Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0103 VRANA & SON CONSTRUCTION CO./CHAS.
Contract ID:2834
Estimate Number:0027
Pay Period End Date:01.15.2003
Contract Location:
WESTBOUND TO SOUTHBOUND C-D ROAD, BRIDGE AND LOOPSEstimate Type:PROG
Contractor:
VRANA & SON CONSTRUCTION CO./CHAS.Date Let:07.12.2001
4816 F STDate Awarded:07.31.2001
Date Contract Executed:08.03.2001
Date Notice to Proceed:08.03.2001
OMAHA NE 68117-1481Date Work Began:08.09.2001
Phone:Date Physical Work Completed:
(402)733-5200Date Accepted:
Escrow Agent:
Surety Co:
THE CONTINENTAL INSURANCE COMPANY
Counties
DOUGLAS
Project Number PCT Fed State Project Number Description
21834 000  0.000 EACIM-680-9(790)  GR CP CULV BR ELEC SIGN
21837 000  0.000 EACIM-680-9(793)  GR CP BR
21877 000  0.000 EACIM-680-9(803)  GR CP CULV BR
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$5,196,524.95$5,188,569.39$7,955.56
$5,094,828.56Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$5,196,524.95$5,188,569.39$7,955.56
$5,026,696.99Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
102.00%Net Earnings$5,171,524.95$5,163,569.39$7,955.56
Liquidated Damages-$13,176.00-$8,784.00-$4,392.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-263.54$-263.54$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$13,439.54-$9,047.54-$4,392.00
Payment$5,158,085.41$5,154,521.85$3,563.56
Project ManagerDiv. Head/Dist. Eng.
Baehr, Dennis01.15.2003Lech, Marvin (Marv)01.15.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve01.16.2003
Controller Div. Processed
Burling, Laurie01.16.2003
Detailed breakdown of stockpiled materials
Est Nbr:0002
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00966131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment2,817.731979
Epoxy Coated Resteel
Total for estimate 0002:2,817.73
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00966131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-2,817.731979
Epoxy Coated Resteel
Total for estimate 0005:-2,817.73
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00264095.00 CONCRETE FACE PANELS
S.P. Initial Payment38,689.8935497
concrete face panels
S.P. Adjustment-27,150.8035497
concrete face panels
00906005.83 FIXED BEARING
S.P. Initial Payment5,667.50E20729
Fixed Bearings
Total for estimate 0008:17,206.59
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00264095.00 CONCRETE FACE PANELS
S.P. Adjustment-11,539.0935497
concrete face panels
Total for estimate 0009:-11,539.09
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00966131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment1,354.322268
Epoxy Coated Resteel
Total for estimate 0011:1,354.32
Est Nbr:0013
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00936071.11 STEEL SUPERSTRUCTURE
S.P. Initial Payment232,000.0014-S-02
STEEL SUPERSTRUCTURE
00946080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Initial Payment269.8014-S-02
STRUC STEEL FOR SUBSTRUCTURE
01036951.12 SHEAR CONNECTORS
S.P. Initial Payment1,866.6014-S-02
SHEAR CONNECTORS
Total for estimate 0013:234,136.40
Est Nbr:0014
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00906005.83 FIXED BEARING
S.P. Adjustment-5,667.50E20729
Fixed Bearings
00936071.11 STEEL SUPERSTRUCTURE
S.P. Adjustment-92,800.0014-S-02
STEEL SUPERSTRUCTURE
Total for estimate 0014:-98,467.50
Est Nbr:0015
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00936071.11 STEEL SUPERSTRUCTURE
S.P. Adjustment-62,640.0014-S-02
STEEL SUPERSTRUCTURE
00966131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-274.632268
Epoxy Coated Resteel
Total for estimate 0015:-62,914.63
Est Nbr:0017
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.75 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment22,686.35CI110120
Epoxy Dowel Baskets
S.P. Adjustment-1,114.05CI110120
Epoxy Dowel Baskets
00453075.95 355 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment3,330.16CI110120
Epoxy Dowel Baskets
Total for estimate 0017:24,902.46
Est Nbr:0018
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.75 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-2,181.08CI110120
Epoxy Dowel Baskets
S.P. Initial Payment5,656.32CI111020
Basket accessories
S.P. Adjustment-571.89CI111020
Basket accessories
00744155.50 REINFORCING STEEL FOR INLET AND JUNCTION BOX
S.P. Initial Payment497.78CI110726
resteel for inlets
S.P. Adjustment-87.54CI110726
resteel for inlets
Total for estimate 0018:3,313.59
Est Nbr:0019
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.75 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-4,811.58CI110120
Epoxy Dowel Baskets
S.P. Adjustment-1,261.61CI111020
Basket accessories
00936071.11 STEEL SUPERSTRUCTURE
S.P. Adjustment-76,560.0014-S-02
STEEL SUPERSTRUCTURE
00946080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Adjustment-269.8014-S-02
STRUC STEEL FOR SUBSTRUCTURE
00966131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-1,079.692268
Epoxy Coated Resteel
S.P. Initial Payment1,354.322587
Epoxy Coated Resteel
S.P. Adjustment-280.902587
Epoxy Coated Resteel
Total for estimate 0019:-82,909.26
Est Nbr:0020
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.75 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-5,355.28CI110120
Epoxy Dowel Baskets
S.P. Adjustment-1,404.17CI111020
Basket accessories
00966131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-1,073.422587
Epoxy Coated Resteel
01036951.12 SHEAR CONNECTORS
S.P. Adjustment-1,866.6014-S-02
SHEAR CONNECTORS
Total for estimate 0020:-9,699.47
Est Nbr:0021
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.75 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-7,726.58CI110120
Epoxy Dowel Baskets
S.P. Adjustment-2,025.93CI111020
Basket accessories
00453075.95 355 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-1,875.05CI110120
Epoxy Dowel Baskets
00744155.50 REINFORCING STEEL FOR INLET AND JUNCTION BOX
S.P. Adjustment-254.96CI110726
resteel for inlets
Total for estimate 0021:-11,882.52
Est Nbr:0022
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.75 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-647.80CI110120
Epoxy Dowel Baskets
S.P. Adjustment-169.86CI111020
Basket accessories
00453075.95 355 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-769.41CI110120
Epoxy Dowel Baskets
00896005.35 PRECOMPRESSED POLYURETHANE FOAM JOINT
S.P. Initial Payment2,274.78614135
Total for estimate 0022:687.71
Est Nbr:0024
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.75 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Closure-222.86CI111020
Basket accessories
00453075.95 355 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-685.71CI110120
Epoxy Dowel Baskets
00744155.50 REINFORCING STEEL FOR INLET AND JUNCTION BOX
S.P. Adjustment-23.00CI110726
resteel for inlets
00896005.35 PRECOMPRESSED POLYURETHANE FOAM JOINT
S.P. Adjustment-2,274.78614135
Total for estimate 0024:-3,206.35
Est Nbr:0025
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.75 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Closure-849.98CI110120
Epoxy Dowel Baskets
00744155.50 REINFORCING STEEL FOR INLET AND JUNCTION BOX
S.P. Adjustment-53.68CI110726
resteel for inlets
Total for estimate 0025:-903.66
Est Nbr:0026
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00744155.50 REINFORCING STEEL FOR INLET AND JUNCTION BOX
S.P. Adjustment-78.60CI110726
resteel for inlets
Total for estimate 0026:-78.60
Est Nbr:0002
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01226131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment4,157.011979
Epoxy Coated Resteel
Total for estimate 0002:4,157.01
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01226131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-1,881.001979
Epoxy Coated Resteel
Total for estimate 0005:-1,881.00
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01226131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-2,276.011979
Epoxy Coated Resteel
Total for estimate 0006:-2,276.01
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01166005.83 FIXED BEARING
S.P. Initial Payment6,740.00E20729
Fixed Bearing
Total for estimate 0008:6,740.00
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01226131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment3,118.692268
Epoxy Coated Resteel
S.P. Adjustment-802.562268
Epoxy Coated Resteel
Total for estimate 0011:2,316.13
Est Nbr:0012
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01166005.83 FIXED BEARING
S.P. Adjustment-6,740.00E20729
Fixed Bearing
01276951.12 SHEAR CONNECTORS
S.P. Initial Payment1,848.309-S-02
Shear connectors
Total for estimate 0012:-4,891.70
Est Nbr:0014
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01226131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-2,316.132268
Epoxy Coated Resteel
Total for estimate 0014:-2,316.13
Est Nbr:0015
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01276951.12 SHEAR CONNECTORS
S.P. Adjustment-1,848.309-S-02
Shear connectors
Total for estimate 0015:-1,848.30
Est Nbr:0016
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01226131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment10,197.522421
EPOXY COATED RE-STEEL
S.P. Adjustment-341.092421
EPOXY COATED RE-STEEL
Total for estimate 0016:9,856.43
Est Nbr:0017
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01113051.10 EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES
S.P. Initial Payment5,599.112461
EPOXY COATED RE-STEEL FOR PVMT APPRO
01226131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment6,755.132460
Epoxy Coated Resteel
S.P. Initial Payment4,018.602460
Epoxy Coated Resteel
Total for estimate 0017:16,372.84
Est Nbr:0018
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01113051.10 EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES
S.P. Adjustment-3,153.182461
EPOXY COATED RE-STEEL FOR PVMT APPRO
01226131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-6,755.132460
Epoxy Coated Resteel
S.P. Adjustment-4,018.602460
Epoxy Coated Resteel
S.P. Adjustment-9,856.432421
EPOXY COATED RE-STEEL
Total for estimate 0018:-23,783.34
Est Nbr:0019
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01113051.10 EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES
S.P. Adjustment-1,631.452461
EPOXY COATED RE-STEEL FOR PVMT APPRO
Total for estimate 0019:-1,631.45
Est Nbr:0020
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01113051.10 EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES
S.P. Adjustment-814.472461
EPOXY COATED RE-STEEL FOR PVMT APPRO
Total for estimate 0020:-814.47
Est Nbr:0002
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01436131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment4,008.411979
Epoxy Coated Resteel
Total for estimate 0002:4,008.41
Est Nbr:0003
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01436131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-3,702.431979
Epoxy Coated Resteel
Total for estimate 0003:-3,702.43
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01376005.83 FIXED BEARING
S.P. Initial Payment6,130.00E20729
Fixed Bearing
Total for estimate 0008:6,130.00
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01406071.11 STEEL SUPERSTRUCTURE
S.P. Initial Payment313,200.005-S-02
Steel Superstructure
01416080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Initial Payment227.205-S-02
Struc Steel For Superstructure
01436131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-199.391979
Epoxy Coated Resteel
01486951.12 SHEAR CONNECTORS
S.P. Initial Payment1,674.455-S-02
Shear Connectors
Total for estimate 0011:314,902.26
Est Nbr:0014
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01376005.83 FIXED BEARING
S.P. Adjustment-6,130.00E20729
Fixed Bearing
Total for estimate 0014:-6,130.00
Est Nbr:0017
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01436131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment2,802.692461
Epoxy Coated Resteel
Total for estimate 0017:2,802.69
Est Nbr:0020
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01406071.11 STEEL SUPERSTRUCTURE
S.P. Adjustment-156,600.005-S-02
Steel Superstructure
Total for estimate 0020:-156,600.00
Est Nbr:0021
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01406071.11 STEEL SUPERSTRUCTURE
S.P. Adjustment-156,600.005-S-02
Steel Superstructure
01416080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Adjustment-227.205-S-02
Struc Steel For Superstructure
Total for estimate 0021:-156,827.20
Est Nbr:0022
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01366005.35 PRECOMPRESSED POLYURETHANE FOAM JOINT
S.P. Initial Payment2,198.39614135
Precompress Foam Jt
01436131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-106.591979
Epoxy Coated Resteel
S.P. Adjustment-1,294.762461
Epoxy Coated Resteel
Total for estimate 0022:797.04
Est Nbr:0023
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01436131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-981.882461
Epoxy Coated Resteel
Total for estimate 0023:-981.88
Est Nbr:0024
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01436131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-526.052461
Epoxy Coated Resteel
01486951.12 SHEAR CONNECTORS
S.P. Adjustment-1,674.455-S-02
Shear Connectors
Total for estimate 0024:-2,200.50
Est Nbr:0026
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01366005.35 PRECOMPRESSED POLYURETHANE FOAM JOINT
S.P. Adjustment-2,198.39614135
Precompress Foam Jt
Total for estimate 0026:-2,198.39
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L010.98 7.80422.4003,294.72
TEMPORARY EROSION CONTROL m2 422.4003,294.72
390.0003,042.00
0.0000.00

0002                          L020.00 1.4028,481.00039,873.40
EROSION CONTROL m2 28,481.00039,873.40
37,894.03053,051.64
0.0000.00

0003                          L020.01 5.503,462.00019,041.00
EROSION CONTROL, TYPE A m2 3,462.00019,041.00
3,331.33018,322.32
0.0000.00

0004                          L020.10 1.505,082.0007,623.00
EROSION CONTROL, TYPE HV m2 5,082.0007,623.00
5,126.8857,690.33
0.0000.00

0005                          L021.01 18.0089.0001,602.00
EROSION CHECKS, TYPE A BALE89.0001,602.00
89.0001,602.00
0.0000.00

0006                          L021.06 15.0036.000540.00
EROSION CHECKS, TYPE HV BALE36.000540.00
36.000540.00
0.0000.00

0007                          L022.11 8.00101.800814.40
FABRIC SILT FENCE-LOW POROSITY m 101.800814.40
318.9002,551.20
0.0000.00

0008                          L022.12 9.00156.7001,410.30
FABRIC SILT FENCE-HIGH POROSITY m 156.7001,410.30
473.0004,257.00
0.0000.00

0009                          L022.23 20.0090.5001,810.00
FABRIC SILT FENCE-WP-WW-LOW POROSITY m 90.5001,810.00
99.5001,990.00
0.0000.00

0010                          L022.24 20.0080.6001,612.00
FABRIC SILT FENCE-WP-WW-HIGH POROSITY m 80.6001,612.00
63.0001,260.00
0.0000.00

0011                          0030.10 71,228.321.00071,228.32
MOBILIZATION LS 1.00071,228.32
1.00071,228.32
0.0000.00

0012                          1009.00 25,000.001.00025,000.00
GENERAL CLEARING AND GRUBBING LS 1.00025,000.00
1.00025,000.00
0.0000.00

0013                          1010.00 3.25160,960.000523,120.00
EXCAVATION m3 160,960.000523,120.00
160,960.000523,120.00
0.0000.00

0014                          1011.00 1.203,219.0003,862.80
WATER kL 3,219.0003,862.80
0.0000.00
0.0000.00

0015                          1021.10 5.0071.000355.00
REMOVE DELINEATOR UNITS EACH71.000355.00
91.000455.00
0.0000.00

0016                          1101.25 8.20191.0001,566.20
SAWING PAVEMENT m 191.0001,566.20
268.9002,204.98
0.0000.00

0017                          1102.00 2.606,455.00016,783.00
REMOVE ASPHALT SURFACE m2 6,455.00016,783.00
7,136.70018,555.42
0.0000.00

0018                          1109.20 17.501.50026.25
REMOVE CONCRETE BARRIER m 1.50026.25
0.0000.00
0.0000.00

0019                          1123.00 5.001,025.0005,125.00
REMOVE CONCRETE DITCH LINER m2 1,025.0005,125.00
1,522.7007,613.50
0.0000.00

0020                          3275.20 6.2011,675.00072,385.00
CRUSH CONCRETE PAVEMENT m2 11,675.00072,385.00
12,261.76076,022.92
0.0000.00

0021                          7017.00 5.00233.8001,169.00
REMOVE GUARDRAIL m 233.8001,169.00
327.5001,637.50
0.0000.00

0022                          9110.01 120.0010.0001,200.00
RENTAL OF LOADER, FULLY OPERATED HOUR10.0001,200.00
70.7308,487.60
12.4301,491.60

0023                          9110.03 100.0010.0001,000.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR10.0001,000.00
26.0002,600.00
0.0000.00

0024                          9110.07 100.0010.0001,000.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR10.0001,000.00
21.2002,120.00
0.0000.00

GROUP 1 GRADINGContracted801,441.39
Current801,441.39
In place833,351.73
This Estimate1,491.60

GROUP 1A MSE WALL
0025                          0030.10 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0026                          4095.00 200.00602.000120,400.00
CONCRETE FACE PANELS m2 602.000120,400.00
602.000120,400.00
0.0000.00

0027                          4095.10 48.60113.7005,525.82
CONCRETE LEVELING PADS m 113.7005,525.82
113.7005,525.82
0.0000.00

0028                          4095.20 92.10115.90010,674.39
COPING m 115.90010,674.39
113.90010,490.19
0.0000.00

0029                          4350.24 36.20215.7007,808.34
600 mm CORRUGATED METAL PIPE m 215.7007,808.34
215.7007,808.34
0.0000.00

0030                          8024.75 24.002,579.00061,896.00
SELECT GRANULAR BACKFILL FOR MSE WALL m3 2,579.00061,896.00
2,579.00061,896.00
0.0000.00

GROUP 1A MSE WALLContracted211,304.55
Current211,304.55
In place211,120.35
This Estimate0.00

GROUP 3 CONCRETE PAVEMENT
0031                          L001.01 1,500.004.3006,450.00
SEEDING, TYPE A ha 4.3006,450.00
3.9515,926.50
0.0000.00

0032                          L001.02 1,000.001.2001,200.00
SEEDING, TYPE B ha 1.2001,200.00
1.1081,108.00
0.0000.00

0033                          L006.50 850.004.2003,570.00
TEMPORARY SEEDING ha 4.2003,570.00
8.7927,473.20
0.0000.00

0034                          L032.75 100.0048.5004,850.00
MULCH Mg 48.5004,850.00
65.2106,521.00
0.0000.00

0035                          0030.30 14,470.401.00014,470.40
MOBILIZATION LS 1.00014,470.40
1.00014,470.40
0.0000.00

0036                          1020.02 10.5071.000745.50
DELINEATOR, TYPE II EACH71.000745.50
148.0001,554.00
0.0000.00

0037                          1020.15 10.00735.0007,350.00
MEDIAN CHAIN DELINEATOR m 735.0007,350.00
735.0007,350.00
0.0000.00

0038                          2020.50 42.204,246.000179,181.20
SURFACING m2 4,246.000179,181.20
250 mm 5,323.200224,639.04
0.0000.00

0039                          3008.05 4.60156.000717.60
TIE BARS EACH156.000717.60
55.000253.00
0.0000.00

0040                          3016.21 37.0015.000555.00
CONCRETE CLASS 47B-20 SIDEWALKS m2 15.000555.00
15.000555.00
0.0000.00

0041                          3027.00 2,220.001.0002,220.00
CONCRETE CLASS 47BD-30 MEDIAN BARRIER TRANSITION SECTION EACH1.0002,220.00
1.0002,220.00
0.0000.00

0042                          3075.71 35.203,939.000138,652.80
305 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 3,939.000138,652.80
4,586.920161,459.59
0.0000.00

0043                          3075.75 37.7011,049.000416,547.30
305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 11,049.000416,547.30
10,635.040400,941.01
0.0000.00

0044                          3075.91 41.60596.00024,793.60
355 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 596.00024,793.60
557.45023,189.92
0.0000.00

0045                          3075.95 43.90931.00040,870.90
355 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 931.00040,870.90
931.00040,870.90
0.0000.00

0046                          3089.25 44.603,896.000173,761.60
TEMPORARY SURFACING m2 3,896.000173,761.60
4,492.050200,345.43
0.0000.00

0047                          4020.25 43.00405.00017,415.00
CONCRETE DITCH LINING m2 405.00017,415.00
200 mm 405.00017,415.00
0.0000.00

0048                          4764.35 25.1015.800396.58
100 mm PERFORATED PIPE UNDERDRAIN m 15.800396.58
143.8003,609.38
0.0000.00

0049                          8029.10 6.4015,109.00096,697.60
AGGREGATE FOUNDATION COURSE-D 100 mm m2 542.5803,472.51
542.5803,472.50
0.0000.00

0050                          8029.12 8.701,406.00012,232.20
AGGREGATE FOUNDATION COURSE-D 150 mm m2 0.0000.00
0.0000.00
0.0000.00

0051                          8060.05 150.0015.0002,250.00
GRANULAR SUBDRAIN EACH15.0002,250.00
14.0002,100.00
0.0000.00

0052                          9111.00 4.40333.0001,465.20
WATER kL 333.0001,465.20
13.25058.30
0.0000.00

0053                          9170.00 650.0035.73823,229.70
EARTH SHOULDER CONSTRUCTION StaM35.73823,229.70
35.73823,229.70
0.0000.00

0054                          9173.20 1.6016,515.00026,424.00
SUBGRADE PREPARATION m2 16,515.00026,424.00
16,552.61026,484.18
0.0000.00

4006                          3025.00 170.000.0000.00
CONCRETE CLASS 47BD-30 MEDIAN BARRIER m 40.0006,800.00
35.0005,950.00
0.0000.00

4013                          8029.84 6.000.0000.00
BITUMINOUS FOUNDATION COURSE 100 mm m2 14,566.42087,398.52
14,521.58087,129.48
0.0000.00

4014                          8029.86 8.1250.0000.00
BITUMINOUS FOUNDATION COURSE 150 mm m2 1,406.00011,423.75
1,488.45012,093.66
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted1,196,046.18
Current1,196,211.16
In place1,280,419.19
This Estimate0.00

GROUP 4 CULVERTS
0055                          P070.18 80.40280.20022,528.08
450 mm CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 280.20022,528.08
266.50021,426.60
0.0000.00

0056                          P120.42 297.5027.5008,181.25
1050 mm CULVERT PIPE TYPE 2 m 27.5008,181.25
26.8007,973.00
0.0000.00

0057                          P400.36 219.4070.50015,467.70
900 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 70.50015,467.70
70.50015,467.70
0.0000.00

0058                          P700.18 87.40279.80024,454.52
450 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 279.80024,454.52
296.15025,883.51
0.0000.00

0059                          P702.24 116.0099.00011,484.00
600 mm STORM SEWER PIPE, TYPE 1 m 99.00011,484.00
103.14011,964.24
0.0000.00

0060                          P702.36 259.1016.5004,275.15
900 mm STORM SEWER PIPE, TYPE 1 m 16.5004,275.15
16.5004,275.15
0.0000.00

0061                          0030.40 9,863.641.0009,863.64
MOBILIZATION LS 1.0009,863.64
1.0009,863.64
0.0000.00

0062                          1119.00 510.005.0002,550.00
REMOVE INLET EACH5.0002,550.00
5.0002,550.00
0.0000.00

0063                          4004.50 2.905,735.00016,631.50
CAST IRON GRATE AND FRAME kg 5,735.00016,631.50
5,735.00016,631.50
0.0000.00

0064                          4035.25 320.003.000960.00
REMOVE AND SALVAGE FLARED-END SECTION EACH3.000960.00
4.0001,280.00
0.0000.00

0065                          4040.00 290.004.0001,160.00
REMOVE HEADWALLS FROM CULVERTS EACH4.0001,160.00
4.0001,160.00
0.0000.00

0066                          4043.50 33.7052.2001,759.14
REMOVE SEWER PIPE m 52.2001,759.14
60.2002,028.74
0.0000.00

0067                          4043.60 61.3032.6001,998.38
RELAYING SEWER PIPE m 32.6001,998.38
32.6001,998.38
0.0000.00

0068                          4050.01 11.50476.0005,474.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 476.0005,474.00
476.0005,474.00
0.0000.00

0069                          4100.06 1,110.000.540599.40
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 0.540599.40
0.540599.40
0.0000.00

0070                          4105.59 760.0028.65021,774.00
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 28.65021,774.00
28.65021,774.00
0.0000.00

0071                          4107.07 1,020.003.2603,325.20
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 3.2603,325.20
3.1703,233.40
0.0000.00

0072                          4130.06 1,700.000.300510.00
CLASS 47B-20 OR AX-20 CONCRETE FOR PIPE CULVERT PLUG m3 0.300510.00
0.300510.00
0.0000.00

0073                          4150.00 1.9020.00038.00
REINFORCING STEEL FOR HEADWALL kg 20.00038.00
20.00038.00
0.0000.00

0074                          4155.50 1.201,029.0001,234.80
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 1,029.0001,234.80
1,031.4001,237.68
0.0000.00

0075                          4157.00 1.30155.000201.50
REINFORCING STEEL FOR COLLARS kg 155.000201.50
133.000172.90
0.0000.00

0076                          4310.18 540.0010.0005,400.00
450 mm FLARED-END SECTION EACH10.0005,400.00
10.0005,400.00
0.0000.00

0077                          4310.24 560.001.000560.00
600 mm FLARED-END SECTION EACH1.000560.00
2.0001,120.00
0.0000.00

0078                          4310.42 900.001.000900.00
1050 mm FLARED-END SECTION EACH1.000900.00
1.000900.00
0.0000.00

0079                          4461.24 380.003.0001,140.00
INSTALL 600 mm CONCRETE FLARED-END SECTION EACH3.0001,140.00
3.0001,140.00
0.0000.00

0080                          4670.05 100.002.900290.00
CULVERT SANDFILL m3 2.900290.00
2.900290.00
0.0000.00

0081                          4900.24 670.007.0004,690.00
AREA INLET SEDIMENT FILTER EACH7.0004,690.00
7.0004,690.00
0.0000.00

GROUP 4 CULVERTSContracted167,450.26
Current167,450.26
In place169,081.84
This Estimate0.00

GROUP 6 BRIDGE AT STA. 802+57.238
0082                          0020.00 0.80500.000400.00
TRAINING HOUR500.000400.00
0.0000.00
0.0000.00

0083                          0030.60 35,000.001.00035,000.00
MOBILIZATION LS 1.00035,000.00
1.00035,000.00
0.0000.00

0084                          3050.15 240.00138.70033,288.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 138.70033,288.00
138.70033,288.00
0.0000.00

0085                          3051.10 2.008,709.00017,418.00
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,709.00017,418.00
8,709.00017,418.00
0.0000.00

0086                          6000.10 1,530.001.0001,530.00
ABUTMENT NO.1 EXCAVATION LS 1.0001,530.00
1.0001,530.00
0.0000.00

0087                          6000.11 1,530.001.0001,530.00
ABUTMENT NO.2 EXCAVATION LS 1.0001,530.00
1.0001,530.00
0.0000.00

0088                          6000.20 2,220.001.0002,220.00
PIER NO.1 EXCAVATION LS 1.0002,220.00
1.0002,220.00
0.0000.00

0089                          6005.35 130.0026.8003,484.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 26.8003,484.00
26.8003,484.00
0.0000.00

0090                          6005.83 1,110.005.0005,550.00
FIXED BEARING EACH5.0005,550.00
5.0005,550.00
0.0000.00

0091                          6010.22 388.80150.90058,669.92
CLASS 47B-20 CONCRETE FOR BRIDGE m3 150.90058,669.92
152.00059,097.60
0.0000.00

0092                          6010.26 378.10244.90092,596.69
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 244.90092,596.69
244.90092,596.69
0.0000.00

0093                          6071.11 265,000.001.000265,000.00
STEEL SUPERSTRUCTURE LS 1.000265,000.00
AT STA. 802+57.238 1.000265,000.00
0.0000.00

0094                          6080.00 5.00380.0001,900.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 380.0001,900.00
380.0001,900.00
0.0000.00

0095                          6107.00 49.10256.00012,569.60
CONCRETE SLOPE PROTECTION m2 256.00012,569.60
194.1009,530.31
0.0000.00

0096                          6131.50 1.3037,277.00048,460.10
EPOXY COATED REINFORCING STEEL kg 37,277.00048,460.10
37,328.00048,526.40
0.0000.00

0097                          6139.50 26.3062.0001,630.60
SUBSURFACE DRAINAGE MATTING m2 62.0001,630.60
62.0001,630.60
0.0000.00

0098                          6210.12 66.70264.60017,648.82
HP 250 mm X 62 kg STEEL PILING m 264.60017,648.82
280.88018,734.70
0.0000.00

0099                          6210.14 76.70439.20033,686.64
HP 310 mm X 79 kg STEEL PILING m 439.20033,686.64
396.32030,397.75
0.0000.00

0100                          6510.55 21,100.001.00021,100.00
TEMPORARY BRIDGE SHORING LS 1.00021,100.00
1.00021,100.00
0.0000.00

0101                          6510.60 16,600.001.00016,600.00
BRIDGE SHORING LS 1.00016,600.00
1.00016,600.00
0.0000.00

0102                          6601.15 42.00103.8004,359.60
38 mm CONDUIT IN BRIDGE m 103.8004,359.60
103.8004,359.60
0.0000.00

0103                          6951.12 2.703,060.0008,262.00
SHEAR CONNECTORS EACH3,060.0008,262.00
3,060.0008,262.00
0.0000.00

0104                          7011.20 80.007.620609.60
W-BEAM GUARDRAIL m 7.620609.60
7.620609.60
0.0000.00

0105                          7020.00 1,800.001.0001,800.00
BRIDGE APPROACH SECTIONS EACH1.0001,800.00
1.0001,800.00
0.0000.00

0106                          7024.25 3,000.001.0003,000.00
GUARDRAIL END TREATMENT, TYPE I EACH1.0003,000.00
1.0003,000.00
0.0000.00

0107                          8091.00 50.80190.1009,657.08
GRANULAR BACKFILL m3 190.1009,657.08
190.1009,657.08
0.0000.00

4002                          6210.34 45.660.0000.00
PAY CUT-OFF FOR 310 mm X 79 kg STEEL PILING m 31.4001,433.72
43.7201,996.25
0.0000.00

4007                          6210.32 40.020.0000.00
PAY CUT-OFF FOR 250 mm X 62 kg STEEL PILING m 10.000400.20
0.70028.01
0.0000.00

4008                          6210.42 133.400.0000.00
HP 250 mm X 62 kg, PILE SPLICES EACH20.0002,668.00
1.000133.40
0.0000.00

4009                          6210.44 153.400.0000.00
HP 310 mm X 79 kg, PILE SPLICE EACH20.0003,068.00
3.000460.20
0.0000.00

GROUP 6 BRIDGE AT STA. 802+57.238Contracted697,970.65
Current705,540.57
In place695,440.19
This Estimate0.00

GROUP 8B ELECTRICAL
0150                          A001.16 600.002.0001,200.00
PULL BOX, TYPE PB-6 EACH2.0001,200.00
2.0001,200.00
0.0000.00

0151                          A010.26 800.0010.0008,000.00
LUMINAIRE, TYPE HML-V-1KW EACH10.0008,000.00
10.0008,000.00
0.0000.00

0152                          A018.81 4,700.001.0004,700.00
FOUNDATION DESIGN EACH1.0004,700.00
1.0004,700.00
0.0000.00

0153                          A018.82 225.0011.5002,587.50
CONCRETE FOR FOUNDATION m3 11.5002,587.50
13.3803,010.50
0.0000.00

0154                          A018.83 4.00550.0002,200.00
REINFORCING STEEL kg 550.0002,200.00
663.0002,652.00
0.0000.00

0155                          A018.84 250.006.0001,500.00
ANCHOR BOLTS EACH6.0001,500.00
6.0001,500.00
0.0000.00

0156                          A072.14 20.0010.000200.00
50 mm CONDUIT UNDER ROADWAY m 10.000200.00
10.000200.00
0.0000.00

0157                          A074.14 70.009.000630.00
50 mm CONDUIT, JACKED m 9.000630.00
9.000630.00
0.0000.00

0158                          A082.12 8.00453.0003,624.00
DIRECT BURIAL CABLE, NO. 2 USE m 453.0003,624.00
1,083.0008,664.00
0.0000.00

0159                          A750.10 18,000.001.00018,000.00
MODIFY HIGH MAST TOWER EACH1.00018,000.00
TYPE P-45.7 1.00018,000.00
0.0000.00

0160                          0030.81 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

4012                          1800.01 5,257.170.0000.00
RELOCATE LS 1.0005,257.17
Relocate Temporary Lighting 1.0005,257.17
0.0000.00

4026                          A110.02 1,222.210.0000.00
REPAIR LS 1.0001,222.21
REPAIR LIGHTING CIRCUIT 1.0001,222.21
1.0001,222.21

GROUP 8B ELECTRICALContracted45,641.50
Current52,120.88
In place58,035.88
This Estimate1,222.21

GROUP 8C SIGNING
0161                          0030.82 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0162                          7308.10 1,000.004.0004,000.00
REMOVE SIGN EACH4.0004,000.00
5.0005,000.00
0.0000.00

0163                          7312.00 12,200.001.00012,200.00
OVERHEAD SIGN SUPPORT, LOCATION EACH1.00012,200.00
1 1.00012,200.00
0.0000.00

0164                          7320.00 250.005.0001,250.00
INSTALL SIGN EACH5.0001,250.00
3.000750.00
0.0000.00

0165                          7320.05 650.003.0001,950.00
INSTALL OVERHEAD SIGN EACH3.0001,950.00
2.0001,300.00
0.0000.00

0166                          7340.00 5.50580.0003,190.00
STRUCTURAL STEEL FOR SIGN SUPPORTS kg 580.0003,190.00
0.0000.00
0.0000.00

0167                          7360.24 600.002.0001,200.00
600 mm SIGN SUPPORT FOOTING EACH2.0001,200.00
2.0001,200.00
0.0000.00

0168                          7390.00 800.002.0001,600.00
REMOVE SIGN AND POST EACH2.0001,600.00
4.0003,200.00
0.0000.00

4015                          7308.00 5,043.780.0000.00
REMOVE SIGN, STRUCTURE, AND FOUNDATION EACH1.0005,043.78
1.0005,043.78
0.0000.00

4016                          7320.20 438.380.0000.00
INSTALL TRAFFIC SIGN AND POST LS 1.000438.38
1.000438.38
0.0000.00

4021                          A010.08 1,155.000.0000.00
LUMINAIRE, TYPE HPS-150 EACH1.0001,155.00
Sta. 121+06 Lt. 1.0001,155.00
0.0000.00

4025                          7308.00 2,356.740.0000.00
REMOVE SIGN, STRUCTURE, AND FOUNDATION EACH1.0002,356.74
1.0002,356.74
1.0002,356.74

4027                          1137.50 2,885.010.0000.00
REMOVE AND RESET LS 1.0002,885.01
Remove and Reset Signs and Post 1.0002,885.01
1.0002,885.01

GROUP 8C SIGNINGContracted27,390.00
Current39,268.91
In place37,528.91
This Estimate5,241.75

GROUP 10 GENERAL ITEMS
0169                          A800.70 6.30412.0002,595.60
MAINTENANCE OF LIGHTING UNITS DAY 412.0002,595.60
414.0002,608.20
0.0000.00

0170                          0001.08 0.5024,319.00012,159.50
BARRICADE, TYPE II BDAY24,319.00012,159.50
47,000.00023,500.00
0.0000.00

0171                          0001.10 3.102,497.0007,740.70
BARRICADE, TYPE III BDAY2,497.0007,740.70
10,151.00031,468.10
0.0000.00

0172                          0001.30 3.201,684.0005,388.80
TYPE B HIGH INTENSITY WARNING LIGHT LDAY1,684.0005,388.80
3,097.0009,910.40
0.0000.00

0173                          0001.75 3.301,401.0004,623.30
TEMPORARY SIGN DAY EACH1,401.0004,623.30
1,219.0004,022.70
0.0000.00

0174                          0001.90 2.2015,466.00034,025.20
SIGN DAY EACH15,466.00034,025.20
16,548.00036,405.60
0.0000.00

0175                          0002.30 0.2575,000.00018,750.00
PAVEMENT MARKING REMOVAL m 75,000.00018,750.00
21,212.0005,303.00
0.0000.00

0176                          0002.44 0.10150,000.00015,000.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT m 150,000.00015,000.00
46,390.0004,639.00
0.0000.00

0177                          0002.47 0.1550,000.0007,500.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION m 50,000.0007,500.00
24,705.0003,705.75
0.0000.00

0178                          0002.48 2.202,000.0004,400.00
TEMPORARY RAISED PAVEMENT MARKER EACH2,000.0004,400.00
1,030.0002,266.00
0.0000.00

0179                          0002.97 200.00112.00022,400.00
FLASHING ARROW PANEL DAY 112.00022,400.00
139.00027,800.00
0.0000.00

0180                          0003.10 180.00120.00021,600.00
FLAGGING DAY 120.00021,600.00
51.5009,270.00
0.0000.00

0181                          0003.51 10.902,325.00025,342.50
INSTALL CONCRETE PROTECTION BARRIER m 2,325.00025,342.50
2,383.00025,974.70
0.0000.00

0182                          0003.56 5.401,500.0008,100.00
RELOCATE CONCRETE PROTECTION BARRIER m 1,500.0008,100.00
1,366.9007,381.26
0.0000.00

0183                          0003.57 1,050.005.0005,250.00
RELOCATE INERTIAL BARRIER SYSTEM EACH5.0005,250.00
9.0009,450.00
0.0000.00

0184                          0003.58 1,300.007.0009,100.00
INERTIAL BARRIER SYSTEM EACH7.0009,100.00
5.0006,500.00
0.0000.00

0185                          0003.64 475.005.0002,375.00
REPLACEMENT MODULE EACH5.0002,375.00
11.0005,225.00
0.0000.00

0186                          0010.04 2,060.001.0002,060.00
FIELD OFFICE EACH1.0002,060.00
1.0002,060.00
0.0000.00

0187                          0030.00 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted213,410.60
Current213,410.60
In place222,489.71
This Estimate0.00

GROUP 1 GRADING
0011                          0030.10 263.341.000263.34
MOBILIZATION LS 1.000263.34
0.560147.47
0.0000.00

0016                          1101.25 8.2046.200378.84
SAWING PAVEMENT m 46.200378.84
46.000377.20
0.0000.00

0018                          1109.20 17.504.00070.00
REMOVE CONCRETE BARRIER m 4.00070.00
0.0000.00
0.0000.00

0020                          3275.20 6.20121.000750.20
CRUSH CONCRETE PAVEMENT m2 121.000750.20
117.200726.64
0.0000.00

GROUP 1 GRADINGContracted1,462.38
Current1,462.38
In place1,251.31
This Estimate0.00

GROUP 3 CONCRETE PAVEMENT
0035                          0030.30 264.801.000264.80
MOBILIZATION LS 1.000264.80
1.000264.80
0.0000.00

0039                          3008.05 4.6037.000170.20
TIE BARS EACH37.000170.20
32.000147.20
0.0000.00

0041                          3027.00 2,220.002.0004,440.00
CONCRETE CLASS 47BD-30 MEDIAN BARRIER TRANSITION SECTION EACH2.0004,440.00
2.0004,440.00
0.0000.00

0044                          3075.91 41.60115.0004,784.00
355 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 115.0004,784.00
111.5304,639.65
0.0000.00

0048                          4764.35 25.1015.100379.01
100 mm PERFORATED PIPE UNDERDRAIN m 15.100379.01
15.100379.01
0.0000.00

0050                          8029.12 8.70115.0001,000.50
AGGREGATE FOUNDATION COURSE-D 150 mm m2 115.0001,000.50
111.530970.31
0.0000.00

0052                          9111.00 4.402.0008.80
WATER kL 2.0008.80
0.0000.00
0.0000.00

0054                          9173.20 1.60115.000184.00
SUBGRADE PREPARATION m2 115.000184.00
111.530178.45
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted11,231.31
Current11,231.31
In place11,019.42
This Estimate0.00

GROUP 6A BRIDGE AT STA. 508+29.77
0108                          0020.00 0.801,000.000800.00
TRAINING HOUR1,000.000800.00
0.0000.00
0.0000.00

0109                          0030.60 30,000.001.00030,000.00
MOBILIZATION LS 1.00030,000.00
1.00030,000.00
0.0000.00

0110                          3050.15 220.00138.50030,470.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 138.50030,470.00
138.50030,470.00
0.0000.00

0111                          3051.10 1.408,930.00012,502.00
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,930.00012,502.00
8,930.00012,502.00
0.0000.00

0112                          6000.10 2,420.001.0002,420.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,420.00
1.0002,420.00
0.0000.00

0113                          6000.11 2,090.001.0002,090.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,090.00
1.0002,090.00
0.0000.00

0114                          6000.20 2,310.001.0002,310.00
PIER NO.1 EXCAVATION LS 1.0002,310.00
1.0002,310.00
0.0000.00

0115                          6005.35 130.0028.0003,640.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 28.0003,640.00
28.0003,640.00
0.0000.00

0116                          6005.83 1,410.005.0007,050.00
FIXED BEARING EACH5.0007,050.00
5.0007,050.00
0.0000.00

0117                          6010.22 363.50195.50071,064.25
CLASS 47B-20 CONCRETE FOR BRIDGE m3 195.50071,064.25
195.50071,064.25
0.0000.00

0118                          6010.26 370.00302.400111,888.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 302.400111,888.00
302.400111,888.00
0.0000.00

0119                          6071.11 414,000.001.000414,000.00
STEEL SUPERSTRUCTURE LS 1.000414,000.00
AT STA. 508+29.77 1.000414,000.00
0.0000.00

0120                          6080.00 4.70410.0001,927.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 410.0001,927.00
410.0001,927.00
0.0000.00

0121                          6107.00 49.50250.00012,375.00
CONCRETE SLOPE PROTECTION m2 250.00012,375.00
250.00012,375.00
0.0000.00

0122                          6131.50 1.3044,975.00058,467.50
EPOXY COATED REINFORCING STEEL kg 44,975.00058,467.50
45,268.00058,848.40
0.0000.00

0123                          6139.50 25.8070.0001,806.00
SUBSURFACE DRAINAGE MATTING m2 70.0001,806.00
70.0001,806.00
0.0000.00

0124                          6210.12 66.70411.50027,447.05
HP 250 mm X 62 kg STEEL PILING m 411.50027,447.05
379.09025,285.31
0.0000.00

0125                          6210.14 76.70784.80060,194.16
HP 310 mm X 79 kg STEEL PILING m 784.80060,194.16
686.52052,656.08
0.0000.00

0126                          6601.15 34.00115.5003,927.00
38 mm CONDUIT IN BRIDGE m 115.5003,927.00
115.5003,927.00
0.0000.00

0127                          6951.12 2.703,030.0008,181.00
SHEAR CONNECTORS EACH3,030.0008,181.00
3,030.0008,181.00
0.0000.00

0128                          8091.00 48.60305.00014,823.00
GRANULAR BACKFILL m3 305.00014,823.00
305.00014,823.00
0.0000.00

4003                          6210.34 45.660.0000.00
PAY CUT-OFF FOR 310 mm X 79 kg STEEL PILING m 42.7701,952.88
27.4001,251.09
0.0000.00

4004                          6210.34 45.660.0000.00
PAY CUT-OFF FOR 310 mm X 79 kg STEEL PILING m 70.8403,234.55
70.8403,234.55
0.0000.00

4005                          6210.32 40.020.0000.00
PAY CUT-OFF FOR 250 mm X 62 kg STEEL PILING m 29.8901,196.20
32.3901,296.25
0.0000.00

4017                          7312.00 12,547.500.0000.00
OVERHEAD SIGN SUPPORT, LOCATION EACH1.00012,547.50
STA. 123+61 LT. 1.00012,547.50
0.0000.00

4019                          A010.08 1,155.000.0000.00
LUMINAIRE, TYPE HPS-150 EACH1.0001,155.00
STA. 123+61 LT. 1.0001,155.00
0.0000.00

4024                          7320.05 650.000.0000.00
INSTALL OVERHEAD SIGN EACH1.000650.00
station 123+61 Lt. 1.000650.00
0.0000.00

GROUP 6A BRIDGE AT STA. 508+29.77Contracted877,381.96
Current898,118.09
In place887,397.43
This Estimate0.00

GROUP 1 GRADING
0011                          0030.10 263.341.000263.34
MOBILIZATION LS 1.000263.34
0.550144.84
0.0000.00

0016                          1101.25 8.2046.000377.20
SAWING PAVEMENT m 46.000377.20
39.400323.08
0.0000.00

0018                          1109.20 17.503.30057.75
REMOVE CONCRETE BARRIER m 3.30057.75
0.0000.00
0.0000.00

0020                          3275.20 6.20119.000737.80
CRUSH CONCRETE PAVEMENT m2 119.000737.80
90.480560.98
0.0000.00

GROUP 1 GRADINGContracted1,436.09
Current1,436.09
In place1,028.90
This Estimate0.00

GROUP 3 CONCRETE PAVEMENT
0035                          0030.30 264.801.000264.80
MOBILIZATION LS 1.000264.80
1.000264.80
0.0000.00

0039                          3008.05 4.6037.000170.20
TIE BARS EACH37.000170.20
23.000105.80
0.0000.00

0041                          3027.00 2,220.002.0004,440.00
CONCRETE CLASS 47BD-30 MEDIAN BARRIER TRANSITION SECTION EACH2.0004,440.00
2.0004,440.00
0.0000.00

0044                          3075.91 41.60113.0004,700.80
355 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 113.0004,700.80
84.7203,524.35
0.0000.00

0048                          4764.35 25.1014.900373.99
100 mm PERFORATED PIPE UNDERDRAIN m 14.900373.99
14.900373.99
0.0000.00

0050                          8029.12 8.70113.000983.10
AGGREGATE FOUNDATION COURSE-D 150 mm m2 113.000983.10
84.720737.06
0.0000.00

0052                          9111.00 4.402.0008.80
WATER kL 2.0008.80
0.0000.00
0.0000.00

0054                          9173.20 1.60113.000180.80
SUBGRADE PREPARATION m2 113.000180.80
84.720135.55
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted11,122.49
Current11,122.49
In place9,581.55
This Estimate0.00

GROUP 4 CULVERTS
0061                          0030.40 136.361.000136.36
MOBILIZATION LS 1.000136.36
1.000136.36
0.0000.00

0066                          4043.50 33.7012.000404.40
REMOVE SEWER PIPE m 12.000404.40
12.000404.40
0.0000.00

0067                          4043.60 61.3012.000735.60
RELAYING SEWER PIPE m 12.000735.60
12.000735.60
0.0000.00

0071                          4107.07 1,020.000.640652.80
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 0.640652.80
0.640652.80
0.0000.00

0075                          4157.00 1.3034.00044.20
REINFORCING STEEL FOR COLLARS kg 34.00044.20
34.00044.20
0.0000.00

GROUP 4 CULVERTSContracted1,973.36
Current1,973.36
In place1,973.36
This Estimate0.00

GROUP 6B BRIDGE AT STA. 602+49.196
0129                          0020.00 0.80500.000400.00
TRAINING HOUR500.000400.00
0.0000.00
0.0000.00

0130                          0030.60 30,000.001.00030,000.00
MOBILIZATION LS 1.00030,000.00
1.00030,000.00
0.0000.00

0131                          3050.15 220.00136.50030,030.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 136.50030,030.00
136.50030,030.00
0.0000.00

0132                          3051.10 1.408,624.00012,073.60
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,624.00012,073.60
8,624.00012,073.60
0.0000.00

0133                          6000.10 2,170.001.0002,170.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,170.00
1.0002,170.00
0.0000.00

0134                          6000.11 2,210.001.0002,210.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,210.00
1.0002,210.00
0.0000.00

0135                          6000.20 2,310.001.0002,310.00
PIER NO.1 EXCAVATION LS 1.0002,310.00
1.0002,310.00
0.0000.00

0136                          6005.35 130.0025.9003,367.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 25.9003,367.00
25.9003,367.00
0.0000.00

0137                          6005.83 1,540.005.0007,700.00
FIXED BEARING EACH5.0007,700.00
5.0007,700.00
0.0000.00

0138                          6010.22 362.50184.80066,990.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 184.80066,990.00
184.80066,990.01
0.0000.00

0139                          6010.26 377.40254.00095,859.60
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 254.00095,859.60
254.00095,859.60
0.0000.00

0140                          6071.11 350,000.001.000350,000.00
STEEL SUPERSTRUCTURE LS 1.000350,000.00
AT STA. 602+49.196 1.000350,000.00
0.0000.00

0141                          6080.00 5.80320.0001,856.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 320.0001,856.00
320.0001,856.00
0.0000.00

0142                          6107.00 42.90448.00019,219.20
CONCRETE SLOPE PROTECTION m2 448.00019,219.20
448.00019,219.20
0.0000.00

0143                          6131.50 1.3039,260.00051,038.00
EPOXY COATED REINFORCING STEEL kg 39,260.00051,038.00
39,260.00051,038.00
0.0000.00

0144                          6139.50 25.1086.0002,158.60
SUBSURFACE DRAINAGE MATTING m2 86.0002,158.60
86.0002,158.60
0.0000.00

0145                          6210.12 66.70263.60017,582.12
HP 250 mm X 62 kg STEEL PILING m 263.60017,582.12
247.89016,534.26
0.0000.00

0146                          6210.14 76.70547.50041,993.25
HP 310 mm X 79 kg STEEL PILING m 547.50041,993.25
494.57737,934.05
0.0000.00

0147                          6601.15 34.00105.6003,590.40
38 mm CONDUIT IN BRIDGE m 105.6003,590.40
105.6003,590.40
0.0000.00

0148                          6951.12 2.702,745.0007,411.50
SHEAR CONNECTORS EACH2,745.0007,411.50
2,745.0007,411.50
0.0000.00

0149                          8091.00 49.00275.00013,475.00
GRANULAR BACKFILL m3 275.00013,475.00
275.00013,475.00
0.0000.00

4001                          6210.34 45.660.0000.00
PAY CUT-OFF FOR 310 mm X 79 kg STEEL PILING m 10.190465.28
55.0602,514.04
0.0000.00

4010                          6210.44 153.400.0000.00
HP 310 mm X 79 kg, PILE SPLICES EACH20.0003,068.00
5.000767.00
0.0000.00

4011                          6005.39 386.000.0000.00
SHIM PLATE EACH5.0001,930.00
Furnish and Install Shim Plate 5.0001,930.00
0.0000.00

4018                          7312.00 13,230.000.0000.00
OVERHEAD SIGN SUPPORT, LOCATION NO. EACH1.00013,230.00
STA.118+51 RT. 1.00013,230.00
0.0000.00

4020                          A010.08 1,155.000.0000.00
LUMINAIRE, TYPE HPS-150 EACH1.0001,155.00
STA. 118+51 RT. 1.0001,155.00
0.0000.00

4022                          6210.32 40.200.0000.00
PAY CUT-OFF FOR 250 mm X 62 kg STEEL PILING m 20.000804.00
15.710631.54
0.0000.00

4023                          7320.05 650.000.0000.00
INSTALL OVERHEAD SIGN EACH1.000650.00
station 118+51 Rt. 1.000650.00
0.0000.00

GROUP 6B BRIDGE AT STA. 602+49.196Contracted761,434.27
Current782,736.55
In place776,804.80
This Estimate0.00

Totals for contractContracted5,026,696.99
Current5,094,828.59
In place5,196,524.57
This Estimate7,955.56