| | Detailed breakdown of stockpiled materials | |
|
|---|
| Est Nbr: | 0004 | | |
|
| Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
| 0082 | 6131.50 | EPOXY COATED REINFORCING STEEL | |
|
| | S.P. Initial Payment | 10,457.04 | 0001
|
| | SUBSTRUCTURE BRIDGE 6 | |
|
| 0084 | 6210.50 | PIPE PILING | |
|
| | S.P. Initial Payment | 21,428.55 | 133958
|
| | 6-PIPE PILING | |
|
| 0159 | 6210.50 | PIPE PILING | |
|
| | S.P. Initial Payment | 18,282.00 | 133474
|
| | 6A-PIPE PILING | |
|
| | Total for estimate 0004: | 50,167.59 |
|
| Est Nbr: | 0005 | | |
|
| Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
| 0025 | 1701.30 | 750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 | |
|
| | S.P. Initial Payment | 2,395.20 | 26-2911-00
|
| | 750 mm CMP | |
|
| 0026 | 1701.36 | 900 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 | |
|
| | S.P. Initial Payment | 1,623.28 | 26-2911-00
|
| | 900 mm CMP | |
|
| 0027 | 1705.42 | 1050 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE, TYPE 2,3,4 | |
|
| | S.P. Initial Payment | 1,805.12 | 26-2911-00
|
| | 1050 mm CMP | |
|
| 0078 | 6011.11 | PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | |
|
| | S.P. Initial Payment | 18,424.26 | 9400090682
|
| | Prestressed Girders | |
|
| 0082 | 6131.50 | EPOXY COATED REINFORCING STEEL | |
|
| | S.P. Adjustment | -1,110.78 | 0001
|
| | SUBSTRUCTURE BRIDGE 6 | |
|
| | Total for estimate 0005: | 23,137.08 |
|
| Est Nbr: | 0006 | | |
|
| Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
| 0084 | 6210.50 | PIPE PILING | |
|
| | S.P. Adjustment | -21,428.55 | 133958
|
| | 6-PIPE PILING | |
|
| | Total for estimate 0006: | -21,428.55 |
|
| Est Nbr: | 0007 | | |
|
| Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
| 0078 | 6011.11 | PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | |
|
| | S.P. Adjustment | -18,424.26 | 9400090682
|
| | Prestressed Girders | |
|
| 0082 | 6131.50 | EPOXY COATED REINFORCING STEEL | |
|
| | S.P. Adjustment | -3,923.26 | 0001
|
| | SUBSTRUCTURE BRIDGE 6 | |
|
| | Total for estimate 0007: | -22,347.52 |
|
| Est Nbr: | 0008 | | |
|
| Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
| 0025 | 1701.30 | 750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 | |
|
| | S.P. Adjustment | -1,197.60 | 26-2911-00
|
| | 750 mm CMP | |
|
| 0027 | 1705.42 | 1050 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE, TYPE 2,3,4 | |
|
| | S.P. Adjustment | -1,805.12 | 26-2911-00
|
| | 1050 mm CMP | |
|
| 0082 | 6131.50 | EPOXY COATED REINFORCING STEEL | |
|
| | S.P. Adjustment | -4,517.92 | 0001
|
| | SUBSTRUCTURE BRIDGE 6 | |
|
| 0103 | 6030.00 | PREPARATION OF BRIDGE | |
|
| | S.P. Initial Payment | 25,124.18 | 9400372139
|
| | Precast Beams Bridge 6A | |
|
| | S.P. Initial Payment | 25,124.18 | 9400372139
|
| | Precast Beams Bridge 6B | |
|
| | S.P. Initial Payment | 19,059.07 | 9400372139
|
| | Precast Beams Bridge 6C | |
|
| | Total for estimate 0008: | 61,786.79 |
|
| Est Nbr: | 0009 | | |
|
| Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
| 0026 | 1701.36 | 900 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 | |
|
| | S.P. Adjustment | -1,623.28 | 26-2911-00
|
| | 900 mm CMP | |
|
| 0082 | 6131.50 | EPOXY COATED REINFORCING STEEL | |
|
| | S.P. Adjustment | -905.08 | 0001
|
| | SUBSTRUCTURE BRIDGE 6 | |
|
| | Total for estimate 0009: | -2,528.36 |
|
| Est Nbr: | 0010 | | |
|
| Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
| 0093 | 3051.10 | EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | |
|
| | S.P. Initial Payment | 5,926.01 | 127864
|
| | Approaches 6A (TAB) | |
|
| 0102 | 6011.11 | PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | |
|
| | S.P. Initial Payment | 25,124.18 | 9400372139
|
| | Girders 6A | |
|
| 0103 | 6030.00 | PREPARATION OF BRIDGE | |
|
| | S.P. Closure | -25,124.18 | 9400372139
|
| | Precast Beams Bridge 6A | |
|
| | S.P. Closure | -25,124.18 | 9400372139
|
| | Precast Beams Bridge 6B | |
|
| | S.P. Closure | -19,059.07 | 9400372139
|
| | Precast Beams Bridge 6C | |
|
| 0127 | 6011.11 | PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | |
|
| | S.P. Initial Payment | 25,124.18 | 9400372139
|
| | Girders 6B | |
|
| 0153 | 6011.11 | PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | |
|
| | S.P. Initial Payment | 19,059.07 | 9400372139
|
| | Girders 6C | |
|
| | Total for estimate 0010: | 5,926.01 |
|
| Est Nbr: | 0011 | | |
|
| Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
| 0025 | 1701.30 | 750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 | |
|
| | S.P. Adjustment | -1,197.60 | 26-2911-00
|
| | 750 mm CMP | |
|
| | Total for estimate 0011: | -1,197.60 |
|
| Est Nbr: | 0013 | | |
|
| Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
| 0099 | 6005.60 | ELASTOMERIC BEARING | |
|
| | S.P. Initial Payment | 1,830.36 | 16346
|
| | BEARING PADS 6A REPLACEMENTS | |
|
| | S.P. Adjustment | -784.44 | 16346
|
| | BEARING PADS 6A REPLACEMENTS | |
|
| | S.P. Initial Payment | 633.52 | 16346
|
| | BEARING PADS 6A NEW | |
|
| | S.P. Adjustment | -475.14 | 16346
|
| | BEARING PADS 6A NEW | |
|
| 0102 | 6011.11 | PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | |
|
| | S.P. Adjustment | -12,562.09 | 9400372139
|
| | Girders 6A | |
|
| 0110 | 6510.55 | TEMPORARY BRIDGE SHORING | |
|
| | S.P. Initial Payment | 6,536.73 | 8892
|
| | SHEET PILING FOR SHORING | |
|
| 0124 | 6005.60 | ELASTOMERIC BEARING | |
|
| | S.P. Initial Payment | 1,830.36 | 16346
|
| | BEARING PAD 6B REPLACEMENTS | |
|
| | S.P. Initial Payment | 633.52 | 16346
|
| | BEARING PADS 6B NEW | |
|
| 0136 | 6510.55 | TEMPORARY BRIDGE SHORING | |
|
| | S.P. Initial Payment | 6,536.72 | 8892
|
| | SHEET PILE FOR SHORING | |
|
| 0150 | 6005.60 | ELASTOMERIC BEARING | |
|
| | S.P. Initial Payment | 633.52 | 16346
|
| | BEARING PADS 6C NEW | |
|
| | S.P. Initial Payment | 1,830.36 | 16346
|
| | BEARING PADS 6C REPLACEMENTS | |
|
| 0160 | 6510.55 | TEMPORARY BRIDGE SHORING | |
|
| | S.P. Initial Payment | 6,536.72 | 8892
|
| | SHEET PILING FOR SHORING | |
|
| | Total for estimate 0013: | 13,180.14 |
|
| Est Nbr: | 0014 | | |
|
| Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
| 0102 | 6011.11 | PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | |
|
| | S.P. Adjustment | -12,562.09 | 9400372139
|
| | Girders 6A | |
|
| | Total for estimate 0014: | -12,562.09 |
|
| | Total remaining for contract: | 94,133.49 |
|
|---|
| | | 1. Contracted
|
|---|
| | | 2. Current
|
|---|
| | | 3. To date
|
|---|
| Item Nbr Item Code | Unit Price | | 4. This Est
|
|---|
| Item Description | Units | Qty | Amount
|
|---|
| GROUP 1 GRADING | | |
|
| 0001 L006.00 | 264.29 | 4.000 | 1,057.16
|
| COVER CROP SEEDING | ha | 4.000 | 1,057.16
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0002 L020.00 | 1.61 | 2,197.000 | 3,537.17
|
| EROSION CONTROL | m2 | 2,197.000 | 3,537.17
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0003 L020.01 | 5.22 | 450.000 | 2,349.00
|
| EROSION CONTROL, TYPE A | m2 | 450.000 | 2,349.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0004 L020.08 | 5.22 | 3,786.000 | 19,762.92
|
| EROSION CONTROL, TYPE AA | m2 | 3,786.000 | 19,762.92
|
| | | 3,796.700 | 19,818.77
|
| | 0.000 | 0.00
|
| | |
|
| 0005 L021.01 | 13.91 | 35.000 | 486.85
|
| EROSION CHECKS, TYPE A | BALE | 35.000 | 486.85
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0006 L021.21 | 13.91 | 224.000 | 3,115.84
|
| EROSION CHECKS, TYPE AA | BALE | 224.000 | 3,115.84
|
| | | 63.000 | 876.33
|
| | 0.000 | 0.00
|
| | |
|
| 0007 L022.11 | 7.02 | 565.000 | 3,966.30
|
| FABRIC SILT FENCE-LOW POROSITY | m | 565.000 | 3,966.30
|
| | | 40.840 | 286.70
|
| | 0.000 | 0.00
|
| | |
|
| 0008 L022.75 | 16.05 | 255.000 | 4,092.75
|
| TEMPORARY SILT CHECK | m | 255.000 | 4,092.75
|
| | | 105.070 | 1,686.37
|
| | 0.000 | 0.00
|
| | |
|
| 0009 0030.10 | 19,500.00 | 1.000 | 19,500.00
|
| MOBILIZATION | LS | 1.000 | 19,500.00
|
| | | 1.000 | 19,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0010 1009.00 | 12,510.00 | 1.000 | 12,510.00
|
| GENERAL CLEARING AND GRUBBING | LS | 1.000 | 12,510.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0011 1010.00 | 3.31 | 21,044.000 | 69,655.64
|
| EXCAVATION | m3 | 18,704.000 | 61,910.24
|
| | | 11,000.000 | 36,410.00
|
| | 0.000 | 0.00
|
| | |
|
| 0012 1011.00 | 4.28 | 440.000 | 1,883.20
|
| WATER | kL | 440.000 | 1,883.20
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0013 1043.50 | 5.35 | 36.000 | 192.60
|
| RIPRAP FILTER FABRIC | m2 | 36.000 | 192.60
|
| | | 134.000 | 716.90
|
| | 134.000 | 716.90
|
| | |
|
| 0014 1090.00 | 1,605.00 | 1.000 | 1,605.00
|
| ABANDON WELLS | EACH | 1.000 | 1,605.00
|
| | | 1.000 | 1,605.00
|
| | 0.000 | 0.00
|
| | |
|
| 0015 1101.00 | 4.49 | 1,408.100 | 6,322.37
|
| REMOVE PAVEMENT | m2 | 1,408.100 | 6,322.37
|
| | | 342.700 | 1,538.72
|
| | 0.000 | 0.00
|
| | |
|
| 0016 1102.00 | 3.49 | 4,663.400 | 16,275.27
|
| REMOVE ASPHALT SURFACE | m2 | 4,663.400 | 16,275.27
|
| | | 4,176.000 | 14,574.24
|
| | 0.000 | 0.00
|
| | |
|
| 0017 1109.00 | 11.09 | 410.000 | 4,546.90
|
| REMOVE CURB | m | 410.000 | 4,546.90
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0018 1122.01 | 5.24 | 501.000 | 2,625.24
|
| REMOVE CONCRETE MEDIAN SURFACING | m2 | 501.000 | 2,625.24
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0019 1122.30 | 214.00 | 2.000 | 428.00
|
| REMOVE ISLAND NOSE | EACH | 2.000 | 428.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0020 1124.00 | 535.00 | 1.000 | 535.00
|
| REMOVE BUILDING | EACH | 1.000 | 535.00
|
| AT STA. 400+75 RT. | | 1.000 | 535.00
|
| | 0.000 | 0.00
|
| | |
|
| 0021 1124.01 | 535.00 | 1.000 | 535.00
|
| REMOVE BUILDING | EACH | 1.000 | 535.00
|
| AT STA. 401+00 RT. | | 1.000 | 535.00
|
| | 0.000 | 0.00
|
| | |
|
| 0022 1124.02 | 856.00 | 1.000 | 856.00
|
| REMOVE BUILDING | EACH | 1.000 | 856.00
|
| AT STA. 401+07 RT | | 1.000 | 856.00
|
| | 0.000 | 0.00
|
| | |
|
| 0023 1124.03 | 535.00 | 1.000 | 535.00
|
| REMOVE BUILDING | EACH | 1.000 | 535.00
|
| AT STA. 401+10 RT. | | 1.000 | 535.00
|
| | 0.000 | 0.00
|
| | |
|
| 0024 1125.00 | 3,210.00 | 1.000 | 3,210.00
|
| CLEAR TRACT | EACH | 1.000 | 3,210.00
|
| AT STA. 400+25 TO STA. 401+25 RT. | | 0.900 | 2,889.00
|
| | 0.000 | 0.00
|
| | |
|
| 0025 1701.30 | 114.45 | 48.000 | 5,493.60
|
| 750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 | m | 48.000 | 5,493.60
|
| | | 48.000 | 5,493.60
|
| | 0.000 | 0.00
|
| | |
|
| 0026 1701.36 | 123.49 | 27.000 | 3,334.23
|
| 900 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 | m | 27.000 | 3,334.23
|
| | | 27.000 | 3,334.23
|
| | 0.000 | 0.00
|
| | |
|
| 0027 1705.42 | 188.25 | 16.000 | 3,012.00
|
| 1050 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE, TYPE 2,3,4OR 5 | m | 16.000 | 3,012.00
|
| | | 16.000 | 3,012.00
|
| | 0.000 | 0.00
|
| | |
|
| 0028 6040.00 | 1,070.00 | 1.000 | 1,070.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 1,070.00
|
| AT STA. 47+15.21 RT. | | 1.000 | 1,070.00
|
| | 0.000 | 0.00
|
| | |
|
| 0029 6040.01 | 1,070.00 | 1.000 | 1,070.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 1,070.00
|
| AT STA. 51+92.29 RT. | | 1.000 | 1,070.00
|
| | 0.000 | 0.00
|
| | |
|
| 0030 6040.03 | 1,070.00 | 1.000 | 1,070.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 1,070.00
|
| AT STA. 54+18.65 RT. | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0031 6105.02 | 32.10 | 50.000 | 1,605.00
|
| ROCK RIPRAP, TYPE B | Mg | 50.000 | 1,605.00
|
| | | 129.000 | 4,140.90
|
| | 129.000 | 4,140.90
|
| | |
|
| 0032 7017.00 | 3.75 | 1,492.110 | 5,595.41
|
| REMOVE GUARDRAIL | m | 1,492.110 | 5,595.41
|
| | | 185.390 | 695.21
|
| | 62.800 | 235.50
|
| | |
|
| 4003 6952.02 | 6,411.18 | 0.000 | 0.00
|
| SHOO-FLY | EACH | 1.000 | 6,411.18
|
| BRIDGE 6CO/SA #001 | | 1.000 | 6,411.18
|
| | 0.000 | 0.00
|
| | |
|
| 4007 1014.00 | 105.72 | 0.000 | 0.00
|
| INSTALL RIGHT-OF-WAY MARKERS | EACH | 43.000 | 4,545.96
|
| CO/SA #5 | | 43.000 | 4,545.96
|
| | 0.000 | 0.00
|
| | |
|
| 4008 1013.00 | 62.28 | 0.000 | 0.00
|
| RESET RIGHT-OF-WAY MARKERS | EACH | 90.000 | 5,605.20
|
| STATE SUPPLIED R.O.W. MARKERSCO/SA #5 | | 30.000 | 1,868.40
|
| | 0.000 | 0.00
|
| | |
|
| 4009 2010.03 | 19.54 | 0.000 | 0.00
|
| CRUSHED ROCK SURFACE COURSE | Mg | 60.000 | 1,172.40
|
| CO/SA #5 | | 129.910 | 2,538.44
|
| | 0.000 | 0.00
|
| | |
|
| 4010 4976.05 | 205.80 | 0.000 | 0.00
|
| ADDITIONAL WORK | LS | 1.000 | 205.80
|
| 750mm Connecting Bands | | 1.000 | 205.80
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 1 GRADING | | Contracted | 201,833.45
|
| | Current | 212,028.59
|
| | In place | 136,748.75
|
| | This Estimate | 5,093.30
|
| | |
|
| GROUP 4 CULVERTS | | |
|
| 0033 P120.24 | 151.94 | 7.500 | 1,139.55
|
| 600 mm CULVERT PIPE, TYPE 2 | m | 7.500 | 1,139.55
|
| | | 7.000 | 1,063.58
|
| | 0.000 | 0.00
|
| | |
|
| 0034 P120.30 | 189.39 | 14.000 | 2,651.46
|
| 750 mm CULVERT PIPE, TYPE 2 | m | 14.000 | 2,651.46
|
| | | 14.000 | 2,651.46
|
| | 0.000 | 0.00
|
| | |
|
| 0035 P120.36 | 282.48 | 6.000 | 1,694.88
|
| 900 mm CULVERT PIPE, TYPE 2 | m | 6.000 | 1,694.88
|
| | | 4.500 | 1,271.16
|
| | 0.000 | 0.00
|
| | |
|
| 0036 P310.54 | 478.29 | 19.000 | 9,087.51
|
| 1350 mm CULVERT PIPE, TYPE 2,4 OR 5 | m | 19.000 | 9,087.51
|
| | | 19.000 | 9,087.51
|
| | 0.000 | 0.00
|
| | |
|
| 0037 P500.24 | 173.34 | 12.000 | 2,080.08
|
| 600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 | m | 0.000 | 0.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0038 P500.36 | 292.11 | 31.000 | 9,055.41
|
| 900 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 | m | 31.000 | 9,055.41
|
| | | 25.000 | 7,302.75
|
| | 0.000 | 0.00
|
| | |
|
| 0039 0030.40 | 2,354.00 | 1.000 | 2,354.00
|
| MOBILIZATION | LS | 1.000 | 2,354.00
|
| | | 1.000 | 2,354.00
|
| | 0.000 | 0.00
|
| | |
|
| 0040 4035.00 | 219.35 | 6.000 | 1,316.10
|
| REMOVE FLARED-END SECTION | EACH | 6.000 | 1,316.10
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0041 4040.00 | 1,792.25 | 2.000 | 3,584.50
|
| REMOVE HEADWALLS FROM CULVERTS | EACH | 2.000 | 3,584.50
|
| | | 1.000 | 1,792.25
|
| | 0.000 | 0.00
|
| | |
|
| 0042 4044.00 | 1,391.00 | 1.000 | 1,391.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 1,391.00
|
| AT STA. 80+80 | | 0.500 | 695.50
|
| | 0.000 | 0.00
|
| | |
|
| 0043 4045.00 | 4,772.20 | 1.000 | 4,772.20
|
| REMOVE STRUCTURE | EACH | 1.000 | 4,772.20
|
| AT STA. 500+17.7 | | 1.000 | 4,772.20
|
| | 0.000 | 0.00
|
| | |
|
| 0044 4050.01 | 12.84 | 620.000 | 7,960.80
|
| EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 620.000 | 7,960.80
|
| | | 620.000 | 7,960.80
|
| | 104.000 | 1,335.36
|
| | |
|
| 0045 4051.01 | 9.20 | 555.000 | 5,106.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 555.000 | 5,106.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0046 4101.06 | 391.62 | 75.390 | 29,524.23
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 75.390 | 29,524.23
|
| | | 61.002 | 23,889.61
|
| | 21.400 | 8,380.67
|
| | |
|
| 0047 4107.07 | 506.11 | 5.150 | 2,606.47
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS | m3 | 5.150 | 2,606.47
|
| | | 6.537 | 3,308.44
|
| | 0.000 | 0.00
|
| | |
|
| 0048 4151.00 | 1.78 | 4,425.000 | 7,876.50
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 4,425.000 | 7,876.50
|
| | | 4,004.280 | 7,127.62
|
| | 3,583.560 | 6,378.74
|
| | |
|
| 0049 4157.00 | 2.01 | 214.000 | 430.14
|
| REINFORCING STEEL FOR COLLARS | kg | 214.000 | 430.14
|
| | | 178.000 | 357.78
|
| | 0.000 | 0.00
|
| | |
|
| 0050 4310.24 | 527.51 | 5.000 | 2,637.55
|
| 600 mm FLARED-END SECTION | EACH | 5.000 | 2,637.55
|
| | | 3.000 | 1,582.53
|
| | 0.000 | 0.00
|
| | |
|
| 0051 4310.30 | 610.97 | 1.000 | 610.97
|
| 750 mm FLARED-END SECTION | EACH | 1.000 | 610.97
|
| | | 1.000 | 610.97
|
| | 0.000 | 0.00
|
| | |
|
| 0052 4310.36 | 796.08 | 4.000 | 3,184.32
|
| 900 mm FLARED-END SECTION | EACH | 4.000 | 3,184.32
|
| | | 3.000 | 2,388.24
|
| | 0.000 | 0.00
|
| | |
|
| 0053 4310.54 | 1,580.39 | 2.000 | 3,160.78
|
| 1350 mm FLARED-END SECTION | EACH | 2.000 | 3,160.78
|
| | | 2.000 | 3,160.78
|
| | 0.000 | 0.00
|
| | |
|
| 4004 4029.97 | 63.00 | 0.000 | 0.00
|
| REMOVE AND RELAY REINFORCED CONCRETE PIPE | m | 16.000 | 1,008.00
|
| | | 16.000 | 1,008.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4 CULVERTS | | Contracted | 102,224.45
|
| | Current | 101,152.37
|
| | In place | 82,385.18
|
| | This Estimate | 16,094.77
|
| | |
|
| GROUP 4A CONCRETE BOX CULVERT AT STA. 70+29 | | |
|
| 0054 0030.40 | 41,500.00 | 1.000 | 41,500.00
|
| MOBILIZATION | LS | 1.000 | 41,500.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0055 1102.00 | 6.42 | 994.000 | 6,381.48
|
| REMOVE ASPHALT SURFACE | m2 | 994.000 | 6,381.48
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0056 2020.50 | 49.70 | 327.000 | 16,251.90
|
| SURFACING | m2 | 327.000 | 16,251.90
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0057 4045.00 | 28,825.80 | 1.000 | 28,825.80
|
| REMOVE STRUCTURE | EACH | 1.000 | 28,825.80
|
| AT STA. 70+29 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0058 4051.01 | 21.40 | 2,500.000 | 53,500.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 2,500.000 | 53,500.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0059 4054.65 | 80,250.00 | 1.000 | 80,250.00
|
| TEMPORARY SHORING | LS | 1.000 | 80,250.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0060 4101.06 | 354.17 | 389.050 | 137,789.84
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 389.050 | 137,789.84
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0061 4151.00 | 1.50 | 24,694.000 | 37,041.00
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 24,694.000 | 37,041.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0062 9009.75 | 27.69 | 623.000 | 17,250.87
|
| TEMPORARY SURFACING | m2 | 623.000 | 17,250.87
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4A CONCRETE BOX CULVERT AT STA. 70+29 | | Contracted | 418,790.89
|
| | Current | 418,790.89
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 4B CONCRETE BOX CULVERT AT STA. 500+28 | | |
|
| 0063 0030.40 | 8,400.00 | 1.000 | 8,400.00
|
| MOBILIZATION | LS | 1.000 | 8,400.00
|
| | | 1.000 | 8,400.00
|
| | 0.000 | 0.00
|
| | |
|
| 0064 4051.01 | 12.84 | 1,460.000 | 18,746.40
|
| EXCAVATION FOR BOX CULVERTS | m3 | 1,519.740 | 19,513.46
|
| | | 1,519.740 | 19,513.46
|
| | 0.000 | 0.00
|
| | |
|
| 0065 4101.06 | 354.17 | 127.600 | 45,192.09
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 127.600 | 45,192.09
|
| | | 127.600 | 45,192.09
|
| | 0.000 | 0.00
|
| | |
|
| 0066 4151.00 | 1.50 | 7,959.000 | 11,938.50
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 7,959.000 | 11,938.50
|
| | | 7,959.000 | 11,938.50
|
| | 0.000 | 0.00
|
| | |
|
| 4005 2017.01 | 35.42 | 0.000 | 0.00
|
| CRUSHED ROCK | m3 | 86.220 | 3,053.91
|
| Sta. 500+28 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 4006 2017.01 | 35.42 | 0.000 | 0.00
|
| CRUSHED ROCK | m3 | 86.220 | 3,053.91
|
| Sta. 500+28 | | 86.220 | 3,053.91
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4B CONCRETE BOX CULVERT AT STA. 500+28 | | Contracted | 84,276.99
|
| | Current | 91,151.88
|
| | In place | 88,097.96
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 6 BRIDGE AT STA. 22+73.609 | | |
|
| 0067 0020.00 | 0.80 | 500.000 | 400.00
|
| TRAINING | HOUR | 500.000 | 400.00
|
| | | 386.500 | 309.20
|
| | 281.000 | 224.80
|
| | |
|
| 0068 0030.60 | 41,500.00 | 1.000 | 41,500.00
|
| MOBILIZATION | LS | 1.000 | 41,500.00
|
| | | 1.000 | 41,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0069 1010.01 | 6.46 | 1,430.000 | 9,237.80
|
| EXCAVATION (ESTABLISHED QUANTITY) | m3 | 1,430.000 | 9,237.80
|
| | | 1,430.000 | 9,237.80
|
| | 0.000 | 0.00
|
| | |
|
| 0070 1043.50 | 2.40 | 1,029.000 | 2,469.60
|
| RIPRAP FILTER FABRIC | m2 | 1,029.000 | 2,469.60
|
| | | 603.800 | 1,449.12
|
| | 0.000 | 0.00
|
| | |
|
| 0071 3050.15 | 299.87 | 141.300 | 42,371.63
|
| CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 | m3 | 141.300 | 42,371.63
|
| | | 141.300 | 42,371.63
|
| | 0.000 | 0.00
|
| | |
|
| 0072 3051.10 | 1.56 | 9,233.000 | 14,403.48
|
| EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | kg | 9,233.000 | 14,403.48
|
| | | 9,233.000 | 14,403.48
|
| | 0.000 | 0.00
|
| | |
|
| 0073 6000.10 | 2,309.38 | 1.000 | 2,309.38
|
| ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 1.000 | 2,309.38
|
| | 0.000 | 0.00
|
| | |
|
| 0074 6000.11 | 2,309.38 | 1.000 | 2,309.38
|
| ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 1.000 | 2,309.38
|
| | 0.000 | 0.00
|
| | |
|
| 0075 6005.60 | 296.63 | 16.000 | 4,746.08
|
| ELASTOMERIC BEARING | EACH | 16.000 | 4,746.08
|
| | | 16.000 | 4,746.08
|
| | 0.000 | 0.00
|
| | |
|
| 0076 6010.22 | 854.08 | 48.000 | 40,995.84
|
| CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 48.000 | 40,995.84
|
| | | 48.810 | 41,687.65
|
| | 0.000 | 0.00
|
| | |
|
| 0077 6010.26 | 554.43 | 103.800 | 57,549.83
|
| CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 103.800 | 57,549.83
|
| | | 103.800 | 57,549.84
|
| | 0.000 | 0.00
|
| | |
|
| 0078 6011.11 | 28,217.18 | 1.000 | 28,217.18
|
| PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | LS | 1.000 | 28,217.18
|
| AT STA. 22+73.609 | | 1.000 | 28,217.18
|
| | 0.000 | 0.00
|
| | |
|
| 0079 6030.00 | 42,110.92 | 1.000 | 42,110.92
|
| PREPARATION OF BRIDGE | EACH | 1.000 | 42,110.92
|
| AT STA. 22+73.609 | | 1.000 | 42,110.92
|
| | 0.000 | 0.00
|
| | |
|
| 0080 6081.00 | 36.35 | 29.000 | 1,054.15
|
| STRUCTURAL STEEL FOR SUPERSTRUCTURE | kg | 29.000 | 1,054.15
|
| | | 29.000 | 1,054.15
|
| | 0.000 | 0.00
|
| | |
|
| 0081 6105.02 | 27.92 | 988.000 | 27,584.96
|
| ROCK RIPRAP, TYPE B | Mg | 988.000 | 27,584.96
|
| | | 581.000 | 16,221.52
|
| | 0.000 | 0.00
|
| | |
|
| 0082 6131.50 | 1.87 | 14,408.000 | 26,942.96
|
| EPOXY COATED REINFORCING STEEL | kg | 14,408.000 | 26,942.96
|
| | | 15,002.000 | 28,053.74
|
| | 0.000 | 0.00
|
| | |
|
| 0083 6139.50 | 30.16 | 50.600 | 1,526.10
|
| SUBSURFACE DRAINAGE MATTING | m2 | 50.600 | 1,526.10
|
| | | 50.600 | 1,526.10
|
| | 0.000 | 0.00
|
| | |
|
| 0084 6210.50 | 78.94 | 468.600 | 36,991.28
|
| PIPE PILING | m | 468.600 | 36,991.28
|
| | | 499.800 | 39,454.21
|
| | 0.000 | 0.00
|
| | |
|
| 0085 6510.55 | 23,703.92 | 1.000 | 23,703.92
|
| TEMPORARY BRIDGE SHORING | LS | 0.000 | 0.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0086 6616.65 | 528.11 | 12.000 | 6,337.32
|
| BEARING DEVICE REPLACEMENT | EACH | 12.000 | 6,337.32
|
| | | 12.000 | 6,337.32
|
| | 0.000 | 0.00
|
| | |
|
| 0087 8091.00 | 30.10 | 155.300 | 4,674.53
|
| GRANULAR BACKFILL | m3 | 155.300 | 4,674.53
|
| | | 155.300 | 4,674.53
|
| | 0.000 | 0.00
|
| | |
|
| 4002 6952.02 | 19,554.07 | 0.000 | 0.00
|
| SHOO-FLY | EACH | 1.000 | 19,554.07
|
| BRIDGE 6CO/SA #001 | | 1.000 | 19,554.07
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 6 BRIDGE AT STA. 22+73.609 | | Contracted | 417,436.35
|
| | Current | 413,286.50
|
| | In place | 405,077.30
|
| | This Estimate | 224.80
|
| | |
|
| GROUP 6A BRIDGE AT STA. 35+42.651 | | |
|
| 0088 0020.00 | 0.80 | 500.000 | 400.00
|
| TRAINING | HOUR | 500.000 | 400.00
|
| | | 399.000 | 319.20
|
| | 399.000 | 319.20
|
| | |
|
| 0089 0030.60 | 49,000.00 | 1.000 | 49,000.00
|
| MOBILIZATION | LS | 1.000 | 49,000.00
|
| | | 1.000 | 49,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0090 1010.01 | 3.91 | 2,365.000 | 9,247.15
|
| EXCAVATION (ESTABLISHED QUANTITY) | m3 | 2,365.000 | 9,247.15
|
| | | 2,000.000 | 7,820.00
|
| | 500.000 | 1,955.00
|
| | |
|
| 0091 1043.50 | 2.34 | 1,102.000 | 2,578.68
|
| RIPRAP FILTER FABRIC | m2 | 1,102.000 | 2,578.68
|
| | | 500.000 | 1,170.00
|
| | 500.000 | 1,170.00
|
| | |
|
| 0092 3050.15 | 299.87 | 141.600 | 42,461.59
|
| CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 | m3 | 141.600 | 42,461.59
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0093 3051.10 | 1.55 | 9,303.000 | 14,419.65
|
| EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | kg | 9,303.000 | 14,419.65
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0094 6000.10 | 2,309.38 | 1.000 | 2,309.38
|
| ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 1.000 | 2,309.38
|
| | 0.000 | 0.00
|
| | |
|
| 0095 6000.11 | 2,309.38 | 1.000 | 2,309.38
|
| ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 1.000 | 2,309.38
|
| | 0.000 | 0.00
|
| | |
|
| 0096 6000.20 | 2,309.38 | 1.000 | 2,309.38
|
| PIER NO.1 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 1.000 | 2,309.38
|
| | 0.000 | 0.00
|
| | |
|
| 0097 6000.21 | 2,309.38 | 1.000 | 2,309.38
|
| PIER NO.2 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 1.000 | 2,309.38
|
| | 0.000 | 0.00
|
| | |
|
| 0098 6005.35 | 163.43 | 29.800 | 4,870.21
|
| PRECOMPRESSED POLYURETHANE FOAM JOINT | m | 29.800 | 4,870.21
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0099 6005.60 | 218.96 | 22.000 | 4,817.12
|
| ELASTOMERIC BEARING | EACH | 22.000 | 4,817.12
|
| | | 6.000 | 1,313.76
|
| | 0.000 | 0.00
|
| | |
|
| 0100 6010.22 | 484.14 | 100.200 | 48,510.83
|
| CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 100.200 | 48,510.83
|
| | | 72.900 | 35,293.80
|
| | 0.000 | 0.00
|
| | |
|
| 0101 6010.26 | 457.82 | 162.900 | 74,578.88
|
| CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 162.900 | 74,578.88
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0102 6011.11 | 33,727.68 | 1.000 | 33,727.68
|
| PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | LS | 1.000 | 33,727.68
|
| AT STA. 35+42.651 | | 1.000 | 33,727.68
|
| | 0.000 | 0.00
|
| | |
|
| 0103 6030.00 | 46,371.66 | 1.000 | 46,371.66
|
| PREPARATION OF BRIDGE | EACH | 1.000 | 46,371.66
|
| AT STA. 35+42.651 | | 0.800 | 37,097.32
|
| | 0.400 | 18,548.66
|
| | |
|
| 0104 6080.00 | 6.42 | 564.000 | 3,620.88
|
| STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 564.000 | 3,620.88
|
| | | 564.000 | 3,620.88
|
| | 0.000 | 0.00
|
| | |
|
| 0105 6081.00 | 6.42 | 94.000 | 603.48
|
| STRUCTURAL STEEL FOR SUPERSTRUCTURE | kg | 94.000 | 603.48
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0106 6105.02 | 27.31 | 1,058.000 | 28,893.98
|
| ROCK RIPRAP, TYPE B | Mg | 1,058.000 | 28,893.98
|
| | | 159.050 | 4,343.66
|
| | 0.000 | 0.00
|
| | |
|
| 0107 6131.50 | 1.29 | 24,171.000 | 31,180.59
|
| EPOXY COATED REINFORCING STEEL | kg | 24,171.000 | 31,180.59
|
| | | 3,797.000 | 4,898.13
|
| | 0.000 | 0.00
|
| | |
|
| 0108 6139.50 | 30.39 | 48.600 | 1,476.95
|
| SUBSURFACE DRAINAGE MATTING | m2 | 48.600 | 1,476.95
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0109 6200.00 | 86.28 | 594.000 | 51,250.32
|
| CONCRETE PILING | m | 594.000 | 51,250.32
|
| | | 316.800 | 27,333.50
|
| | 0.000 | 0.00
|
| | |
|
| 0110 6510.55 | 24,995.68 | 1.000 | 24,995.68
|
| TEMPORARY BRIDGE SHORING | LS | 1.000 | 24,995.68
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0111 6616.65 | 528.11 | 10.000 | 5,281.10
|
| BEARING DEVICE REPLACEMENT | EACH | 10.000 | 5,281.10
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0112 8091.00 | 31.92 | 137.800 | 4,398.58
|
| GRANULAR BACKFILL | m3 | 137.800 | 4,398.58
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 6A BRIDGE AT STA. 35+42.651 | | Contracted | 491,922.53
|
| | Current | 491,922.53
|
| | In place | 215,175.45
|
| | This Estimate | 21,992.86
|
| | |
|
| GROUP 6B BRIDGE AT STA. 43+91.371 | | |
|
| 0113 0020.00 | 0.80 | 500.000 | 400.00
|
| TRAINING | HOUR | 500.000 | 400.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0114 0030.60 | 51,000.00 | 1.000 | 51,000.00
|
| MOBILIZATION | LS | 1.000 | 51,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0115 1010.01 | 3.87 | 2,385.000 | 9,229.95
|
| EXCAVATION (ESTABLISHED QUANTITY) | m3 | 2,385.000 | 9,229.95
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0116 1043.50 | 2.14 | 1,230.000 | 2,632.20
|
| RIPRAP FILTER FABRIC | m2 | 1,230.000 | 2,632.20
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0117 3050.15 | 299.87 | 141.500 | 42,431.61
|
| CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 | m3 | 141.500 | 42,431.61
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0118 3051.10 | 2.14 | 9,303.000 | 19,908.42
|
| EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | kg | 9,303.000 | 19,908.42
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0119 6000.10 | 2,309.38 | 1.000 | 2,309.38
|
| ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0120 6000.11 | 2,309.38 | 1.000 | 2,309.38
|
| ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0121 6000.60 | 2,309.38 | 1.000 | 2,309.38
|
| PIER NO.1 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0122 6000.61 | 2,309.38 | 1.000 | 2,309.38
|
| PIER NO.2 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0123 6005.35 | 166.04 | 29.800 | 4,947.99
|
| PRECOMPRESSED POLYURETHANE FOAM JOINT | m | 29.800 | 4,947.99
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0124 6005.60 | 218.96 | 22.000 | 4,817.12
|
| ELASTOMERIC BEARING | EACH | 22.000 | 4,817.12
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0125 6010.22 | 454.39 | 109.800 | 49,892.02
|
| CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 109.800 | 49,892.02
|
| | | 13.235 | 6,013.85
|
| | 13.235 | 6,013.85
|
| | |
|
| 0126 6010.26 | 445.60 | 169.500 | 75,529.20
|
| CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 169.500 | 75,529.20
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0127 6011.11 | 33,727.68 | 1.000 | 33,727.68
|
| PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | LS | 1.000 | 33,727.68
|
| AT STA. 43+91.371 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0128 6030.00 | 46,371.66 | 1.000 | 46,371.66
|
| PREPARATION OF BRIDGE | EACH | 1.000 | 46,371.66
|
| AT STA. 43+91.371 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0129 6080.00 | 16.05 | 652.000 | 10,464.60
|
| STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 652.000 | 10,464.60
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0130 6081.00 | 12.84 | 94.000 | 1,206.96
|
| STRUCTURAL STEEL FOR SUPERSTRUCTURE | kg | 94.000 | 1,206.96
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0131 6105.02 | 27.66 | 1,017.000 | 28,130.22
|
| ROCK RIPRAP, TYPE B | Mg | 1,017.000 | 28,130.22
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0132 6105.03 | 32.66 | 164.000 | 5,356.24
|
| ROCK RIPRAP, TYPE C | Mg | 164.000 | 5,356.24
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0133 6131.50 | 1.29 | 24,566.000 | 31,690.14
|
| EPOXY COATED REINFORCING STEEL | kg | 24,566.000 | 31,690.14
|
| | | 675.000 | 870.75
|
| | 675.000 | 870.75
|
| | |
|
| 0134 6139.50 | 30.70 | 49.600 | 1,522.72
|
| SUBSURFACE DRAINAGE MATTING | m2 | 49.600 | 1,522.72
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0135 6200.00 | 86.04 | 561.000 | 48,268.44
|
| CONCRETE PILING | m | 561.000 | 48,268.44
|
| | | 152.400 | 13,112.50
|
| | 152.400 | 13,112.50
|
| | |
|
| 0136 6510.55 | 25,086.90 | 1.000 | 25,086.90
|
| TEMPORARY BRIDGE SHORING | LS | 1.000 | 25,086.90
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0137 6616.65 | 528.11 | 10.000 | 5,281.10
|
| BEARING DEVICE REPLACEMENT | EACH | 10.000 | 5,281.10
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0138 8091.00 | 31.70 | 140.100 | 4,441.17
|
| GRANULAR BACKFILL | m3 | 140.100 | 4,441.17
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 6B BRIDGE AT STA. 43+91.371 | | Contracted | 511,573.86
|
| | Current | 511,573.86
|
| | In place | 19,997.10
|
| | This Estimate | 19,997.10
|
| | |
|
| GROUP 6C BRIDGE AT STA. 61+83.515 | | |
|
| 0139 0020.00 | 0.80 | 500.000 | 400.00
|
| TRAINING | HOUR | 500.000 | 400.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0140 0030.60 | 47,000.00 | 1.000 | 47,000.00
|
| MOBILIZATION | LS | 1.000 | 47,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0141 1010.01 | 6.89 | 1,340.000 | 9,232.60
|
| EXCAVATION (ESTABLISHED QUANTITY) | m3 | 1,340.000 | 9,232.60
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0142 1043.50 | 3.09 | 718.000 | 2,218.62
|
| RIPRAP FILTER FABRIC | m2 | 718.000 | 2,218.62
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0143 3050.15 | 299.87 | 141.400 | 42,401.62
|
| CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 | m3 | 141.400 | 42,401.62
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0144 3051.10 | 2.14 | 9,265.000 | 19,827.10
|
| EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | kg | 9,265.000 | 19,827.10
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0145 6000.10 | 2,309.38 | 1.000 | 2,309.38
|
| ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0146 6000.11 | 2,309.38 | 1.000 | 2,309.38
|
| ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0147 6000.60 | 2,309.38 | 1.000 | 2,309.38
|
| PIER NO.1 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0148 6000.61 | 2,309.38 | 1.000 | 2,309.38
|
| PIER NO.2 EXCAVATION | LS | 1.000 | 2,309.38
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0149 6005.35 | 168.43 | 28.990 | 4,882.79
|
| PRECOMPRESSED POLYURETHANE FOAM JOINT | m | 28.990 | 4,882.79
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0150 6005.60 | 218.96 | 22.000 | 4,817.12
|
| ELASTOMERIC BEARING | EACH | 22.000 | 4,817.12
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0151 6010.22 | 446.72 | 131.000 | 58,520.32
|
| CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 131.000 | 58,520.32
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0152 6010.26 | 481.34 | 132.800 | 63,921.95
|
| CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 132.800 | 63,921.95
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0153 6011.11 | 20,437.00 | 1.000 | 20,437.00
|
| PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | LS | 1.000 | 20,437.00
|
| AT STA. 61+83.515 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0154 6030.00 | 49,046.66 | 1.000 | 49,046.66
|
| PREPARATION OF BRIDGE | EACH | 1.000 | 49,046.66
|
| AT STA. 61+83.515 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0155 6105.02 | 29.75 | 620.000 | 18,445.00
|
| ROCK RIPRAP, TYPE B | Mg | 620.000 | 18,445.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0156 6105.03 | 52.54 | 68.000 | 3,572.72
|
| ROCK RIPRAP, TYPE C | Mg | 68.000 | 3,572.72
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0157 6131.50 | 1.29 | 21,803.000 | 28,125.87
|
| EPOXY COATED REINFORCING STEEL | kg | 21,803.000 | 28,125.87
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0158 6139.50 | 32.22 | 47.000 | 1,514.34
|
| SUBSURFACE DRAINAGE MATTING | m2 | 47.000 | 1,514.34
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0159 6210.50 | 71.05 | 753.000 | 53,500.65
|
| PIPE PILING | m | 753.000 | 53,500.65
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0160 6510.55 | 24,233.57 | 1.000 | 24,233.57
|
| TEMPORARY BRIDGE SHORING | LS | 1.000 | 24,233.57
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0161 6616.65 | 528.11 | 10.000 | 5,281.10
|
| BEARING DEVICE REPLACEMENT | EACH | 10.000 | 5,281.10
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0162 8091.00 | 31.66 | 140.500 | 4,448.23
|
| GRANULAR BACKFILL | m3 | 140.500 | 4,448.23
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 6C BRIDGE AT STA. 61+83.515 | | Contracted | 471,064.78
|
| | Current | 471,064.78
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 7 GUARDRAIL | | |
|
| 0163 0030.70 | 1,078.46 | 1.000 | 1,078.46
|
| MOBILIZATION | LS | 1.000 | 1,078.46
|
| | | 0.769 | 829.58
|
| | 0.000 | 0.00
|
| | |
|
| 0164 7001.50 | 524.30 | 4.000 | 2,097.20
|
| CULVERT MOUNTED GUARDRAIL POST | EACH | 4.000 | 2,097.20
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0165 7011.20 | 40.39 | 474.360 | 19,159.40
|
| W-BEAM GUARDRAIL | m | 474.360 | 19,159.40
|
| | | 45.720 | 1,846.64
|
| | 0.000 | 0.00
|
| | |
|
| 0166 7015.00 | 24.61 | 425.000 | 10,459.25
|
| CABLE GUARDRAIL | m | 425.000 | 10,459.25
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0167 7019.50 | 15,220.75 | 1.000 | 15,220.75
|
| IMPACT ATTENUATOR | EACH | 1.000 | 15,220.75
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0168 7020.00 | 1,016.50 | 15.000 | 15,247.50
|
| BRIDGE APPROACH SECTIONS | EACH | 15.000 | 15,247.50
|
| | | 4.000 | 4,066.00
|
| | 0.000 | 0.00
|
| | |
|
| 0169 7023.00 | 1,605.00 | 4.000 | 6,420.00
|
| TERMINAL ANCHORAGE SECTIONS | EACH | 4.000 | 6,420.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0170 7024.27 | 1,471.25 | 25.000 | 36,781.25
|
| GUARDRAIL END TREATMENT, TYPE II | EACH | 25.000 | 36,781.25
|
| | | 4.000 | 5,885.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 7 GUARDRAIL | | Contracted | 106,463.81
|
| | Current | 106,463.81
|
| | In place | 12,627.22
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 8B ELECTRICAL | | |
|
| 0171 A001.12 | 321.00 | 2.000 | 642.00
|
| PULL BOX, TYPE PB-5 | EACH | 2.000 | 642.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0172 A009.16 | 2,270.54 | 4.000 | 9,082.16
|
| STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.20 | EACH | 4.000 | 9,082.16
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0173 A020.10 | 1,284.00 | 1.000 | 1,284.00
|
| LIGHTING CONTROL CENTER, TYPE D | EACH | 1.000 | 1,284.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0174 A070.10 | 6.42 | 146.000 | 937.32
|
| 38 mm CONDUIT IN TRENCH | m | 146.000 | 937.32
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0175 A074.12 | 48.15 | 42.000 | 2,022.30
|
| 38 mm CONDUIT, JACKED | m | 42.000 | 2,022.30
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0176 A080.22 | 1.61 | 188.000 | 302.68
|
| STREET LIGHTING CABLE, NO. 6 BARE | m | 188.000 | 302.68
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0177 A080.24 | 3.21 | 376.000 | 1,206.96
|
| STREET LIGHTING CABLE, NO. 6 USE | m | 376.000 | 1,206.96
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0178 0030.81 | 1,337.50 | 1.000 | 1,337.50
|
| MOBILIZATION | LS | 1.000 | 1,337.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 8B ELECTRICAL | | Contracted | 16,814.92
|
| | Current | 16,814.92
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 9 BITUMINOUS | | |
|
| 0179 L001.01 | 1,543.49 | 3.000 | 4,630.47
|
| SEEDING, TYPE A | ha | 3.000 | 4,630.47
|
| | | 1.320 | 2,037.41
|
| | 0.000 | 0.00
|
| | |
|
| 0180 L001.02 | 976.40 | 1.000 | 976.40
|
| SEEDING, TYPE B | ha | 1.000 | 976.40
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0181 L032.75 | 74.90 | 18.000 | 1,348.20
|
| MULCH | Mg | 18.000 | 1,348.20
|
| | | 11.620 | 870.34
|
| | 0.000 | 0.00
|
| | |
|
| 0182 0002.55 | 24.08 | 289.860 | 6,979.83
|
| OVERLAY BROKEN LINES | StaM | 289.860 | 6,979.83
|
| | | 1.830 | 44.07
|
| | 0.000 | 0.00
|
| | |
|
| 0183 0002.60 | 24.08 | 579.720 | 13,959.66
|
| OVERLAY SOLID LINES | StaM | 579.720 | 13,959.66
|
| | | 31.830 | 766.47
|
| | 0.000 | 0.00
|
| | |
|
| 0184 0030.90 | 25,980.67 | 1.000 | 25,980.67
|
| MOBILIZATION | LS | 1.000 | 25,980.67
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0185 2001.03 | 26.12 | 56.000 | 1,462.72
|
| GRAVEL SURFACE COURSE | Mg | 56.000 | 1,462.72
|
| | | 132.260 | 3,454.63
|
| | 0.000 | 0.00
|
| | |
|
| 0186 2021.00 | 53.50 | 13.000 | 695.50
|
| MAILBOX POST | EACH | 13.000 | 695.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0187 3040.12 | 151.57 | 50.100 | 7,593.66
|
| CONCRETE PAVEMENT REPAIR, TYPE B, FULL DEPTH | m2 | 50.100 | 7,593.66
|
| | | 2.000 | 303.14
|
| | 0.000 | 0.00
|
| | |
|
| 0188 3040.13 | 139.80 | 114.300 | 15,979.14
|
| CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH | m2 | 114.300 | 15,979.14
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0189 3221.05 | 123.16 | 413.900 | 50,975.92
|
| CONCRETE PAVEMENT, CLASS PR-25 | m2 | 413.900 | 50,975.92
|
| JOINT REPAIR | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0190 9000.75 | 14.23 | 100.000 | 1,423.00
|
| ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | Mg | 100.000 | 1,423.00
|
| SPS | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0191 9005.00 | 39.22 | 300.000 | 11,766.00
|
| ASPHALTIC CONCRETE FOR PATCHING, TYPE | Mg | 300.000 | 11,766.00
|
| SP4(12.5) | | 188.200 | 7,381.20
|
| | 0.000 | 0.00
|
| | |
|
| 0192 9005.23 | 19.25 | 7,490.000 | 144,182.50
|
| ASPHALTIC CONCRETE, TYPE SPS | Mg | 7,490.000 | 144,182.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0193 9005.45 | 23.01 | 19,950.000 | 459,049.50
|
| ASPHALTIC CONCRETE, TYPE SP4(12.5) | Mg | 19,950.000 | 459,049.50
|
| | | 1,940.310 | 44,646.53
|
| | 0.000 | 0.00
|
| | |
|
| 0194 9009.00 | 3.21 | 3,910.000 | 12,551.10
|
| PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS | m2 | 3,910.000 | 12,551.10
|
| | | 409.200 | 1,313.53
|
| | 0.000 | 0.00
|
| | |
|
| 0195 9020.92 | 212.93 | 5.400 | 1,149.82
|
| PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING | Mg | 5.400 | 1,149.82
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0196 9021.01 | 212.93 | 1,093.500 | 232,838.96
|
| PERFORMANCE GRADED BINDER (64-22) | Mg | 1,093.500 | 232,838.96
|
| | | 77.690 | 16,542.53
|
| | 77.690 | 16,542.53
|
| | |
|
| 0197 9021.03 | 212.93 | 404.460 | 86,121.67
|
| PERFORMANCE GRADED BINDER (58-28) | Mg | 404.460 | 86,121.67
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0198 9034.00 | 3.21 | 614.000 | 1,970.94
|
| PREPARATION OF INTERSECTIONS AND DRIVEWAYS | m2 | 614.000 | 1,970.94
|
| | | 204.600 | 656.77
|
| | -204.600 | -656.77
|
| | |
|
| 0199 9053.00 | 0.24 | 93,760.000 | 22,502.40
|
| TACK COAT | L | 93,760.000 | 22,502.40
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0200 9111.00 | 2.85 | 614.000 | 1,749.90
|
| WATER | kL | 614.000 | 1,749.90
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0201 9170.00 | 168.92 | 181.870 | 30,721.48
|
| EARTH SHOULDER CONSTRUCTION | StaM | 181.870 | 30,721.48
|
| | | 10.378 | 1,753.05
|
| | 0.000 | 0.00
|
| | |
|
| 0202 9173.00 | 1,086.39 | 5.680 | 6,170.70
|
| SUBGRADE PREPARATION | StaM | 5.680 | 6,170.70
|
| | | 4.230 | 4,595.43
|
| | 0.000 | 0.00
|
| | |
|
| 0203 9173.20 | 3.48 | 508.000 | 1,767.84
|
| SUBGRADE PREPARATION | m2 | 508.000 | 1,767.84
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0204 9179.23 | 552.12 | 93.721 | 51,745.24
|
| COLD MILLING, CLASS 3 | StaM | 93.721 | 51,745.24
|
| | | 1.150 | 634.94
|
| | 0.000 | 0.00
|
| | |
|
| 0205 9188.50 | 16.75 | 2,908.000 | 48,709.00
|
| SURFACING UNDER GUARDRAIL | m2 | 2,908.000 | 48,709.00
|
| | | 379.500 | 6,356.63
|
| | 0.000 | 0.00
|
| | |
|
| 0206 9300.52 | 3,210.00 | 1.000 | 3,210.00
|
| ASPHALT PAVEMENT SMOOTHNESS TESTING I/D | LS | 1.000 | 3,210.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 9 BITUMINOUS | | Contracted | 1,248,212.21
|
| | Current | 1,248,212.21
|
| | In place | 91,356.67
|
| | This Estimate | 15,885.76
|
| | |
|
| GROUP 10 GENERAL ITEMS | | |
|
| 0207 0001.08 | 0.50 | 26,000.000 | 13,000.00
|
| BARRICADE, TYPE II | BDAY | 26,000.000 | 13,000.00
|
| | | 6,580.000 | 3,290.00
|
| | 797.000 | 398.50
|
| | |
|
| 0208 0001.10 | 2.14 | 5,978.000 | 12,792.92
|
| BARRICADE, TYPE III | BDAY | 5,978.000 | 12,792.92
|
| | | 5,477.000 | 11,720.78
|
| | 556.000 | 1,189.84
|
| | |
|
| 0209 0001.75 | 5.35 | 560.000 | 2,996.00
|
| TEMPORARY SIGN DAY | EACH | 560.000 | 2,996.00
|
| | | 4.000 | 21.40
|
| | 0.000 | 0.00
|
| | |
|
| 0210 0001.90 | 0.27 | 38,544.000 | 10,406.88
|
| SIGN DAY | EACH | 38,544.000 | 10,406.88
|
| | | 9,227.000 | 2,491.29
|
| | 1,043.000 | 281.61
|
| | |
|
| 0211 0002.30 | 2.14 | 700.000 | 1,498.00
|
| PAVEMENT MARKING REMOVAL | m | 700.000 | 1,498.00
|
| | | 260.000 | 556.40
|
| | 186.000 | 398.04
|
| | |
|
| 0212 0002.44 | 1.07 | 10,000.000 | 10,700.00
|
| TEMPORARY PAVEMENT MARKING, TYPE PAINT | m | 10,000.000 | 10,700.00
|
| | | 10,202.200 | 10,916.35
|
| | 3,134.200 | 3,353.59
|
| | |
|
| 0213 0002.47 | 0.27 | 700.000 | 189.00
|
| TEMPORARY PAVEMENT MARKING SURFACE PREPARATION | m | 700.000 | 189.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0214 0003.10 | 274.39 | 80.000 | 21,951.20
|
| FLAGGING | DAY | 80.000 | 21,951.20
|
| | | 6.000 | 1,646.36
|
| | 2.000 | 548.78
|
| | |
|
| 0215 0003.20 | 399.11 | 30.000 | 11,973.30
|
| FURNISHING AND OPERATING PILOT VEHICLE | DAY | 30.000 | 11,973.30
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0216 0003.51 | 25.68 | 374.000 | 9,604.32
|
| INSTALL CONCRETE PROTECTION BARRIER | m | 209.000 | 5,367.12
|
| | | 168.000 | 4,314.24
|
| | 168.000 | 4,314.24
|
| | |
|
| 0217 0003.56 | 10.16 | 1,026.000 | 10,424.16
|
| RELOCATE CONCRETE PROTECTION BARRIER | m | 861.000 | 8,747.76
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0218 0003.75 | 11,235.00 | 4.000 | 44,940.00
|
| TEMPORARY TRAFFIC SIGNAL | EACH | 3.000 | 33,705.00
|
| | | 2.000 | 22,470.00
|
| | 0.000 | 0.00
|
| | |
|
| 0219 0010.04 | 4,012.50 | 1.000 | 4,012.50
|
| FIELD OFFICE | EACH | 1.000 | 4,012.50
|
| | | 1.000 | 4,012.50
|
| | 0.000 | 0.00
|
| | |
|
| 0220 0030.00 | 10,225.56 | 1.000 | 10,225.56
|
| MOBILIZATION | LS | 1.000 | 10,225.56
|
| | | 0.743 | 7,603.62
|
| | 0.000 | 0.00
|
| | |
|
| 0221 9110.01 | 82.71 | 40.000 | 3,308.40
|
| RENTAL OF LOADER, FULLY OPERATED | HOUR | 40.000 | 3,308.40
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0222 9110.02 | 71.33 | 30.000 | 2,139.90
|
| RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 30.000 | 2,139.90
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0223 9110.03 | 55.96 | 40.000 | 2,238.40
|
| RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 40.000 | 2,238.40
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0224 9110.07 | 40.13 | 40.000 | 1,605.20
|
| RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 40.000 | 1,605.20
|
| | | 34.250 | 1,374.45
|
| | 0.000 | 0.00
|
| | |
|
| 4000 0025.10 | 4,264.05 | 0.000 | 0.00
|
| VALUE ENGINEERING ADJUSTMENT | LS | 1.000 | 4,264.05
|
| SHOOFLY CONSTRUCTION - BRIDGE 6CO/SA #001 | | 1.000 | 4,264.05
|
| | 0.000 | 0.00
|
| | |
|
| 4001 6952.02 | 14,104.57 | 0.000 | 0.00
|
| SHOO-FLY | EACH | 1.000 | 14,104.57
|
| BRIDGE 6 - CATAGORY 0101CO/SA #001 | | 1.000 | 14,104.57
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 10 GENERAL ITEMS | | Contracted | 174,005.74
|
| | Current | 175,225.76
|
| | In place | 88,786.01
|
| | This Estimate | 10,484.60
|
| | |
|
| Totals for contract | | Contracted | 4,244,619.96
|
|---|
| | Current | 4,257,688.08
|
|---|
| | In place | 1,140,251.64
|
|---|
| | This Estimate | 89,773.19
|
|---|