Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:3606 DOBSON BROTHERS CONSTRUCTION CO. & AFFIL
Contract ID:1821
Estimate Number:0006
Pay Period End Date:01.18.2003
Contract Location:
WILBER - CRETEEstimate Type:PROG
Contractor:
DOBSON BROTHERS CONSTRUCTION CO. & AFFILDate Let:10.10.2002
410 S 7THDate Awarded:10.17.2002
PO BOX 81409Date Contract Executed:10.21.2002
Date Notice to Proceed:10.21.2002
LINCOLN NE 68501Date Work Began:
Phone:Date Physical Work Completed:
(402)474-5115Date Accepted:
Escrow Agent:
Surety Co:
WESTERN SURETY COMPANY
Counties
SALINE
Project Number PCT Fed State Project Number Description
11821 000  0.000 EACSTPD-103-1(105)  GRAD CULV SEED BR GDRL ELEC BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$653,123.04$601,274.08$51,848.96
$4,440,125.55Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$653,123.04$601,274.08$51,848.96
$4,440,125.55Retainage$-6,531.23$-6,012.74$-518.49
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
14.71%Net Earnings$646,591.81$595,261.34$51,330.47
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$646,591.81$595,261.34$51,330.47
Project ManagerDiv. Head/Dist. Eng.
Kuper, Melvin01.30.2003Sklenar, Michael J01.31.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve02.03.2003
Controller Div. Processed
Burling, Laurie02.03.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 87.4033.0002,884.20
COVER CROP SEEDING ha 33.0002,884.20
0.0000.00
0.0000.00

0002                          L020.00 1.953,733.0007,279.35
EROSION CONTROL m2 3,733.0007,279.35
0.0000.00
0.0000.00

0003                          L020.09 14.50352.5005,111.25
EROSION CONTROL, TYPE AAA m2 352.5005,111.25
0.0000.00
0.0000.00

0004                          L021.06 22.0048.0001,056.00
EROSION CHECKS, TYPE HV BALE48.0001,056.00
0.0000.00
0.0000.00

0005                          L022.11 7.00375.0002,625.00
FABRIC SILT FENCE-LOW POROSITY m 375.0002,625.00
0.0000.00
0.0000.00

0006                          L022.12 23.309.000209.70
FABRIC SILT FENCE-HIGH POROSITY m 9.000209.70
0.0000.00
0.0000.00

0007                          L022.75 18.80160.0003,008.00
TEMPORARY SILT CHECK m 160.0003,008.00
0.0000.00
0.0000.00

0008                          0030.10 40,000.001.00040,000.00
MOBILIZATION LS 1.00040,000.00
1.00040,000.00
0.0000.00

0009                          1000.00 181.8118.0003,272.58
LARGE TREE REMOVAL EACH18.0003,272.58
11.0001,999.91
2.000363.62

0010                          1009.00 11,761.631.00011,761.63
GENERAL CLEARING AND GRUBBING LS 1.00011,761.63
0.5005,880.82
0.0000.00

0011                          1010.00 1.8658,218.000108,285.48
EXCAVATION m3 58,218.000108,285.48
10,124.00018,830.64
0.0000.00

0012                          1010.10 3.3860,368.000204,043.84
EXCAVATION, BORROW m3 60,368.000204,043.84
18,323.00061,931.74
0.0000.00

0013                          1011.00 1.045,929.0006,166.16
WATER kL 5,929.0006,166.16
0.0000.00
0.0000.00

0014                          1012.00 59.16186.00011,003.76
RIGHT-OF-WAY MARKERS EACH186.00011,003.76
0.0000.00
0.0000.00

0015                          1041.00 0.806,900.0005,520.00
SALVAGING AND PLACING TOPSOIL m2 6,900.0005,520.00
2,300.0001,840.00
0.0000.00

0016                          1090.00 1,200.001.0001,200.00
ABANDON WELLS EACH1.0001,200.00
0.0000.00
0.0000.00

0017                          1101.00 2.507,638.00019,095.00
REMOVE PAVEMENT m2 7,638.00019,095.00
0.0000.00
0.0000.00

0018                          1101.25 8.20316.0002,591.20
SAWING PAVEMENT m 316.0002,591.20
0.0000.00
0.0000.00

0019                          1102.00 5.111,069.0005,462.59
REMOVE ASPHALT SURFACE m2 1,069.0005,462.59
0.0000.00
0.0000.00

0020                          1701.24 50.50349.50017,649.75
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 349.50017,649.75
0.0000.00
0.0000.00

0021                          1701.36 86.1375.0006,459.75
900 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 75.0006,459.75
0.0000.00
0.0000.00

0022                          4040.00 176.782.000353.56
REMOVE HEADWALLS FROM CULVERTS EACH2.000353.56
0.0000.00
0.0000.00

0023                          6040.00 1,111.821.0001,111.82
REMOVE STRUCTURE EACH1.0001,111.82
AT STA. 133+25.30 LT. 0.0000.00
0.0000.00

0024                          7017.00 4.96252.5001,252.40
REMOVE GUARDRAIL m 252.5001,252.40
0.0000.00
0.0000.00

0025                          9110.01 87.475.000437.35
RENTAL OF LOADER, FULLY OPERATED HOUR5.000437.35
0.0000.00
0.0000.00

0026                          9110.03 45.625.000228.10
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR5.000228.10
0.0000.00
0.0000.00

0027                          9110.06 132.575.000662.85
RENTAL OF BACKHOE, FULLY OPERATED HOUR5.000662.85
2.000265.14
2.000265.14

0028                          9110.07 68.805.000344.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR5.000344.00
0.0000.00
0.0000.00

0029                          9110.09 125.1810.0001,251.80
RENTAL OF TRACTOR AND SCRAPER, FULLY OPERATED HOUR10.0001,251.80
0.0000.00
0.0000.00

GROUP 1 GRADINGContracted470,327.12
Current470,327.12
In place130,748.25
This Estimate628.76

GROUP 4 CULVERTS
0030                          P120.24 104.009.100946.40
600 mm CULVERT PIPE, TYPE 2 m 9.100946.40
7.000728.00
0.0000.00

0031                          P120.30 146.5026.0003,809.00
750 mm CULVERT PIPE, TYPE 2 m 26.0003,809.00
26.0003,809.00
0.0000.00

0032                          P120.36 193.0038.3007,391.90
900 mm CULVERT PIPE, TYPE 2 m 38.3007,391.90
32.0006,176.00
0.0000.00

0033                          P120.42 239.506.5001,556.75
1050 mm CULVERT PIPE TYPE 2 m 6.5001,556.75
6.5001,556.75
0.0000.00

0034                          P120.48 299.0028.0008,372.00
1200 mm CULVERT PIPE, TYPE 2 m 28.0008,372.00
28.0008,372.00
0.0000.00

0035                          P300.48 169.5011.9002,017.05
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 11.9002,017.05
0.0000.00
0.0000.00

0036                          P375.54 241.0047.10011,351.10
1350 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 3,4 OR 5 m 47.10011,351.10
42.00010,122.00
0.0000.00

0037                          P400.36 193.0020.0003,860.00
900 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 20.0003,860.00
20.0003,860.00
0.0000.00

0038                          P402.24 76.0045.3003,442.80
600 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 45.3003,442.80
45.3003,442.80
0.0000.00

0039                          0030.40 20,000.001.00020,000.00
MOBILIZATION LS 1.00020,000.00
1.00020,000.00
0.0000.00

0040                          1043.50 1.90350.000665.00
RIPRAP FILTER FABRIC m2 350.000665.00
350.000665.00
350.000665.00

0041                          1118.25 300.001.000300.00
REMOVE SPLASH BASIN EACH1.000300.00
0.0000.00
0.0000.00

0042                          1119.00 170.002.000340.00
REMOVE INLET EACH2.000340.00
0.0000.00
0.0000.00

0043                          4040.00 120.0028.0003,360.00
REMOVE HEADWALLS FROM CULVERTS EACH28.0003,360.00
32.0003,840.00
0.0000.00

0044                          4044.00 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA. 11+95.43 1.0001,800.00
0.0000.00

0045                          4044.01 600.001.000600.00
PREPARATION OF STRUCTURE EACH1.000600.00
AT STA. 18+90.37 1.000600.00
0.0000.00

0046                          4044.02 600.001.000600.00
PREPARATION OF STRUCTURE EACH1.000600.00
AT STA. 23+91.01 1.000600.00
0.0000.00

0047                          4044.03 1,000.001.0001,000.00
PREPARATION OF STRUCTURE EACH1.0001,000.00
AT STA. 30+67.21 1.0001,000.00
0.0000.00

0048                          4044.04 500.001.000500.00
PREPARATION OF STRUCTURE EACH1.000500.00
AT STA. 43+22.07 1.000500.00
0.0000.00

0049                          4044.05 500.001.000500.00
PREPARATION OF STRUCTURE EACH1.000500.00
AT STA. 43+58.63 1.000500.00
0.0000.00

0050                          4044.06 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA. 47+46.04 1.0001,800.00
0.0000.00

0051                          4044.07 1,600.001.0001,600.00
PREPARATION OF STRUCTURE EACH1.0001,600.00
AT STA. 125+19.66 1.0001,600.00
0.0000.00

0052                          4044.08 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA. 130+46.08 1.0001,800.00
0.0000.00

0053                          4044.09 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA. 10148+61 1.0001,800.00
0.0000.00

0054                          4050.01 8.00368.0002,944.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 368.0002,944.00
348.0002,784.00
0.0000.00

0055                          4051.01 24.00298.0007,152.00
EXCAVATION FOR BOX CULVERTS m3 298.0007,152.00
298.0007,152.00
0.0000.00

0056                          4100.06 710.0011.9808,505.80
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 11.9808,505.80
11.9808,505.80
4.0002,840.00

0057                          4101.06 369.00387.820143,105.58
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 387.820143,105.58
383.001141,327.38
52.63319,421.58

0058                          4107.07 514.0016.1808,316.52
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 16.1808,316.52
18.9609,745.44
0.0000.00

0059                          4150.00 1.70845.0001,436.50
REINFORCING STEEL FOR HEADWALL kg 845.0001,436.50
845.0001,436.50
275.000467.50

0060                          4151.00 1.2023,817.00028,580.40
REINFORCING STEEL FOR BOX CULVERT kg 23,817.00028,580.40
23,592.05628,310.47
3,333.1603,999.79

0061                          4157.00 1.70652.0001,108.40
REINFORCING STEEL FOR COLLARS kg 652.0001,108.40
690.0001,173.00
0.0000.00

0062                          4310.24 402.002.000804.00
600 mm FLARED-END SECTION EACH2.000804.00
2.000804.00
0.0000.00

0063                          4310.30 458.008.0003,664.00
750 mm FLARED-END SECTION EACH8.0003,664.00
8.0003,664.00
0.0000.00

0064                          4310.36 743.006.0004,458.00
900 mm FLARED-END SECTION EACH6.0004,458.00
6.0004,458.00
0.0000.00

0065                          4310.42 939.002.0001,878.00
1050 mm FLARED-END SECTION EACH2.0001,878.00
2.0001,878.00
0.0000.00

0066                          4310.48 1,038.008.0008,304.00
1200 mm FLARED-END SECTION EACH8.0008,304.00
8.0008,304.00
0.0000.00

0067                          6104.00 18.00273.0004,914.00
BROKEN CONCRETE RIPRAP Mg 273.0004,914.00
273.0004,914.00
273.0004,914.00

GROUP 4 CULVERTSContracted304,583.20
Current304,583.20
In place299,028.14
This Estimate32,307.87

GROUP 4A CONCRETE BOX CULVERT AT STA. 35+27.46
0068                          0030.40 1,500.001.0001,500.00
MOBILIZATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0069                          4044.00 5,590.001.0005,590.00
PREPARATION OF STRUCTURE EACH1.0005,590.00
AT STA. 35+27.46 1.0005,590.00
0.0000.00

0070                          4051.01 50.009.000450.00
EXCAVATION FOR BOX CULVERTS m3 9.000450.00
9.000450.00
0.0000.00

0071                          4101.06 340.0084.17028,617.80
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 84.17028,617.80
84.17028,617.80
0.0000.00

0072                          4151.00 1.205,790.0006,948.00
REINFORCING STEEL FOR BOX CULVERT kg 5,790.0006,948.00
5,790.0006,948.00
0.0000.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 35+27.46Contracted43,105.80
Current43,105.80
In place43,105.80
This Estimate0.00

GROUP 4B CONCRETE BOX CULVERT AT STA. 55+27.25
0073                          0030.40 1,500.001.0001,500.00
MOBILIZATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0074                          4044.00 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA. 55+27.25 1.0001,800.00
0.0000.00

0075                          4051.01 30.0030.000900.00
EXCAVATION FOR BOX CULVERTS m3 30.000900.00
30.000900.00
0.0000.00

0076                          4101.06 340.0087.12029,620.80
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 87.12029,620.80
87.12029,620.80
0.0000.00

0077                          4151.00 1.205,272.0006,326.40
REINFORCING STEEL FOR BOX CULVERT kg 5,272.0006,326.40
5,272.0006,326.40
0.0000.00

GROUP 4B CONCRETE BOX CULVERT AT STA. 55+27.25Contracted40,147.20
Current40,147.20
In place40,147.20
This Estimate0.00

GROUP 4C CONCRETE BOX CULVERT AT STA. 62+67.92
0078                          0030.40 1,500.001.0001,500.00
MOBILIZATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0079                          4044.00 3,990.001.0003,990.00
PREPARATION OF STRUCTURE EACH1.0003,990.00
AT STA. 62+67.92 1.0003,990.00
0.0000.00

0080                          4051.01 30.0037.0001,110.00
EXCAVATION FOR BOX CULVERTS m3 37.0001,110.00
37.0001,110.00
0.0000.00

0081                          4101.06 340.0066.70022,678.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 66.70022,678.00
66.70022,678.00
0.0000.00

0082                          4151.00 1.404,181.0005,853.40
REINFORCING STEEL FOR BOX CULVERT kg 4,181.0005,853.40
4,181.0005,853.40
0.0000.00

GROUP 4C CONCRETE BOX CULVERT AT STA. 62+67.92Contracted35,131.40
Current35,131.40
In place35,131.40
This Estimate0.00

GROUP 4D CONCRETE BOX CULVERT AT STA. 81+54.33
0083                          0030.40 1,500.001.0001,500.00
MOBILIZATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0084                          4044.00 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA. 81+54.33 1.0001,800.00
0.0000.00

0085                          4051.01 20.0086.0001,720.00
EXCAVATION FOR BOX CULVERTS m3 86.0001,720.00
86.0001,720.00
0.0000.00

0086                          4101.06 340.0093.04031,633.60
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 93.04031,633.60
93.04031,633.60
0.0000.00

0087                          4151.00 1.206,167.0007,400.40
REINFORCING STEEL FOR BOX CULVERT kg 6,167.0007,400.40
6,167.0007,400.40
0.0000.00

GROUP 4D CONCRETE BOX CULVERT AT STA. 81+54.33Contracted44,054.00
Current44,054.00
In place44,054.00
This Estimate0.00

GROUP 4E CONCRETE BOX CULVERT AT STA. 119+23.50
0088                          0030.40 1,500.001.0001,500.00
MOBILIZATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0089                          4044.00 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA. 119+23.50 1.0001,800.00
0.0000.00

0090                          4051.01 20.0066.0001,320.00
EXCAVATION FOR BOX CULVERTS m3 66.0001,320.00
66.0001,320.00
0.0000.00

0091                          4101.06 340.0063.08021,447.20
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 63.08021,447.20
63.08021,447.20
0.0000.00

0092                          4151.00 1.204,170.0005,004.00
REINFORCING STEEL FOR BOX CULVERT kg 4,170.0005,004.00
4,170.0005,004.00
0.0000.00

GROUP 4E CONCRETE BOX CULVERT AT STA. 119+23.50Contracted31,071.20
Current31,071.20
In place31,071.20
This Estimate0.00

GROUP 4F CONCRETE BOX CULVERT AT STA. 133+11.86
0093                          0030.40 1,500.001.0001,500.00
MOBILIZATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0094                          4044.00 2,190.001.0002,190.00
PREPARATION OF STRUCTURE EACH1.0002,190.00
AT STA. 133+11.86 1.0002,190.00
0.0000.00

0095                          4051.01 30.0031.000930.00
EXCAVATION FOR BOX CULVERTS m3 31.000930.00
31.000930.00
0.0000.00

0096                          4101.06 340.0097.34033,095.60
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 97.34033,095.60
43.76714,880.78
43.76714,880.78

0097                          4151.00 1.206,337.0007,604.40
REINFORCING STEEL FOR BOX CULVERT kg 6,337.0007,604.40
2,892.2533,470.70
2,892.2533,470.70

GROUP 4F CONCRETE BOX CULVERT AT STA. 133+11.86Contracted45,320.00
Current45,320.00
In place22,971.48
This Estimate18,351.48

GROUP 5 SEEDING
0098                          L001.01 1,198.0022.00026,356.00
SEEDING, TYPE A ha 22.00026,356.00
0.0000.00
0.0000.00

0099                          L001.02 913.0011.00010,043.00
SEEDING, TYPE B ha 11.00010,043.00
0.0000.00
0.0000.00

0100                          L020.07 3.641,900.0006,916.00
EROSION CONTROL, TYPE B-1 m2 1,900.0006,916.00
0.0000.00
0.0000.00

0101                          L032.75 65.00150.0009,750.00
MULCH Mg 150.0009,750.00
0.0000.00
0.0000.00

0102                          0030.50 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted55,565.00
Current55,565.00
In place0.00
This Estimate0.00

GROUP 6 BRIDGE AT STA. 100+52.32
0103                          0030.60 12,500.001.00012,500.00
MOBILIZATION LS 1.00012,500.00
0.0000.00
0.0000.00

0104                          1010.01 48.00304.30014,606.40
EXCAVATION (ESTABLISHED QUANTITY) m3 304.30014,606.40
0.0000.00
0.0000.00

0105                          1043.50 2.50327.000817.50
RIPRAP FILTER FABRIC m2 327.000817.50
0.0000.00
0.0000.00

0106                          3050.15 380.00140.80053,504.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 140.80053,504.00
0.0000.00
0.0000.00

0107                          3051.10 1.429,465.00013,440.30
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 9,465.00013,440.30
0.0000.00
0.0000.00

0108                          6000.10 1,500.001.0001,500.00
ABUTMENT NO.1 EXCAVATION LS 1.0001,500.00
0.0000.00
0.0000.00

0109                          6000.11 1,500.001.0001,500.00
ABUTMENT NO.2 EXCAVATION LS 1.0001,500.00
0.0000.00
0.0000.00

0110                          6005.35 180.0028.8005,184.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 28.8005,184.00
0.0000.00
0.0000.00

0111                          6007.02 168.0053.2008,937.60
CLASS II REPAIR m2 53.2008,937.60
0.0000.00
0.0000.00

0112                          6007.03 240.004.000960.00
CLASS III REPAIR m2 4.000960.00
0.0000.00
0.0000.00

0113                          6008.40 42.00446.20018,740.40
PLACING, FINISHING, AND CURING CONCRETE OVERLAY-SF m2 446.20018,740.40
0.0000.00
0.0000.00

0114                          6010.22 490.0042.50020,825.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 42.50020,825.00
0.0000.00
0.0000.00

0115                          6010.26 425.00107.10045,517.50
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 107.10045,517.50
0.0000.00
0.0000.00

0116                          6016.02 550.0022.30012,265.00
CONCRETE FOR OVERLAYS-SF m3 22.30012,265.00
0.0000.00
0.0000.00

0117                          6030.00 22,000.001.00022,000.00
PREPARATION OF BRIDGE EACH1.00022,000.00
AT STA. 100+52.32 0.0000.00
0.0000.00

0118                          6080.00 6.00890.0005,340.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 890.0005,340.00
0.0000.00
0.0000.00

0119                          6104.00 20.0064.0001,280.00
BROKEN CONCRETE RIPRAP Mg 64.0001,280.00
0.0000.00
0.0000.00

0120                          6105.02 39.00120.0004,680.00
ROCK RIPRAP, TYPE B Mg 120.0004,680.00
0.0000.00
0.0000.00

0121                          6131.50 1.4220,015.00028,421.30
EPOXY COATED REINFORCING STEEL kg 20,015.00028,421.30
0.0000.00
0.0000.00

0122                          6200.00 93.00347.60032,326.80
CONCRETE PILING m 347.60032,326.80
0.0000.00
0.0000.00

0123                          6310.00 143.00209.40029,944.20
STEEL SHEET PILING m2 209.40029,944.20
0.0000.00
0.0000.00

0124                          6510.60 6,800.001.0006,800.00
BRIDGE SHORING LS 1.0006,800.00
0.0000.00
0.0000.00

0125                          8091.00 35.0020.800728.00
GRANULAR BACKFILL m3 20.800728.00
0.0000.00
0.0000.00

GROUP 6 BRIDGE AT STA. 100+52.32Contracted341,818.00
Current341,818.00
In place0.00
This Estimate0.00

GROUP 6A BRIDGE AT STA. 10153+48.23
0126                          0030.60 14,500.001.00014,500.00
MOBILIZATION LS 1.00014,500.00
0.0000.00
0.0000.00

0127                          1010.01 56.00112.4006,294.40
EXCAVATION (ESTABLISHED QUANTITY) m3 112.4006,294.40
0.0000.00
0.0000.00

0128                          1043.50 2.50335.000837.50
RIPRAP FILTER FABRIC m2 335.000837.50
0.0000.00
0.0000.00

0129                          3050.15 380.00141.10053,618.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 141.10053,618.00
0.0000.00
0.0000.00

0130                          3051.10 1.429,560.00013,575.20
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 9,560.00013,575.20
0.0000.00
0.0000.00

0131                          6000.10 1,500.001.0001,500.00
ABUTMENT NO.1 EXCAVATION LS 1.0001,500.00
0.0000.00
0.0000.00

0132                          6000.11 1,500.001.0001,500.00
ABUTMENT NO.2 EXCAVATION LS 1.0001,500.00
0.0000.00
0.0000.00

0133                          6005.35 180.0030.7005,526.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 30.7005,526.00
0.0000.00
0.0000.00

0134                          6007.02 168.0039.8006,686.40
CLASS II REPAIR m2 39.8006,686.40
0.0000.00
0.0000.00

0135                          6007.03 240.004.000960.00
CLASS III REPAIR m2 4.000960.00
0.0000.00
0.0000.00

0136                          6008.40 42.00333.30013,998.60
PLACING, FINISHING, AND CURING CONCRETE OVERLAY-SF m2 333.30013,998.60
0.0000.00
0.0000.00

0137                          6010.22 620.0043.90027,218.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 43.90027,218.00
0.0000.00
0.0000.00

0138                          6010.26 510.0067.00034,170.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 67.00034,170.00
0.0000.00
0.0000.00

0139                          6016.02 610.0016.70010,187.00
CONCRETE FOR OVERLAYS-SF m3 16.70010,187.00
0.0000.00
0.0000.00

0140                          6030.00 18,000.001.00018,000.00
PREPARATION OF BRIDGE EACH1.00018,000.00
AT STA. 10153+48.23 0.0000.00
0.0000.00

0141                          6080.00 5.80940.0005,452.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 940.0005,452.00
0.0000.00
0.0000.00

0142                          6104.00 20.0053.0001,060.00
BROKEN CONCRETE RIPRAP Mg 53.0001,060.00
0.0000.00
0.0000.00

0143                          6105.02 39.00157.0006,123.00
ROCK RIPRAP, TYPE B Mg 157.0006,123.00
0.0000.00
0.0000.00

0144                          6131.50 1.4214,180.00020,135.60
EPOXY COATED REINFORCING STEEL kg 14,180.00020,135.60
0.0000.00
0.0000.00

0145                          6200.00 93.00407.60037,906.80
CONCRETE PILING m 407.60037,906.80
0.0000.00
0.0000.00

0146                          6310.00 143.00192.10027,470.30
STEEL SHEET PILING m2 192.10027,470.30
0.0000.00
0.0000.00

0147                          6510.60 6,500.001.0006,500.00
BRIDGE SHORING LS 1.0006,500.00
0.0000.00
0.0000.00

0148                          8091.00 35.0020.100703.50
GRANULAR BACKFILL m3 20.100703.50
0.0000.00
0.0000.00

GROUP 6A BRIDGE AT STA. 10153+48.23Contracted313,922.30
Current313,922.30
In place0.00
This Estimate0.00

GROUP 7 GUARDRAIL
0149                          0030.70 1,000.001.0001,000.00
MOBILIZATION LS 1.0001,000.00
0.0000.00
0.0000.00

0150                          7011.20 43.11114.3204,928.34
W-BEAM GUARDRAIL m 114.3204,928.34
0.0000.00
0.0000.00

0151                          7020.00 2,606.008.00020,848.00
BRIDGE APPROACH SECTIONS EACH8.00020,848.00
0.0000.00
0.0000.00

0152                          7024.27 1,541.008.00012,328.00
GUARDRAIL END TREATMENT, TYPE II EACH8.00012,328.00
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted39,104.34
Current39,104.34
In place0.00
This Estimate0.00

GROUP 8B ELECTRICAL
0153                          A070.10 9.80130.0001,274.00
38 mm CONDUIT IN TRENCH m 130.0001,274.00
0.0000.00
0.0000.00

0154                          A072.10 11.6063.000730.80
38 mm CONDUIT UNDER ROADWAY m 63.000730.80
0.0000.00
0.0000.00

0155                          A080.22 2.60193.000501.80
STREET LIGHTING CABLE, NO. 6 BARE m 193.000501.80
0.0000.00
0.0000.00

0156                          A080.24 2.75386.0001,061.50
STREET LIGHTING CABLE, NO. 6 USE m 386.0001,061.50
0.0000.00
0.0000.00

0157                          A700.20 795.004.0003,180.00
RELOCATE STREET LIGHTING UNIT EACH4.0003,180.00
0.0000.00
0.0000.00

0158                          A706.00 245.001.000245.00
RELOCATE PULL BOX EACH1.000245.00
0.0000.00
0.0000.00

0159                          0030.81 500.001.000500.00
MOBILIZATION LS 1.000500.00
0.0000.00
0.0000.00

GROUP 8B ELECTRICALContracted7,493.10
Current7,493.10
In place0.00
This Estimate0.00

GROUP 9 BITUMINOUS
0160                          0002.55 25.00299.6407,491.00
OVERLAY BROKEN LINES StaM299.6407,491.00
0.0000.00
0.0000.00

0161                          0002.60 25.00599.28014,982.00
OVERLAY SOLID LINES StaM599.28014,982.00
0.0000.00
0.0000.00

0162                          0030.30 75,000.001.00075,000.00
MOBILIZATION LS 1.00075,000.00
0.0000.00
0.0000.00

0163                          1020.03 14.6040.000584.00
DELINEATOR, TYPE III EACH40.000584.00
0.0000.00
0.0000.00

0164                          1020.20 20.5016.000328.00
INSTALL CHEVRONS EACH16.000328.00
0.0000.00
0.0000.00

0165                          1102.05 3.162,972.0009,391.52
REMOVE ASPHALT SURFACING FROM PAVEMENT m2 2,972.0009,391.52
0.0000.00
0.0000.00

0166                          2001.03 15.19198.0003,007.62
GRAVEL SURFACE COURSE Mg 198.0003,007.62
59.126898.12
0.0000.00

0167                          2010.03 18.6753.000989.51
CRUSHED ROCK SURFACE COURSE Mg 53.000989.51
0.0000.00
0.0000.00

0168                          2021.00 50.006.000300.00
MAILBOX POST EACH6.000300.00
0.0000.00
0.0000.00

0169                          3008.05 4.60823.0003,785.80
TIE BARS EACH823.0003,785.80
0.0000.00
0.0000.00

0170                          3031.08 38.024,060.000154,361.20
205 mm CONCRETE BASE COURSE m2 4,060.000154,361.20
0.0000.00
0.0000.00

0171                          3040.11 117.5068.0007,990.00
CONCRETE PAVEMENT REPAIR, TYPE A, FULL DEPTH m2 68.0007,990.00
0.0000.00
0.0000.00

0172                          3040.12 109.63505.40055,407.00
CONCRETE PAVEMENT REPAIR, TYPE B, FULL DEPTH m2 505.40055,407.00
0.0000.00
0.0000.00

0173                          3040.13 100.45752.60075,598.67
CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH m2 752.60075,598.67
0.0000.00
0.0000.00

0174                          3040.18 167.002.700450.90
CONCRETE PAVEMENT REPAIR, TYPE A, PARTIAL DEPTH m2 2.700450.90
0.0000.00
0.0000.00

0175                          3041.25 750.0038.00028,500.00
BITUMINOUS PATCHING Mg 38.00028,500.00
0.0000.00
0.0000.00

0176                          3221.05 112.00129.80014,537.60
CONCRETE PAVEMENT, CLASS PR-25 m2 129.80014,537.60
JOINT REPAIR 0.0000.00
0.0000.00

0177                          8029.75 3.004,088.00012,264.00
BITUMINOUS FOUNDATION COURSE m2 4,088.00012,264.00
0.0000.00
0.0000.00

0178                          8111.00 81.07286.19823,202.07
SHOULDER SUBGRADE PREPARATION StaM286.19823,202.07
0.0000.00
0.0000.00

0179                          9000.75 17.14200.0003,428.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 200.0003,428.00
SPS 0.0000.00
0.0000.00

0180                          9005.23 17.1426,650.000456,781.00
ASPHALTIC CONCRETE, TYPE SPS Mg 26,650.000456,781.00
0.0000.00
0.0000.00

0181                          9005.45 21.9136,050.000789,855.50
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 36,050.000789,855.50
0.0000.00
0.0000.00

0182                          9009.00 2.044,824.0009,840.96
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 4,824.0009,840.96
0.0000.00
0.0000.00

0183                          9009.75 75.0052.0003,900.00
TEMPORARY SURFACING m2 52.0003,900.00
0.0000.00
0.0000.00

0184                          9020.92 190.0010.8002,052.00
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 10.8002,052.00
0.0000.00
0.0000.00

0185                          9021.03 190.001,449.900275,481.00
PERFORMANCE GRADED BINDER (58-28) Mg 1,449.900275,481.00
0.0000.00
0.0000.00

0186                          9021.08 225.001,946.700438,007.50
PERFORMANCE GRADED BINDER (64-28) Mg 1,946.700438,007.50
0.0000.00
0.0000.00

0187                          9034.00 0.784,824.0003,762.72
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 4,824.0003,762.72
0.0000.00
0.0000.00

0188                          9053.00 0.21123,010.00025,832.10
TACK COAT L 123,010.00025,832.10
0.0000.00
0.0000.00

0189                          9111.00 1.501,810.0002,715.00
WATER kL 1,810.0002,715.00
0.0000.00
0.0000.00

0190                          9170.00 210.0912.4562,616.88
EARTH SHOULDER CONSTRUCTION StaM12.4562,616.88
0.0000.00
0.0000.00

0191                          9173.20 2.004,088.0008,176.00
SUBGRADE PREPARATION m2 4,088.0008,176.00
0.0000.00
0.0000.00

0192                          9179.80 893.002.0001,786.00
MILLING CONCRETE FOR INLAYS EACH2.0001,786.00
0.0000.00
0.0000.00

0193                          9188.50 16.27356.0005,792.12
SURFACING UNDER GUARDRAIL m2 356.0005,792.12
0.0000.00
0.0000.00

0194                          9300.50 3,000.001.0003,000.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0003,000.00
0.0000.00
0.0000.00

GROUP 9 BITUMINOUSContracted2,521,197.67
Current2,521,197.67
In place898.12
This Estimate0.00

GROUP 10 GENERAL ITEMS
0195                          0001.08 0.5026,600.00013,300.00
BARRICADE, TYPE II BDAY26,600.00013,300.00
0.0000.00
0.0000.00

0196                          0001.10 1.406,822.0009,550.80
BARRICADE, TYPE III BDAY6,822.0009,550.80
195.000273.00
0.0000.00

0197                          0001.75 1.001,100.0001,100.00
TEMPORARY SIGN DAY EACH1,100.0001,100.00
0.0000.00
0.0000.00

0198                          0001.90 0.3029,908.0008,972.40
SIGN DAY EACH29,908.0008,972.40
738.000221.40
104.00031.20

0199                          0002.30 1.50650.000975.00
PAVEMENT MARKING REMOVAL m 650.000975.00
0.0000.00
0.0000.00

0200                          0002.39 2.951,800.0005,310.00
TEMPORARY PAVEMENT MARKING, TYPE II m 1,800.0005,310.00
0.0000.00
0.0000.00

0201                          0003.10 176.55110.00019,420.50
FLAGGING DAY 110.00019,420.50
31.0005,473.05
3.000529.65

0202                          0003.20 222.9550.00011,147.50
FURNISHING AND OPERATING PILOT VEHICLE DAY 50.00011,147.50
0.0000.00
0.0000.00

0203                          0003.50 167.93167.64028,151.79
CONCRETE PROTECTION BARRIER m 167.64028,151.79
0.0000.00
0.0000.00

0204                          0003.56 23.29464.82010,825.66
RELOCATE CONCRETE PROTECTION BARRIER m 464.82010,825.66
0.0000.00
0.0000.00

0205                          0003.70 400.008.0003,200.00
TEMPORARY RUMBLE STRIP EACH8.0003,200.00
0.0000.00
0.0000.00

0206                          0003.75 12,475.002.00024,950.00
TEMPORARY TRAFFIC SIGNAL EACH2.00024,950.00
0.0000.00
0.0000.00

0207                          0010.04 381.581.000381.58
FIELD OFFICE EACH1.000381.58
0.0000.00
0.0000.00

0208                          0030.00 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted147,285.22
Current147,285.22
In place5,967.45
This Estimate560.85

Totals for contractContracted4,440,125.55
Current4,440,125.55
In place653,123.04
This Estimate51,848.96