
CONSTRUCTING ASPHALTIC CONCRETE FLUME EACH4.0007,976.00
0.0000.00
0.0000.00

0057                          9111.00 1.59835.0001,327.65
WATER kL 835.0001,327.65
0.0000.00
0.0000.00

0058                          9170.00 1,087.5144.33048,209.32
EARTH SHOULDER CONSTRUCTION StaM44.33048,209.32
0.0000.00
0.0000.00

0059                          9173.20 1.5845,971.00072,634.18
SUBGRADE PREPARATION m2 45,971.00072,634.18
3,459.1905,465.52
3,459.1905,465.52

0060                          L001.02 4,968.310.8003,974.65
SEEDING, TYPE B ha 0.8003,974.65
0.0000.00
0.0000.00

0061                          L010.00 4.399,149.00040,164.11
SODDING m2 9,149.00040,164.11
0.0000.00
0.0000.00

0062                          L032.75 83.004.000332.00
MULCH Mg 4.000332.00
0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted3,093,000.74
Current3,093,000.74
In place24,558.15
This Estimate24,558.15

GROUP 4 CULVERTS
0063                          0030.40 53,851.001.00053,851.00
MOBILIZATION LS 1.00053,851.00
0.0000.00
0.0000.00

0064                          1117.00 244.001.000244.00
REMOVE MANHOLE EACH1.000244.00
0.0000.00
0.0000.00

0065                          1119.00 194.3384.00016,323.72
REMOVE INLET EACH84.00016,323.72
0.0000.00
0.0000.00

0066                          1119.50 180.003.000540.00
REMOVE JUNCTION BOX EACH3.000540.00
0.0000.00
0.0000.00

0067                          4002.00 2.256,198.00013,945.50
CAST IRON COVER AND FRAME kg 6,198.00013,945.50
0.0000.00
0.0000.00

0068                          4004.50 2.257,363.00016,566.75
CAST IRON GRATE AND FRAME kg 7,363.00016,566.75
0.0000.00
0.0000.00

0069                          4005.00 1.68624.0001,048.32
CAST IRON RING AND COVER kg 624.0001,048.32
0.0000.00
0.0000.00

0070                          4015.50 643.004.0002,572.00
RECONSTRUCT MANHOLE EACH4.0002,572.00
0.0000.00
0.0000.00

0071                          4016.00 1,754.001.0001,754.00
MANHOLE EACH1.0001,754.00
AT STA. 68+30.3 RT. 0.0000.00
0.0000.00

0072                          4016.01 2,853.001.0002,853.00
MANHOLE EACH1.0002,853.00
AT STA. 103+09 LT. 0.0000.00
0.0000.00

0073                          4016.02 5,042.001.0005,042.00
MANHOLE EACH1.0005,042.00
AT STA. 512+44.6 LT. 0.0000.00
0.0000.00

0074                          4016.03 1,749.001.0001,749.00
MANHOLE EACH1.0001,749.00
AT STA. 512+48 LT. 0.0000.00
0.0000.00

0075                          4016.04 1,750.001.0001,750.00
MANHOLE EACH1.0001,750.00
AT STA. 513+24.8 RT. 0.0000.00
0.0000.00

0076                          4016.05 1,650.001.0001,650.00
MANHOLE EACH1.0001,650.00
AT STA. 513+56.8 RT. 0.0000.00
0.0000.00

0077                          4016.06 1,679.001.0001,679.00
MANHOLE EACH1.0001,679.00
AT STA. 514+17.4 RT. 0.0000.00
0.0000.00

0078                          4016.07 1,601.001.0001,601.00
MANHOLE EACH1.0001,601.00
AT STA. 514+41.3 RT. 0.0000.00
0.0000.00

0079                          4016.08 1,854.001.0001,854.00
MANHOLE EACH1.0001,854.00
AT STA. 515+00.9 RT. 0.0000.00
0.0000.00

0080                          4016.09 1,615.001.0001,615.00
MANHOLE EACH1.0001,615.00
AT STA. 518+54.7 RT. 0.0000.00
0.0000.00

0081                          4016.10 4,577.001.0004,577.00
MANHOLE EACH1.0004,577.00
AT STA. 522+89.8 LT. 0.0000.00
0.0000.00

0082                          4016.11 1,732.001.0001,732.00
MANHOLE EACH1.0001,732.00
AT STA. 523+69.1 RT. 0.0000.00
0.0000.00

0083                          4016.12 1,440.001.0001,440.00
MANHOLE EACH1.0001,440.00
AT STA. 523+99.6 RT. 0.0000.00
0.0000.00

0084                          4016.13 1,878.001.0001,878.00
MANHOLE EACH1.0001,878.00
AT STA. 611+29.8 LT. 0.0000.00
0.0000.00

0085                          4017.00 290.008.0002,320.00
TAPPING EXISTING MANHOLE EACH8.0002,320.00
0.0000.00
0.0000.00

0086                          4018.00 264.007.0001,848.00
TAPPING EXISTING STRUCTURE EACH7.0001,848.00
0.0000.00
0.0000.00

0087                          4020.25 46.1064.1002,955.01
CONCRETE DITCH LINING m2 64.1002,955.01
100 mm 0.0000.00
0.0000.00

0088                          4035.00 53.005.000265.00
REMOVE FLARED-END SECTION EACH5.000265.00
0.0000.00
0.0000.00

0089                          4043.50 28.591,263.70036,129.18
REMOVE SEWER PIPE m 1,263.70036,129.18
0.0000.00
0.0000.00

0090                          4054.68 31,915.001.00031,915.00
TEMPORARY SHORING LS 1.00031,915.00
0.0000.00
0.0000.00

0091                          4093.80 126.6817.4002,204.23
WALL MATERIALS m2 17.4002,204.23
0.0000.00
0.0000.00

0092                          4095.15 13.8720.000277.40
COMPACTED EARTH LEVELING PAD m 20.000277.40
0.0000.00
0.0000.00

0093                          4102.03 440.02264.300116,297.29
CLASS 47B-20 CONCRETE FOR RETAINING WALL m3 264.300116,297.29
0.0000.00
0.0000.00

0094                          4105.59 512.44219.160112,306.35
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 219.160112,306.35
0.0000.00
0.0000.00

0095                          4107.07 712.006.3404,514.08
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 6.3404,514.08
0.0000.00
0.0000.00

0096                          4152.20 1.4521,349.00030,956.05
EPOXY COATED REINFORCING STEEL FOR RETAINING WALL kg 21,349.00030,956.05
0.0000.00
0.0000.00

0097                          4155.50 0.5711,485.0006,546.45
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 11,485.0006,546.45
0.0000.00
0.0000.00

0098                          4157.00 0.57332.000189.24
REINFORCING STEEL FOR COLLARS kg 332.000189.24
0.0000.00
0.0000.00

0099                          4670.05 259.002.040528.36
CULVERT SANDFILL m3 2.040528.36
0.0000.00
0.0000.00

0100                          4852.18 408.4531.50012,866.18
JACKING 450 mm STORM SEWER PIPE, TYPE m 31.50012,866.18
1 CLASS IV 0.0000.00
0.0000.00

0101                          4852.24 457.4675.00034,309.50
JACKING 600 mm STORM SEWER PIPE, TYPE m 75.00034,309.50
1 CLASS IV 0.0000.00
0.0000.00

0102                          4900.24 696.002.0001,392.00
AREA INLET SEDIMENT FILTER EACH2.0001,392.00
0.0000.00
0.0000.00

0103                          6131.22 42.78130.0005,561.40
SURFACE COATING m2 130.0005,561.40
0.0000.00
0.0000.00

0104                          6133.15 9.38130.0001,219.40
ANTI-GRAFFITI COATING m2 130.0001,219.40
0.0000.00
0.0000.00

0105                          6139.50 13.04372.3004,854.79
SUBSURFACE DRAINAGE MATTING m2 372.3004,854.79
0.0000.00
0.0000.00

0106                          6404.00 149.0565.0009,688.25
PEDESTRIAN RAILING (CHAIN LINK TYPE) m 65.0009,688.25
0.0000.00
0.0000.00

0107                          8024.50 18.53955.10017,698.00
SELECT GRANULAR BACKFILL FOR RETAINED EARTH STRUCTURE m3 955.10017,698.00
0.0000.00
0.0000.00

0108                          P702.15 79.85242.40019,355.64
375 mm STORM SEWER PIPE, TYPE 1 m 242.40019,355.64
0.0000.00
0.0000.00

0109                          P702.18 73.36871.90063,962.58
450 mm STORM SEWER PIPE, TYPE 1 m 871.90063,962.58
0.0000.00
0.0000.00

0110                          P702.24 120.03295.80035,504.87
600 mm STORM SEWER PIPE, TYPE 1 m 295.80035,504.87
0.0000.00
0.0000.00

0111                          P702.30 162.21366.00059,368.86
750 mm STORM SEWER PIPE, TYPE 1 m 366.00059,368.86
0.0000.00
0.0000.00

0112                          P705.18 46.7831.5001,473.57
450 mm STORM SEWER PIPE, TYPE 1 CLASS IV m 31.5001,473.57
0.0000.00
0.0000.00

0113                          P705.24 80.5675.0006,042.00
600 mm STORM SEWER PIPE, TYPE 1 CLASS IV m 75.0006,042.00
0.0000.00
0.0000.00

0114                          W176.70 828.006.0004,968.00
WATER SERVICE CONNECTION EACH6.0004,968.00
0.0000.00
0.0000.00

GROUP 4 CULVERTSContracted763,781.98
Current763,781.98
In place0.00
This Estimate0.00

GROUP 8B ELECTRICAL
0115                          0003.77 39,034.001.00039,034.00
TEMPORARY TRAFFIC SIGNAL EACH1.00039,034.00
AT 132nd STREET & NORTH FRONTAGE ROAD 0.0000.00
0.0000.00

0116                          0030.81 6,691.001.0006,691.00
MOBILIZATION LS 1.0006,691.00
0.0000.00
0.0000.00

0117                          A001.12 351.006.0002,106.00
PULL BOX, TYPE PB-5 EACH6.0002,106.00
0.0000.00
0.0000.00

0118                          A001.16 471.003.0001,413.00
PULL BOX, TYPE PB-6 EACH3.0001,413.00
0.0000.00
0.0000.00

0119                          A001.60 518.002.0001,036.00
JUNCTION BOX EACH2.0001,036.00
0.0000.00
0.0000.00

0120                          A008.62 1,855.003.0005,565.00
STREET LIGHTING UNIT, TYPE SL-S-12.2-0-0.20 EACH3.0005,565.00
0.0000.00
0.0000.00

0121                          A008.63 2,257.8242.00094,828.44
STREET LIGHTING UNIT, TYPE SL-BT-12.2-0-0.20 EACH42.00094,828.44
0.0000.00
0.0000.00

0122                          A020.36 3,119.003.0009,357.00
LIGHTING CONTROL CENTER, TYPE R-2 EACH3.0009,357.00
0.0000.00
0.0000.00

0123                          A069.14 10.7679.000850.04
25 mm CONDUIT IN TRENCH m 79.000850.04
0.0000.00
0.0000.00

0124                          A070.10 11.005.00055.00
38 mm CONDUIT IN TRENCH m 5.00055.00
0.0000.00
0.0000.00

0125                          A070.14 10.652,543.00027,082.95
50 mm CONDUIT IN TRENCH m 2,543.00027,082.95
0.0000.00
0.0000.00

0126                          A070.22 19.008.000152.00
100 mm CONDUIT IN TRENCH m 8.000152.00
0.0000.00
0.0000.00

0127                          A072.07 9.8422.000216.48
19 mm CONDUIT UNDER ROADWAY m 22.000216.48
0.0000.00
0.0000.00

0128                          A072.08 10.7914.000151.06
25 mm CONDUIT UNDER ROADWAY m 14.000151.06
0.0000.00
0.0000.00

0129                          A072.10 11.1615.000167.40
38 mm CONDUIT UNDER ROADWAY m 15.000167.40
0.0000.00
0.0000.00

0130                          A072.14 13.20208.0002,745.60
50 mm CONDUIT UNDER ROADWAY m 208.0002,745.60
0.0000.00
0.0000.00

0131                          A079.50 1.49265.000394.85
GROUNDING CONDUCTOR m 265.000394.85
0.0000.00
0.0000.00

0132                          A079.55 3.5220.00070.40
SERVICE CABLE m 20.00070.40
NO. 3 0.0000.00
0.0000.00

0133                          A079.57 2.0125.00050.25
SERVICE CABLE m 25.00050.25
NO. 8 0.0000.00
0.0000.00

0134                          A079.58 2.005.00010.00
SERVICE CABLE m 5.00010.00
NO. 10 0.0000.00
0.0000.00

0135                          A080.08 3.927,044.00027,612.48
STREET LIGHTING CABLE, NO. 3 XHHW m 7,044.00027,612.48
0.0000.00
0.0000.00

0136                          A080.24 3.0877.000237.16
STREET LIGHTING CABLE, NO. 6 USE m 77.000237.16
0.0000.00
0.0000.00

0137                          A080.26 2.78219.000608.82
STREET LIGHTING CABLE, NO. 6 XHHW m 219.000608.82
0.0000.00
0.0000.00

0138                          A080.34 2.385,784.00013,765.92
STREET LIGHTING CABLE, NO. 8 XHHW m 5,784.00013,765.92
0.0000.00
0.0000.00

0139                          A080.36 1.87992.0001,855.04
STREET LIGHTING CABLE, NO. 10 XHHW m 992.0001,855.04
0.0000.00
0.0000.00

0140                          A600.00 145.7465.0009,473.10
REMOVE LIGHTING UNIT EACH65.0009,473.10
2.000291.48
2.000291.48

0141                          A700.20 848.002.0001,696.00
RELOCATE STREET LIGHTING UNIT EACH2.0001,696.00
0.0000.00
0.0000.00

0142                          A780.00 27,389.001.00027,389.00
TEMPORARY LIGHTING SYSTEM, TYPE EACH1.00027,389.00
A 0.0000.00
0.0000.00

0143                          A780.02 12,846.001.00012,846.00
TEMPORARY LIGHTING SYSTEM, TYPE EACH1.00012,846.00
B 0.0000.00
0.0000.00

0144                          A780.04 9,817.001.0009,817.00
TEMPORARY LIGHTING SYSTEM, TYPE EACH1.0009,817.00
C 0.0000.00
0.0000.00

0145                          A780.05 21,209.001.00021,209.00
TEMPORARY LIGHTING SYSTEM EACH1.00021,209.00
TYPE D 0.0000.00
0.0000.00

0146                          A780.06 28,882.001.00028,882.00
TEMPORARY LIGHTING SYSTEM EACH1.00028,882.00
TYPE E 0.0000.00
0.0000.00

0147                          A780.07 8,380.001.0008,380.00
TEMPORARY LIGHTING SYSTEM EACH1.0008,380.00
TYPE F 0.0000.00
0.0000.00

0148                          A800.70 6.03460.0002,773.80
MAINTENANCE OF LIGHTING UNITS DAY 460.0002,773.80
5.00030.15
5.00030.15

GROUP 8B ELECTRICALContracted358,521.79
Current358,521.79
In place321.63
This Estimate321.63

GROUP 8C SIGNING
0149                          0030.82 3,251.001.0003,251.00
MOBILIZATION LS 1.0003,251.00
0.0000.00
0.0000.00

0150                          7312.00 46,279.001.00046,279.00
OVERHEAD SIGN SUPPORT, LOCATION EACH1.00046,279.00
2 0.0000.00
0.0000.00

0151                          7322.01 209.7712.6732,658.42
TYPE B SIGN m2 12.6732,658.42
0.0000.00
0.0000.00

0152                          7340.00 8.61171.6001,477.48
STRUCTURAL STEEL FOR SIGN SUPPORTS kg 171.6001,477.48
0.0000.00
0.0000.00

0153                          7360.24 480.002.000960.00
600 mm SIGN SUPPORT FOOTING EACH2.000960.00
0.0000.00
0.0000.00

0154                          A010.08 132.001.000132.00
LUMINAIRE, TYPE HPS-150 EACH1.000132.00
0.0000.00
0.0000.00

GROUP 8C SIGNINGContracted54,757.89
Current54,757.89
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0155                          0001.08 0.5075,985.00037,992.50
BARRICADE, TYPE II BDAY75,985.00037,992.50
1,076.000538.00
1,076.000538.00

0156                          0001.10 2.0412,095.00024,673.80
BARRICADE, TYPE III BDAY12,095.00024,673.80
279.000569.16
279.000569.16

0157                          0001.75 3.31700.0002,317.00
TEMPORARY SIGN DAY EACH700.0002,317.00
60.000198.60
60.000198.60

0158                          0001.90 0.3937,784.00014,735.76
SIGN DAY EACH37,784.00014,735.76
582.000226.98
582.000226.98

0159                          0001.99 2.211,792.0003,960.32
CONTRACTOR FURNISHED SIGN DAY EACH1,792.0003,960.32
0.0000.00
0.0000.00

0160                          0002.30 1.383,382.0004,667.16
PAVEMENT MARKING REMOVAL m 3,382.0004,667.16
0.0000.00
0.0000.00

0161                          0002.44 0.4519,191.0008,635.95
TEMPORARY PAVEMENT MARKING, TYPE PAINT m 19,191.0008,635.95
0.0000.00
0.0000.00

0162                          0002.47 0.8319,191.00015,928.53
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION m 19,191.00015,928.53
0.0000.00
0.0000.00

0163                          0002.97 138.01232.00032,018.32
FLASHING ARROW PANEL DAY 232.00032,018.32
10.0001,380.10
10.0001,380.10

0164                          0003.10 379.9020.0007,598.00
FLAGGING DAY 20.0007,598.00
0.0000.00
0.0000.00

0165                          0003.50 123.79111.00013,740.69
CONCRETE PROTECTION BARRIER m 111.00013,740.69
0.0000.00
0.0000.00

0166                          0005.10 138.01305.00042,093.05
TRAFFIC CONTROL MANAGEMENT DAY 305.00042,093.05
0.0000.00
0.0000.00

0167                          0010.04 4,968.001.0004,968.00
FIELD OFFICE EACH1.0004,968.00
0.0000.00
0.0000.00

0168                          0020.00 0.802,000.0001,600.00
TRAINING HOUR2,000.0001,600.00
0.0000.00
0.0000.00

0169                          0030.00 1.001.0001.00
MOBILIZATION LS 1.0001.00
0.0000.00
0.0000.00

0170                          7019.64 4,637.001.0004,637.00
TEMPORARY IMPACT ATTENUATOR EACH1.0004,637.00
0.0000.00
0.0000.00

0171                          9110.01 99.37110.00010,930.70
RENTAL OF LOADER, FULLY OPERATED HOUR110.00010,930.70
0.0000.00
0.0000.00

0172                          9110.02 110.0010.0001,100.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR10.0001,100.00
0.0000.00
0.0000.00

0173                          9110.03 71.76110.0007,893.60
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR110.0007,893.60
0.0000.00
0.0000.00

0174                          9110.06 104.89100.00010,489.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR100.00010,489.00
0.0000.00
0.0000.00

0175                          9110.07 121.45110.00013,359.50
RENTAL OF SKID LOADER, FULLY OPERATED HOUR110.00013,359.50
0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted263,339.88
Current263,339.88
In place2,912.84
This Estimate2,912.84

Totals for contractContracted5,021,822.65
Current5,021,822.65
In place133,348.67
This Estimate133,348.67