Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0880 CHRISTENSEN BROS., INC.
Contract ID:1853X
Estimate Number:0026
Pay Period End Date:07.05.2003
Contract Location:
ROCA SPUREstimate Type:PROG
Contractor:
CHRISTENSEN BROS., INC.Date Let:12.06.2001
644 RIVER ROADDate Awarded:12.20.2001
PO BOX 478Date Contract Executed:01.15.2002
Date Notice to Proceed:03.11.2002
CHEROKEE IA 51012Date Work Began:03.11.2002
Phone:Date Physical Work Completed:
(712)225-6146Date Accepted:
Escrow Agent:
Surety Co:
NATIONAL FIRE INSURANCE COMPANY OF HARTFORD
Counties
LANCASTER
Project Number PCT Fed State Project Number Description
11853 000  0.000 EACSTPD-EACBR-S55F(102)  GRAD CULV SEED BR GDRL BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,528,798.13$1,527,790.13$1,008.00
$1,581,266.24Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$1,528,798.13$1,527,790.13$1,008.00
$1,478,120.53Retainage$-15,287.98$-15,277.90$-10.08
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
96.68%Net Earnings$1,513,510.15$1,512,512.23$997.92
Liquidated Damages-$11,824.00-$11,824.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$711.30$711.30$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$11,112.70-$11,112.70$.00
Payment$1,502,397.45$1,501,399.53$997.92
Project ManagerDiv. Head/Dist. Eng.
Traudt, Bob07.07.2003Sklenar, Michael J07.08.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve07.08.2003
Controller Div. Processed
Burling, Laurie07.08.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 130.007.7001,001.00
COVER CROP SEEDING ha 7.7001,001.00
7.7001,001.00
0.0000.00

0002                          L020.00 1.601,542.0002,467.20
EROSION CONTROL m2 1,542.0002,467.20
2,040.3003,264.48
0.0000.00

0003                          L020.01 6.202,266.50014,052.30
EROSION CONTROL, TYPE A m2 2,266.50014,052.30
2,266.50014,052.30
0.0000.00

0004                          L020.09 12.00348.4004,180.80
EROSION CONTROL, TYPE AAA m2 348.4004,180.80
291.2003,494.40
0.0000.00

0005                          L020.10 1.708,773.30014,914.61
EROSION CONTROL, TYPE HV m2 8,773.30014,914.61
8,437.55014,343.84
0.0000.00

0006                          L021.01 14.50168.0002,436.00
EROSION CHECKS, TYPE A BALE168.0002,436.00
134.0001,943.00
0.0000.00

0007                          L021.06 13.50385.0005,197.50
EROSION CHECKS, TYPE HV BALE385.0005,197.50
388.0005,238.00
0.0000.00

0008                          L021.15 18.0084.0001,512.00
EROSION CHECKS, TYPE ST-HV BALE84.0001,512.00
84.0001,512.00
0.0000.00

0009                          L022.11 7.00388.5002,719.50
FABRIC SILT FENCE-LOW POROSITY m 388.5002,719.50
745.2005,216.40
0.0000.00

0010                          L022.12 8.00163.5001,308.00
FABRIC SILT FENCE-HIGH POROSITY m 163.5001,308.00
180.1001,440.80
0.0000.00

0011                          0030.10 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0012                          1009.00 6,000.001.0006,000.00
GENERAL CLEARING AND GRUBBING LS 1.0006,000.00
1.0006,000.00
0.0000.00

0013                          1010.00 2.4036,749.00088,197.60
EXCAVATION m3 36,749.00088,197.60
36,913.25088,591.80
0.0000.00

0014                          1011.00 3.00920.0002,760.00
WATER kL 920.0002,760.00
0.0000.00
0.0000.00

0015                          1012.00 62.0048.0002,976.00
RIGHT-OF-WAY MARKERS EACH48.0002,976.00
48.0002,976.00
0.0000.00

0016                          1043.50 1.903,456.0006,566.40
RIPRAP FILTER FABRIC m2 3,456.0006,566.40
3,737.4057,101.07
0.0000.00

0017                          1060.03 400.003.0001,200.00
GABION, TYPE C EACH3.0001,200.00
3.0001,200.00
0.0000.00

0018                          1060.06 250.003.000750.00
GABION, TYPE F EACH3.000750.00
3.000750.00
0.0000.00

0019                          1101.00 3.708,439.00031,224.30
REMOVE PAVEMENT m2 8,439.00031,224.30
8,052.03329,792.52
0.0000.00

0020                          1102.00 3.1043.000133.30
REMOVE ASPHALT SURFACE m2 343.0001,063.30
296.404918.86
0.0000.00

0021                          1143.00 3.1041.000127.10
REMOVE DRIVEWAY CULVERT PIPE m 41.000127.10
41.000127.10
0.0000.00

0022                          1405.00 19.0041.000779.00
RELAYING DRIVEWAY CULVERT PIPE m 34.000646.00
34.000646.00
0.0000.00

0023                          1701.24 55.00139.8007,689.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 139.8007,689.00
137.5007,562.50
0.0000.00

0024                          1701.48 64.0033.0002,112.00
1200 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 33.0002,112.00
33.0002,112.00
0.0000.00

0025                          6105.02 23.003,324.00076,452.00
ROCK RIPRAP, TYPE B Mg 3,324.00076,452.00
3,279.28475,423.53
0.0000.00

4014                          2011.05 24.310.0000.00
CRUSHED ROCK FOR TEMPORARY SURFACING Mg 250.0006,077.50
341.7748,308.52
0.0000.00

4016                          0095.00 669.380.0000.00
ADDITIONAL FREIGHT LS 1.000669.38
FOR ADDITIONAL DRIVEWAY CULVERT PIPES 1.000669.38
0.0000.00

4017                          1705.48 44.800.0000.00
1200 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE,TYPE 2,3,4 OR 5 m 34.0001,523.20
STA. 39+40 RT 34.0001,523.20
0.0000.00

GROUP 1 GRADINGContracted281,755.61
Current290,822.69
In place290,208.70
This Estimate0.00

GROUP 4 CULVERTS
0026                          P127.48 454.00107.50048,805.00
1200 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 m 107.50048,805.00
107.50048,805.00
0.0000.00

0027                          P140.36 135.0022.1002,983.50
900 mm CULVERT PIPE, TYPE 4 m 22.1002,983.50
22.1002,983.50
0.0000.00

0028                          P300.18 83.0028.1002,332.30
450 mm CULVERT PIPE, TYPE 3,4 OR 5 m 21.1001,751.30
18.8001,560.40
0.0000.00

0029                          P300.24 89.0024.9002,216.10
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 31.9002,839.10
33.1002,945.90
0.0000.00

0030                          P300.48 150.009.7001,455.00
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 9.7001,455.00
9.7001,455.00
0.0000.00

0031                          P500.24 100.0020.0002,000.00
600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 20.0002,000.00
20.0002,000.00
0.0000.00

0032                          0030.40 9,000.001.0009,000.00
MOBILIZATION LS 1.0009,000.00
1.0009,000.00
0.0000.00

0033                          4004.50 2.20290.000638.00
CAST IRON GRATE AND FRAME kg 501.0001,102.20
501.0001,102.20
0.0000.00

0034                          4035.00 100.006.000600.00
REMOVE FLARED-END SECTION EACH6.000600.00
6.000600.00
0.0000.00

0035                          4040.00 150.002.000300.00
REMOVE HEADWALLS FROM CULVERTS EACH2.000300.00
2.000300.00
0.0000.00

0036                          4044.00 2,000.001.0002,000.00
PREPARATION OF STRUCTURE EACH1.0002,000.00
AT STA. 20+54.11 1.0002,000.00
0.0000.00

0037                          4044.01 2,000.001.0002,000.00
PREPARATION OF STRUCTURE EACH1.0002,000.00
AT STA. 23+25.78 1.0002,000.00
0.0000.00

0038                          4050.01 58.00232.00013,456.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 228.60013,258.80
228.60013,258.80
0.0000.00

0039                          4051.01 51.00165.0008,415.00
EXCAVATION FOR BOX CULVERTS m3 194.7819,933.83
194.7819,933.83
0.0000.00

0040                          4100.06 800.006.7605,408.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 8.8607,088.00
8.8607,088.00
0.0000.00

0041                          4101.06 430.0081.81035,178.30
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 88.99238,266.56
88.92238,236.46
0.0000.00

0042                          4105.59 800.001.5301,224.00
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 2.1001,680.00
2.1001,680.00
0.0000.00

0043                          4107.07 430.000.830356.90
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 1.500645.00
1.500645.00
0.0000.00

0044                          4150.00 2.20563.0001,238.60
REINFORCING STEEL FOR HEADWALL kg 743.0001,634.60
743.0001,634.60
0.0000.00

0045                          4151.00 1.304,075.0005,297.50
REINFORCING STEEL FOR BOX CULVERT kg 4,391.9975,709.60
4,391.9975,709.60
0.0000.00

0046                          4155.50 2.2049.000107.80
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 70.000154.00
70.000154.00
0.0000.00

0047                          4157.00 2.2027.00059.40
REINFORCING STEEL FOR COLLARS kg 73.000160.60
73.000160.60
0.0000.00

0048                          4310.18 130.002.000260.00
450 mm FLARED-END SECTION EACH2.000260.00
2.000260.00
0.0000.00

0049                          4310.24 160.004.000640.00
600 mm FLARED-END SECTION EACH4.000640.00
4.000640.00
0.0000.00

0050                          4310.48 900.002.0001,800.00
1200 mm FLARED-END SECTION EACH2.0001,800.00
2.0001,800.00
0.0000.00

0051                          4764.54 16.001.00016.00
100 mm PERFORATED P.V.C. PIPE UNDERDRAIN m 1.00016.00
1.00016.00
0.0000.00

4003                          3008.05 6.300.0000.00
TIE BARS EACH94.000592.20
BOX FLOOR STA. 20+54.11 94.000592.20
0.0000.00

4004                          4976.05 1,260.000.0000.00
ADDITIONAL WORK LS 1.0001,260.00
BOX CULVERT CAP STA. 20+54.11 LT 1.0001,260.00
0.0000.00

4005                          6105.02 42.000.0000.00
ROCK RIPRAP, TYPE B Mg 24.0001,008.00
26.6071,117.49
0.0000.00

4006                          1043.50 3.000.0000.00
RIPRAP FILTER FABRIC m2 33.00099.00
24.00072.00
0.0000.00

4018                          P120.18 92.400.0000.00
450 mm CULVERT PIPE, TYPE 2 m 3.000277.20
STA. 46+95, 10.3M LT TO 7.3M LT 3.000277.20
0.0000.00

4019                          4977.00 234.300.0000.00
DELIVERED NOT USED EACH1.000234.30
450 mm x 5.0 m CMP STA. 46+96 TO 47+01.24 1.000234.30
0.0000.00

6001                          4051.12 43.000.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 22.458965.69
BOX FLOOR STA. 20+54.11 22.458965.69
0.0000.00

GROUP 4 CULVERTSContracted147,787.40
Current160,519.48
In place160,487.77
This Estimate0.00

GROUP 5 SEEDING
0052                          L001.01 1,400.005.5007,700.00
SEEDING, TYPE A ha 5.5007,700.00
6.7899,504.60
0.0000.00

0053                          L001.02 1,000.002.2002,200.00
SEEDING, TYPE B ha 2.2002,200.00
1.9011,901.00
0.0000.00

0054                          L032.75 80.0038.5003,080.00
MULCH Mg 38.5003,080.00
40.1613,212.88
0.0000.00

0055                          0030.50 50.001.00050.00
MOBILIZATION LS 1.00050.00
1.00050.00
0.0000.00

4024                          L003.02 1,008.000.0000.00
SEEDING LS 1.0001,008.00
(HYDRO) 1.0001,008.00
1.0001,008.00

GROUP 5 SEEDINGContracted13,030.00
Current14,038.00
In place15,676.48
This Estimate1,008.00

GROUP 6 BRIDGE AT STA. 46+12
0056                          0030.60 60,000.001.00060,000.00
MOBILIZATION LS 1.00060,000.00
1.00060,000.00
0.0000.00

0057                          3050.15 230.00126.20029,026.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 126.20029,026.00
126.20029,026.00
0.0000.00

0058                          3051.10 1.109,022.0009,924.20
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 9,022.0009,924.20
9,022.0009,924.20
0.0000.00

0059                          4095.20 340.0053.00018,020.00
COPING m 53.00018,020.00
48.05016,337.00
0.0000.00

0060                          6000.10 5,000.001.0005,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0061                          6000.11 5,000.001.0005,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0062                          6001.50 12,000.001.00012,000.00
BENT NO.1 EXCAVATION LS 1.00012,000.00
1.00012,000.00
0.0000.00

0063                          6001.51 12,000.001.00012,000.00
BENT NO.2 EXCAVATION LS 1.00012,000.00
1.00012,000.00
0.0000.00

0064                          6008.45 160.00311.80049,888.00
PLACING, FINISHING, AND CURING CONDUCTIVE CONCRETE m2 0.0000.00
0.0000.00
0.0000.00

0065                          6010.22 320.00139.00044,480.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 139.00044,480.00
139.00044,480.00
0.0000.00

0066                          6010.26 310.00179.60055,676.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 179.60055,676.00
179.60055,676.00
0.0000.00

0067                          6010.35 2,200.0031.20068,640.00
CONDUCTIVE CONCRETE m3 0.0000.00
0.0000.00
0.0000.00

0068                          6040.00 45,000.001.00045,000.00
REMOVE STRUCTURE EACH1.00045,000.00
AT STA. 46+41 1.00045,000.00
0.0000.00

0069                          6080.00 9.00490.0004,410.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 490.0004,410.00
490.0004,410.00
0.0000.00

0070                          6131.50 1.2035,215.00042,258.00
EPOXY COATED REINFORCING STEEL kg 35,215.00042,258.00
35,215.00042,258.00
0.0000.00

0071                          6210.12 70.00274.00019,180.00
HP 250 mm X 62 kg STEEL PILING m 274.00019,180.00
243.86917,070.83
0.0000.00

0072                          6251.40 1,600.0019.20030,720.00
ROCK SOCKET m 19.20030,720.00
20.88333,412.80
0.0000.00

0073                          6251.50 1,700.0039.20066,640.00
DRILLED SHAFT m 39.20066,640.00
37.55763,846.90
0.0000.00

0074                          6310.00 130.00451.40058,682.00
STEEL SHEET PILING m2 451.40058,682.00
435.26856,584.84
0.0000.00

0075                          8091.00 32.0094.0003,008.00
GRANULAR BACKFILL m3 94.0003,008.00
94.0003,008.00
0.0000.00

4009                          6008.45 160.420.0000.00
PLACING, FINISHING, AND CURING CONDUCTIVE CONCRETE m2 311.80050,018.96
REVISED PRICE 311.80050,018.96
0.0000.00

4010                          6010.35 2,457.310.0000.00
CONDUCTIVE CONCRETE m3 31.20076,668.07
REVISED PRICE 31.20076,668.08
0.0000.00

4011                          0095.00 226.350.0000.00
ADDITIONAL FREIGHT LS 1.000226.35
FOR EPOXY COATED RE-STEEL 1.000226.35
0.0000.00

4012                          6131.50 3.220.0000.00
EPOXY COATED REINFORCING STEEL kg 41.000132.02
ADDITIONAL B1001 BARS 41.000132.02
0.0000.00

4015                          3900.22 126.670.0000.00
ADDITIONAL COST m3 31.2003,952.10
CONDUCTIVE CONCRETE MATERIALS 31.2003,952.10
0.0000.00

4020                          6960.02 2,340.500.0000.00
ADDITIONAL WORK LS 1.0002,340.50
(BRIDGE DECK GRINDING) 1.0002,340.50
0.0000.00

4021                          A820.00 62,536.000.0000.00
CONTROLLER CABINET EACH1.00062,536.00
(BRIDGE DEICING CONTROLLER) 1.00062,536.00
0.0000.00

6002                          6210.32 42.000.0000.00
PAY CUT-OFF FOR 250 mm X 62 kg STEEL PILING m 30.1311,265.50
30.1311,265.50
0.0000.00

GROUP 6 BRIDGE AT STA. 46+12Contracted639,552.20
Current718,163.70
In place712,174.08
This Estimate0.00

GROUP 7 GUARDRAIL
0076                          0030.70 250.001.000250.00
MOBILIZATION LS 1.000250.00
1.000250.00
0.0000.00

0077                          7011.20 40.0015.200608.00
W-BEAM GUARDRAIL m 15.200608.00
15.200608.00
0.0000.00

0078                          7020.00 1,200.004.0004,800.00
BRIDGE APPROACH SECTIONS EACH4.0004,800.00
4.0004,800.00
0.0000.00

0079                          7024.27 1,600.004.0006,400.00
GUARDRAIL END TREATMENT, TYPE II EACH4.0006,400.00
4.0006,400.00
0.0000.00

GROUP 7 GUARDRAILContracted12,058.00
Current12,058.00
In place12,058.00
This Estimate0.00

GROUP 9 BITUMINOUS
0080                          0002.55 25.0064.9201,623.00
OVERLAY BROKEN LINES StaM64.9201,623.00
58.9901,474.75
0.0000.00

0081                          0002.60 25.0064.9201,623.00
OVERLAY SOLID LINES StaM64.9201,623.00
108.6302,715.75
0.0000.00

0082                          0030.90 25,000.001.00025,000.00
MOBILIZATION LS 1.00025,000.00
1.00025,000.00
0.0000.00

0083                          1020.03 14.0047.000658.00
DELINEATOR, TYPE III EACH47.000658.00
47.000658.00
0.0000.00

0084                          1020.20 24.0016.000384.00
INSTALL CHEVRONS EACH16.000384.00
16.000384.00
0.0000.00

0085                          2001.03 19.0058.0001,102.00
GRAVEL SURFACE COURSE Mg 58.0001,102.00
0.0000.00
0.0000.00

0086                          2020.00 9.00115.0001,035.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 115.0001,035.00
115.0001,035.00
0.0000.00

0087                          2021.00 50.004.000200.00
MAILBOX POST EACH4.000200.00
4.000200.00
0.0000.00

0088                          9005.00 38.00100.0003,800.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0003,800.00
SP1(12.5) 46.2801,758.64
0.0000.00

0089                          9005.25 25.507,350.000187,425.00
ASPHALTIC CONCRETE, TYPE SP1(12.5) Mg 7,350.000187,425.00
6,706.523171,016.34
0.0000.00

0090                          9009.00 2.501,116.0002,790.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 1,116.0002,790.00
1,173.0002,932.50
0.0000.00

0091                          9021.01 170.00402.30068,391.00
PERFORMANCE GRADED BINDER (64-22) Mg 402.30068,391.00
276.11046,938.70
0.0000.00

0092                          9034.00 1.051,116.0001,171.80
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 1,116.0001,171.80
536.940563.79
0.0000.00

0093                          9053.00 0.2517,530.0004,382.50
TACK COAT L 17,530.0004,382.50
18,643.2434,660.81
0.0000.00

0094                          9111.00 2.90332.000962.80
WATER kL 332.000962.80
0.0000.00
0.0000.00

0095                          9170.00 210.0063.58213,352.22
EARTH SHOULDER CONSTRUCTION StaM63.58213,352.22
63.36013,305.60
0.0000.00

0096                          9173.00 700.0011.7828,247.40
SUBGRADE PREPARATION StaM11.7828,247.40
13.8469,692.20
0.0000.00

0097                          9188.50 17.50242.0004,235.00
SURFACING UNDER GUARDRAIL m2 242.0004,235.00
254.9964,462.43
0.0000.00

0098                          9300.50 1,200.001.0001,200.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0001,200.00
0.500600.00
0.0000.00

6003                          9300.58 -0.6540.0000.00
SUPERPAVE QUALITY DISINCENTIVE Mg 6,752.803-4,416.33
-2.566% DISINCENTIVE 6,752.803-4,416.33
0.0000.00

GROUP 9 BITUMINOUSContracted327,582.72
Current323,166.39
In place282,982.18
This Estimate0.00

GROUP 10 GENERAL ITEMS
0099                          0001.10 1.505,184.0007,776.00
BARRICADE, TYPE III BDAY5,184.0007,776.00
5,431.0008,146.50
0.0000.00

0100                          0001.30 1.101,296.0001,425.60
TYPE B HIGH INTENSITY WARNING LIGHT LDAY1,296.0001,425.60
235.000258.50
0.0000.00

0101                          0001.90 0.503,456.0001,728.00
SIGN DAY EACH3,456.0001,728.00
4,354.0002,177.00
0.0000.00

0102                          0010.04 3,000.001.0003,000.00
FIELD OFFICE EACH1.0003,000.00
1.0003,000.00
0.0000.00

0103                          0030.00 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0104                          1017.00 34,000.001.00034,000.00
CONSTRUCTION STAKING AND SURVEYING LS 1.00034,000.00
0.95032,300.00
0.0000.00

0105                          9110.01 65.0035.0002,275.00
RENTAL OF LOADER, FULLY OPERATED HOUR35.0002,275.00
8.500552.50
0.0000.00

0106                          9110.02 50.0020.0001,000.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR20.0001,000.00
7.000350.00
0.0000.00

0107                          9110.03 45.0035.0001,575.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR35.0001,575.00
35.0001,575.00
0.0000.00

0108                          9110.07 45.0035.0001,575.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR35.0001,575.00
10.000450.00
0.0000.00

4001                          0001.99 0.580.0000.00
CONTRACTOR FURNISHED SIGN DAY EACH648.000375.84
723.000419.34
0.0000.00

4002                          0001.99 0.580.0000.00
CONTRACTOR FURNISHED SIGN DAY EACH432.000250.56
482.000279.56
0.0000.00

4007                          9110.21 126.340.0000.00
RENTAL OF CRANE, FULLY OPERATED HOUR1.000126.34
1.000126.34
0.0000.00

4008                          9110.06 89.380.0000.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR1.00089.38
1985 KOMATSU 1.00089.38
0.0000.00

4013                          9110.06 111.520.0000.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR14.0001,561.28
1999 JOHN DEERE 15.0001,672.80
0.0000.00

4022                          0003.10 135.000.0000.00
FLAGGING DAY 24.0003,240.00
12.5001,687.50
0.0000.00

4023                          0001.08 0.500.0000.00
BARRICADE, TYPE II BDAY1,000.000500.00
253.000126.50
0.0000.00

GROUP 10 GENERAL ITEMSContracted56,354.60
Current62,498.00
In place55,210.92
This Estimate0.00

Totals for contractContracted1,478,120.53
Current1,581,266.26
In place1,528,798.13
This Estimate1,008.00