Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:1836X
Estimate Number:0016
Pay Period End Date:04.27.2002
Contract Location:
HAWTHORNE AVENUE - CRETEEstimate Type:PROG
Contractor:
WERNER CONSTRUCTION, INC.Date Let:02.22.2001
129 E 2ND STDate Awarded:03.01.2001
PO BOX 1087Date Contract Executed:03.06.2001
Date Notice to Proceed:03.06.2001
HASTINGS NE 68902-1087Date Work Began:04.16.2001
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
SALINE
Project Number PCT Fed State Project Number Description
11836 000  0.000 EACSTPD-33-6(106)  GRADING, CONC PAVEMENT, CULVERTS, ELEC
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$2,519,970.95$2,458,675.24$61,295.71
$2,448,615.29Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$2,519,970.95$2,458,675.24$61,295.71
$2,418,062.09Retainage$-25,000.00$-24,586.75$-413.25
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
102.91%Net Earnings$2,494,970.95$2,434,088.49$60,882.46
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$2,494,970.95$2,434,088.49$60,882.46
Project ManagerDiv. Head/Dist. Eng.
Bannister, Edward Jr.04.30.2002Sklenar, Michael J04.30.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve04.30.2002
Controller Div. Processed
Burling, Laurie05.01.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0002                          1009.00 4,800.001.0004,800.00
GENERAL CLEARING AND GRUBBING LS 1.0004,800.00
1.0004,800.00
0.0000.00

0003                          1010.01 4.488,647.00038,738.56
EXCAVATION (ESTABLISHED QUANTITY) m3 8,647.00038,738.56
8,647.00038,738.56
0.0000.00

0004                          1011.00 2.80140.000392.00
WATER kL 140.000392.00
0.0000.00
0.0000.00

0005                          1101.00 3.8822,100.00085,748.00
REMOVE PAVEMENT m2 22,100.00085,748.00
22,413.07086,962.71
146.720569.27

0006                          1106.00 3.251,625.0005,281.25
REMOVE DRIVEWAY m2 1,625.0005,281.25
1,639.0005,326.76
14.00045.50

0007                          1107.00 3.501,359.0004,756.50
REMOVE WALK m2 1,359.0004,756.50
1,414.0004,949.00
55.000192.50

0008                          1114.10 16.0035.700571.20
REMOVE RETAINING WALL m 35.700571.20
35.700571.20
0.0000.00

0009                          4093.80 142.00270.00038,340.00
WALL MATERIALS m2 270.00038,340.00
270.00038,340.00
0.0000.00

0010                          4095.15 2.00211.000422.00
COMPACTED EARTH LEVELING PAD m 211.000422.00
211.000422.00
0.0000.00

0011                          8024.50 19.0081.0001,539.00
SELECT GRANULAR BACKFILL FOR RETAINED EARTH STRUCTURE m3 81.0001,539.00
81.0001,539.00
0.0000.00

4017                          1102.00 4.230.0000.00
REMOVE ASPHALT SURFACE m2 3,457.08414,623.47
3,457.08414,623.47
3,457.08414,623.47

4018                          3900.25 177.450.0000.00
ADDITIONAL COST m2 41.7707,412.09
Additional cost for added quantities for walls 41.7707,412.09
41.7707,412.09

GROUP 1 GRADINGContracted182,588.51
Current204,624.06
In place205,684.79
This Estimate22,842.83

GROUP 3 CONCRETE PAVEMENT
0012                          L001.02 5,000.001.0005,000.00
SEEDING, TYPE B ha 1.0005,000.00
1.0005,000.00
1.0005,000.00

0013                          L010.00 3.904,777.00018,630.30
SODDING m2 4,777.00018,630.30
6,000.00023,400.00
6,000.00023,400.00

0014                          L032.80 250.002.700675.00
HYDROMULCH Mg 2.700675.00
2.700675.00
2.700675.00

0015                          0030.30 107,865.001.000107,865.00
MOBILIZATION LS 1.000107,865.00
1.000107,865.00
0.0000.00

0016                          3016.21 30.002,295.00068,850.00
CONCRETE CLASS 47B-20 SIDEWALKS m2 2,295.00068,850.00
2,598.54677,956.38
43.2071,296.21

0017                          3020.26 31.301,789.00055,995.70
CONCRETE CLASS 47B-25 DRIVEWAY m2 1,789.00055,995.70
1,666.96152,175.88
137.8154,313.61

0018                          3075.41 38.166,644.000253,535.04
230 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 6,644.000253,535.04
7,275.038277,615.45
-3,646.736-139,159.45

0019                          3075.45 36.6219,896.000728,591.52
230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 19,896.000728,591.52
19,921.945729,541.62
3,496.391128,037.84

0020                          4015.00 350.006.0002,100.00
ADJUST MANHOLE TO GRADE EACH0.0000.00
0.0000.00
0.0000.00

0021                          4103.06 900.002.8502,565.00
CLASS 47B-20 CONCRETE FOR STEP m3 2.8502,565.00
6.4805,832.00
0.0000.00

0022                          4764.35 16.301,514.50024,686.35
100 mm PERFORATED PIPE UNDERDRAIN m 1,514.50024,686.35
1,464.50023,871.35
0.0000.00

0023                          7130.85 65.0092.0005,980.00
VINYL FENCE m 92.0005,980.00
0.0000.00
0.0000.00

0024                          7500.32 205.0028.0005,740.00
ARROW, PREFORMED PAVEMENT MARKING, TYPE 4 EACH28.0005,740.00
0.0000.00
0.0000.00

0025                          7500.38 300.002.000600.00
ONLY, PREFORMED PAVEMENT MARKING, TYPE 4 EACH2.000600.00
0.0000.00
0.0000.00

0026                          7502.12 3.80120.000456.00
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 2, GROOVED m 120.000456.00
0.0000.00
0.0000.00

0027                          7503.12 4.003,520.00014,080.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 2, GROOVED m 3,520.00014,080.00
0.0000.00
0.0000.00

0028                          7508.03 17.78275.0004,889.50
300 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 3 m 275.0004,889.50
0.0000.00
0.0000.00

0029                          7509.12 12.0040.000480.00
300 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 2, GROOVED m 40.000480.00
0.0000.00
0.0000.00

0030                          8029.00 6.1726,540.000163,751.80
AGGREGATE FOUNDATION COURSE m2 0.0000.00
0.0000.00
0.0000.00

0031                          9111.00 2.80481.0001,346.80
WATER kL 481.0001,346.80
0.0000.00
0.0000.00

0032                          9170.00 495.0032.00815,843.96
EARTH SHOULDER CONSTRUCTION StaM32.00815,843.96
32.00815,843.96
0.0000.00

0033                          9173.20 2.5028,329.00070,822.50
SUBGRADE PREPARATION m2 28,329.00070,822.50
30,453.68676,134.23
0.0000.00

4001                          8032.00 5.980.0000.00
CRUSHED CONCRETE FOUNDATION COURSE m2 26,540.000158,709.20
27,518.022164,557.77
0.0000.00

4002                          9009.77 17.870.0000.00
TEMPORARY SURFACING Mg 500.0008,935.00
Temporary Surfacing (Crushed Concrete) 746.40013,338.17
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted1,552,484.47
Current1,554,276.87
In place1,573,806.81
This Estimate23,563.21

GROUP 4 CULVERTS
0034                          P300.30 130.003.500455.00
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 3.500455.00
0.0000.00
0.0000.00

0035                          P300.48 216.005.0001,080.00
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 5.0001,080.00
5.0001,080.00
0.0000.00

0036                          P700.18 98.00403.00039,494.00
450 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 403.00039,494.00
395.00038,710.00
-3.000-294.00

0037                          P700.24 124.00328.50040,734.00
600 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 328.50040,734.00
326.50040,486.00
-2.000-248.00

0038                          P700.30 168.00468.00078,624.00
750 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 468.00078,624.00
597.000100,296.00
1.000168.00

0039                          0030.40 4,000.001.0004,000.00
MOBILIZATION LS 1.0004,000.00
1.0004,000.00
0.0000.00

0040                          1117.00 500.001.000500.00
REMOVE MANHOLE EACH1.000500.00
1.000500.00
0.0000.00

0041                          1119.00 350.0015.0005,250.00
REMOVE INLET EACH15.0005,250.00
16.0005,600.00
1.000350.00

0042                          4002.00 3.102,622.0008,128.20
CAST IRON COVER AND FRAME kg 2,622.0008,128.20
2,622.0008,128.20
0.0000.00

0043                          4003.00 3.00526.0001,578.00
CAST IRON COVER, FRAME, AND FLANGE kg 526.0001,578.00
526.0001,578.00
0.0000.00

0044                          4016.00 2,000.001.0002,000.00
MANHOLE EACH1.0002,000.00
AT STA. 36+22.30 8.2m LT. 1.0002,000.00
0.0000.00

0045                          4016.01 2,000.001.0002,000.00
MANHOLE EACH1.0002,000.00
AT STA. 37+26.49 8.2m LT. 1.0002,000.00
-1.000-2,000.00

0046                          4018.00 250.002.000500.00
TAPPING EXISTING STRUCTURE EACH2.000500.00
2.000500.00
0.0000.00

0047                          4018.50 200.002.000400.00
TAPPING EXISTING PIPE EACH2.000400.00
2.000400.00
0.0000.00

0048                          4035.00 85.002.000170.00
REMOVE FLARED-END SECTION EACH2.000170.00
2.000170.00
0.0000.00

0049                          4040.00 185.005.000925.00
REMOVE HEADWALLS FROM CULVERTS EACH5.000925.00
5.000925.00
0.0000.00

0050                          4043.50 32.60166.5005,427.90
REMOVE SEWER PIPE m 166.5005,427.90
166.5005,427.90
0.0000.00

0051                          4045.00 5,000.001.0005,000.00
REMOVE STRUCTURE EACH1.0005,000.00
STA. 32+01.88 TO STA. 33+90.30 LT. 1.0005,000.00
0.0000.00

0052                          4045.01 4,250.001.0004,250.00
REMOVE STRUCTURE EACH1.0004,250.00
STA. 32+01.88 TO STA. 33+83.29 RT. 1.0004,250.00
0.0000.00

0053                          4050.01 20.0041.000820.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 41.000820.00
83.0001,660.00
-3.000-60.00

0054                          4051.01 35.0017.000595.00
EXCAVATION FOR BOX CULVERTS m3 17.000595.00
17.000595.00
0.0000.00

0055                          4100.06 710.001.070759.70
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 1.070759.70
1.070759.70
0.0000.00

0056                          4101.06 500.0017.5708,785.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 17.5708,785.00
17.5708,785.00
0.0000.00

0057                          4105.59 635.00148.66094,399.10
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 148.66094,399.10
160.560101,955.60
11.9007,556.50

0058                          4150.00 2.2580.000180.00
REINFORCING STEEL FOR HEADWALL kg 80.000180.00
80.000180.00
0.0000.00

0059                          4151.00 1.76930.0001,636.80
REINFORCING STEEL FOR BOX CULVERT kg 930.0001,636.80
930.0001,636.80
-3.530-6.21

0060                          4155.50 1.884,440.0008,347.20
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 4,440.0008,347.20
4,802.0009,027.76
362.000680.56

0061                          4360.30 228.002.000456.00
750 mm METAL FLARED-END SECTION EACH2.000456.00
0.0000.00
0.0000.00

0062                          4803.06 41.804.500188.10
150 mm P.V.C. PIPE m 4.500188.10
6.000250.80
0.0000.00

4007                          6960.06 48.2160.0000.00
ADDITIONAL WORK m 152.4397,350.00
Unforeseen obstruction 152.4397,350.00
0.0000.00

4008                          4011.60 2,618.700.0000.00
AREA INLET EACH1.0002,618.70
Station 43+50.4 Rt. 1.0002,618.70
0.0000.00

GROUP 4 CULVERTSContracted316,683.00
Current326,651.70
In place355,870.46
This Estimate6,146.85

GROUP 4A SANITARY SEWER AND WATER MAIN
0063                          W100.00 185.0013.0002,405.00
CURB STOP AND BOX EACH13.0002,405.00
13.0002,405.00
0.0000.00

0064                          W175.00 185.003.000555.00
19 mm CORPORATION STOP EACH3.000555.00
3.000555.00
0.0000.00

0065                          W175.01 230.0010.0002,300.00
25 mm CORPORATION STOP EACH10.0002,300.00
10.0002,300.00
0.0000.00

0066                          W176.01 37.5085.1903,194.63
25 mm COPPER WATER SERVICE m 85.1903,194.63
85.1903,194.62
0.0000.00

0067                          W176.24 37.0073.4102,716.17
19 mm WATER SERVICE m 73.4102,716.17
73.4102,716.17
0.0000.00

0068                          W176.70 30.003.00090.00
WATER SERVICE CONNECTION EACH3.00090.00
19 mm 3.00090.00
0.0000.00

0069                          W176.71 30.0015.000450.00
WATER SERVICE CONNECTION EACH15.000450.00
25 mm 15.000450.00
0.0000.00

0070                          W200.04 5.301,018.2005,396.46
DUCTILE IRON FITTINGS, M.J. kg 1,018.2005,396.46
1,018.2005,396.46
0.0000.00

0071                          W205.04 53.002.780147.34
100 mm WATER MAIN PIPE m 2.780147.34
2.780147.34
0.0000.00

0072                          W205.06 50.00355.70017,785.00
150 mm WATER MAIN PIPE m 355.70017,785.00
355.70017,785.00
0.0000.00

0073                          W205.08 61.3221.7201,331.87
200 mm WATER MAIN PIPE m 21.7201,331.87
21.7201,331.87
0.0000.00

0074                          W205.12 74.00237.37017,565.38
300 mm WATER MAIN PIPE m 237.37017,565.38
230.98017,092.52
0.0000.00

0075                          W220.06 420.0014.0005,880.00
150 mm GATE VALVE, M.J. EACH14.0005,880.00
14.0005,880.00
0.0000.00

0076                          W220.08 568.003.0001,704.00
200 mm GATE VALVE, M.J. EACH3.0001,704.00
3.0001,704.00
0.0000.00

0077                          W220.12 995.005.0004,975.00
300 mm GATE VALVE, M.J. EACH5.0004,975.00
5.0004,975.00
0.0000.00

0078                          W221.06 105.0014.0001,470.00
150 mm WATER VALVE BOX EACH14.0001,470.00
14.0001,470.00
0.0000.00

0079                          W221.08 105.003.000315.00
200 mm WATER VALVE BOX EACH3.000315.00
3.000315.00
0.0000.00

0080                          W221.12 105.005.000525.00
300 mm WATER VALVE BOX EACH5.000525.00
5.000525.00
0.0000.00

0081                          W222.06 1,550.004.0006,200.00
150 mm FIRE HYDRANT EACH4.0006,200.00
4.0006,200.00
0.0000.00

0082                          W355.04 350.008.0002,800.00
100 mm SLEEVE EACH8.0002,800.00
8.0002,800.00
0.0000.00

0083                          W355.08 365.002.000730.00
200 mm SLEEVE EACH2.000730.00
2.000730.00
0.0000.00

0084                          W355.10 400.001.000400.00
250 mm SLEEVE EACH1.000400.00
1.000400.00
0.0000.00

0085                          W722.51 10.00492.8304,928.30
ABANDON WATER MAIN m 492.8304,928.30
492.8304,928.30
0.0000.00

0086                          W800.06 150.0014.0002,100.00
REMOVE GATE VALVE EACH14.0002,100.00
14.0002,100.00
0.0000.00

0087                          W800.21 32.6064.5902,105.63
REMOVE WATER MAIN PIPE m 64.5902,105.63
64.5902,105.63
0.0000.00

0088                          W800.33 200.003.000600.00
REMOVE HYDRANT EACH3.000600.00
3.000600.00
0.0000.00

0089                          0030.40 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0090                          1117.00 500.0011.0005,500.00
REMOVE MANHOLE EACH11.0005,500.00
11.0005,500.00
0.0000.00

0091                          4016.00 2,782.001.0002,782.00
MANHOLE EACH1.0002,782.00
AT STA. 33+19.60 1.0002,782.00
0.0000.00

0092                          4016.01 2,000.001.0002,000.00
MANHOLE EACH1.0002,000.00
AT STA. 34+19.60 1.0002,000.00
0.0000.00

0093                          4016.02 3,500.001.0003,500.00
MANHOLE EACH1.0003,500.00
AT STA. 34+73.20 1.0003,500.00
0.0000.00

0094                          4016.03 2,400.001.0002,400.00
MANHOLE EACH1.0002,400.00
AT STA. 35+21.40 1.0002,400.00
0.0000.00

0095                          4016.04 2,800.001.0002,800.00
MANHOLE EACH1.0002,800.00
AT STA. 36+23.50 1.0002,800.00
0.0000.00

0096                          4016.05 2,800.001.0002,800.00
MANHOLE EACH1.0002,800.00
AT STA. 37+25.90 1.0002,800.00
0.0000.00

0097                          4016.06 2,500.001.0002,500.00
MANHOLE EACH1.0002,500.00
AT STA. 38+26.20 1.0002,500.00
0.0000.00

0098                          4016.07 2,400.001.0002,400.00
MANHOLE EACH1.0002,400.00
AT STA. 39+62.46 10.79m RT. 1.0002,400.00
0.0000.00

0099                          4016.08 2,400.001.0002,400.00
MANHOLE EACH1.0002,400.00
AT STA. 39+92.61 9.89m RT. 1.0002,400.00
0.0000.00

0100                          4016.09 2,400.001.0002,400.00
MANHOLE EACH1.0002,400.00
AT STA. 40+74.06 10.08m RT. 1.0002,400.00
0.0000.00

0101                          4016.10 2,500.001.0002,500.00
MANHOLE EACH1.0002,500.00
AT STA. 42+02.46 10.05m RT. 1.0002,500.00
0.0000.00

0102                          4016.11 2,600.001.0002,600.00
MANHOLE EACH1.0002,600.00
AT STA. 43+37.60 13.30m RT. 1.0002,600.00
0.0000.00

0103                          4042.55 300.007.0002,100.00
CONNECT SANITARY SERVICE EACH6.0001,800.00
7.0002,100.00
0.0000.00

0104                          4043.50 8.15644.6705,254.06
REMOVE SEWER PIPE m 644.6705,254.06
644.6705,254.06
0.0000.00

0105                          4731.04 58.00155.5009,019.00
100 mm SANITARY SEWER PIPE m 0.0000.00
0.0000.00
0.0000.00

0106                          4763.00 5,500.001.0005,500.00
BYPASS PUMPING LS 1.0005,500.00
1.0005,500.00
0.0000.00

0107                          4764.78 65.0054.5803,547.70
200 mm P.V.C. SEWER PIPE m 54.5803,547.70
54.6003,549.00
0.0000.00

0108                          4764.82 105.32603.30063,539.56
300 mm P.V.C. SEWER PIPE m 603.30063,539.56
603.30063,539.55
0.0000.00

0109                          4764.85 121.0030.3803,675.98
375 mm P.V.C. SEWER PIPE m 30.3803,675.98
30.3803,675.98
0.0000.00

0110                          4795.00 210.0023.0004,830.00
P.V.C. WYE EACH0.0000.00
300 mm X 100 mm 0.0000.00
0.0000.00

0111                          4805.26 586.0017.0009,962.00
650 mm STEEL CASING m 0.0000.00
0.0000.00
0.0000.00

4003                          4042.55 2,769.900.0000.00
CONNECT SANITARY SERVICE EACH1.0002,769.90
Connect Sanitary Service (Revised) 1.0002,769.90
0.0000.00

4004                          4731.06 67.310.0000.00
150 mm SANITARY SEWER PIPE m 86.5685,826.89
150mm Sanitary Sewer Pipe (Revised) 86.5685,826.89
0.0000.00

4005                          4795.00 260.400.0000.00
P.V.C. WYE EACH12.0003,124.80
300mm x 150mm 12.0003,124.80
0.0000.00

4006                          6960.02 4,907.350.0000.00
ADDITIONAL WORK LS 1.0004,907.35
Cancellation of casement placement 1.0004,907.35
0.0000.00

4010                          W176.51 63.3250.0000.00
WATER SERVICE m 4.300272.30
38mm water pipe 4.300272.30
4.300272.30

4011                          W175.06 383.250.0000.00
38 mm CORPORATION STOP EACH1.000383.25
1.000383.25
1.000383.25

4012                          W100.00 249.900.0000.00
CURB STOP AND BOX EACH1.000249.90
1.000249.90
1.000249.90

4013                          W176.08 65.6250.0000.00
38 mm COPPER WATER SERVICE m 1.00065.63
1.00065.63
1.00065.63

4014                          1990.06 406.8230.0000.00
EQUIPMENT RENTAL LS 1.000406.82
1.000406.82
1.000406.82

4015                          1990.01 28.8750.0000.00
LABOR HOUR48.2501,393.22
additional sanitary sewer work 48.2501,393.22
48.2501,393.22

4016                          1000.00 367.500.0000.00
LARGE TREE REMOVAL EACH1.000367.50
1.000367.50
1.000367.50

GROUP 4A SANITARY SEWER AND WATER MAINContracted237,680.08
Current233,336.63
In place233,165.06
This Estimate3,138.62

GROUP 8B ELECTRICAL
0112                          A001.01 400.005.0002,000.00
PULL BOX, TYPE PB-1 EACH5.0002,000.00
5.0002,000.00
0.0000.00

0113                          A001.02 300.001.000300.00
PULL BOX, TYPE PB-1A EACH1.000300.00
1.000300.00
0.0000.00

0114                          A001.12 300.0011.0003,300.00
PULL BOX, TYPE PB-5 EACH11.0003,300.00
11.0003,300.00
3.000900.00

0115                          A003.10 600.006.0003,600.00
TRAFFIC SIGNAL, TYPE TS-1 EACH6.0003,600.00
6.0003,600.00
0.0000.00

0116                          A004.04 1,000.001.0001,000.00
TRAFFIC SIGNAL, TYPE TS-1LL EACH1.0001,000.00
1.0001,000.00
0.0000.00

0117                          A004.28 1,000.001.0001,000.00
TRAFFIC SIGNAL, TYPE TS-1RR EACH1.0001,000.00
1.0001,000.00
0.0000.00

0118                          A006.15 300.008.0002,400.00
PEDESTRIAN SIGNAL, TYPE PS-1 EACH8.0002,400.00
8.0002,400.00
0.0000.00

0119                          A006.70 100.008.000800.00
PEDESTRIAN PUSHBUTTON, TYPE PPB EACH8.000800.00
8.000800.00
0.0000.00

0120                          A006.98 200.004.000800.00
VEHICLE DETECTOR, TYPE A PREFORMED EACH4.000800.00
4.000800.00
0.0000.00

0121                          A007.00 250.004.0001,000.00
VEHICLE DETECTOR, TYPE B PREFORMED EACH4.0001,000.00
8.0002,000.00
0.0000.00

0122                          A008.72 1,900.005.0009,500.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.25 EACH5.0009,500.00
5.0009,500.00
0.0000.00

0123                          A009.14 1,700.004.0006,800.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 EACH4.0006,800.00
4.0006,800.00
0.0000.00

0124                          A009.93 1,550.0015.00023,250.00
STREET LIGHTING UNIT, TYPE SL-A-12.2-0.3-0.25 EACH15.00023,250.00
15.00023,250.00
0.0000.00

0125                          A011.16 4,000.001.0004,000.00
COMBINATION MAST ARM SIGNAL AND LIGHTING POLE,TYPE CMP-9.5-1.2 EACH1.0004,000.00
1.0004,000.00
0.0000.00

0126                          A011.34 4,100.001.0004,100.00
COMBINATION MAST ARM SIGNAL AND LIGHTING POLE,TYPE CMP-11-1.2 EACH1.0004,100.00
1.0004,100.00
0.0000.00

0127                          A011.58 5,000.002.00010,000.00
COMBINATION MAST ARM SIGNAL AND LIGHTING POLE, TYPE CMP-12.5-1.2 EACH2.00010,000.00
2.00010,000.00
0.0000.00

0128                          A020.10 500.001.000500.00
LIGHTING CONTROL CENTER, TYPE D EACH1.000500.00
1.000500.00
0.0000.00

0129                          A020.30 1,500.002.0003,000.00
LIGHTING CONTROL CENTER, TYPE R EACH2.0003,000.00
2.0003,000.00
1.0001,500.00

0130                          A070.10 6.501,009.0006,558.50
38 mm CONDUIT IN TRENCH m 1,009.0006,558.50
1,009.0006,558.50
0.0000.00

0131                          A070.14 7.00215.6001,509.20
50 mm CONDUIT IN TRENCH m 215.6001,509.20
215.0001,505.00
0.0000.00

0132                          A070.18 30.001.40042.00
75 mm CONDUIT IN TRENCH m 1.40042.00
1.40042.00
0.0000.00

0133                          A072.10 7.00377.0002,639.00
38 mm CONDUIT UNDER ROADWAY m 377.0002,639.00
377.0002,639.00
0.0000.00

0134                          A072.14 8.00112.200897.60
50 mm CONDUIT UNDER ROADWAY m 112.200897.60
112.200897.60
0.0000.00

0135                          A072.18 15.0017.100256.50
75 mm CONDUIT UNDER ROADWAY m 17.100256.50
17.100256.50
0.0000.00

0136                          A077.12 1.20237.400284.88
2/C #14 AWG TRAFFIC SIGNAL CABLE m 237.400284.88
237.400284.88
0.0000.00

0137                          A077.17 1.90276.700525.73
7/C #14 AWG TRAFFIC SIGNAL CABLE m 276.700525.73
276.700525.73
0.0000.00

0138                          A077.22 4.00118.700474.80
12/C #14 AWG TRAFFIC SIGNAL CABLE m 118.700474.80
118.700474.80
0.0000.00

0139                          A079.01 1.40105.800148.12
2/C #14 AWG DETECTOR LEAD-IN CABLE m 105.800148.12
105.800148.12
0.0000.00

0140                          A079.50 1.00337.600337.60
GROUNDING CONDUCTOR m 337.600337.60
337.600337.60
37.60037.60

0141                          A079.55 3.0060.000180.00
SERVICE CABLE m 60.000180.00
60.000180.00
30.00090.00

0142                          A080.22 1.101,386.0001,524.60
STREET LIGHTING CABLE, NO. 6 BARE m 1,386.0001,524.60
1,386.0001,524.60
386.000424.60

0143                          A080.24 1.502,772.0004,158.00
STREET LIGHTING CABLE, NO. 6 USE m 2,772.0004,158.00
2,772.0004,158.00
772.0001,158.00

0144                          A500.20 1,000.001.0001,000.00
INSTALL TRAFFIC SIGNAL CONTROLLER, TYPE TC-170 EACH1.0001,000.00
1.0001,000.00
1.0001,000.00

0145                          0030.81 4,000.001.0004,000.00
MOBILIZATION LS 1.0004,000.00
1.0004,000.00
0.0000.00

GROUP 8B ELECTRICALContracted101,886.53
Current101,886.53
In place102,882.33
This Estimate5,110.20

GROUP 10 GENERAL ITEMS
0146                          0001.10 2.505,925.00014,812.50
BARRICADE, TYPE III BDAY5,925.00014,812.50
13,743.00034,357.50
78.000195.00

0147                          0001.30 2.50474.0001,185.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY474.0001,185.00
565.0001,412.50
52.000130.00

0148                          0001.90 0.508,484.0004,242.00
SIGN DAY EACH8,484.0004,242.00
10,383.0005,191.50
338.000169.00

0149                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
1.0001,500.00
0.0000.00

0150                          0030.00 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

4009                          9110.03 55.000.0000.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR20.0001,100.00
20.0001,100.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted26,739.50
Current27,839.50
In place48,561.50
This Estimate494.00

Totals for contractContracted2,418,062.09
Current2,448,615.29
In place2,519,970.95
This Estimate61,295.71