Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:3606 DOBSON BROTHERS CONSTRUCTION CO. & AFFIL
Contract ID:1800A
Estimate Number:0002
Pay Period End Date:08.30.2003
Contract Location:
JULIAN NORTH & SOUTHEstimate Type:PROG
Contractor:
DOBSON BROTHERS CONSTRUCTION CO. & AFFILDate Let:06.26.2003
410 S 7THDate Awarded:07.03.2003
PO BOX 81409Date Contract Executed:07.09.2003
Date Notice to Proceed:07.09.2003
LINCOLN NE 68501Date Work Began:
Phone:Date Physical Work Completed:
(402)474-5115Date Accepted:
Escrow Agent:
Surety Co:
WESTERN SURETY COMPANY
Counties
NEMAHA
OTOE
Project Number PCT Fed State Project Number Description
10800A 000  0.000 S-75-2(1025)  GR CP CULV SEED ELEC
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$368,781.50$77,206.89$291,574.61
$12,654,880.65Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$368,781.50$77,206.89$291,574.61
$12,645,541.65Retainage$-3,687.82$-772.07$-2,915.75
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
2.91%Net Earnings$365,093.68$76,434.82$288,658.86
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$365,093.68$76,434.82$288,658.86
Project ManagerDiv. Head/Dist. Eng.
Mueller, Gerald09.04.2003Sklenar, Michael J09.08.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.08.2003
Controller Div. Processed
Burling, Laurie09.09.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 204,755.001.000204,755.00
MOBILIZATION LS 1.000204,755.00
0.0000.00
0.0000.00

0002                          1000.00 252.5048.00012,120.00
LARGE TREE REMOVAL EACH48.00012,120.00
41.00010,352.50
23.0005,807.50

0003                          1009.00 95,950.001.00095,950.00
GENERAL CLEARING AND GRUBBING LS 1.00095,950.00
0.30028,785.00
0.20019,190.00

0004                          1010.00 1.40876,014.0001,226,419.60
EXCAVATION m3 876,014.0001,226,419.60
18,046.00025,264.40
18,046.00025,264.40

0005                          1010.01 2.5325,717.00065,064.01
EXCAVATION (ESTABLISHED QUANTITY) m3 25,717.00065,064.01
0.0000.00
0.0000.00

0006                          1010.10 2.31446,574.0001,031,585.94
EXCAVATION, BORROW m3 446,574.0001,031,585.94
0.0000.00
0.0000.00

0007                          1011.00 2.0013,226.00026,452.00
WATER kL 13,226.00026,452.00
0.0000.00
0.0000.00

0008                          1012.00 60.60295.00017,877.00
RIGHT-OF-WAY MARKERS EACH295.00017,877.00
0.0000.00
0.0000.00

0009                          1090.00 858.506.0005,151.00
ABANDON WELLS EACH6.0005,151.00
0.0000.00
0.0000.00

0010                          1101.25 8.20393.0003,222.60
SAWING PAVEMENT m 393.0003,222.60
0.0000.00
0.0000.00

0011                          1102.00 2.857,835.00022,329.75
REMOVE ASPHALT SURFACE m2 7,835.00022,329.75
0.0000.00
0.0000.00

0012                          1109.00 3.0391.000275.73
REMOVE CURB m 91.000275.73
0.0000.00
0.0000.00

0013                          1122.01 3.03113.000342.39
REMOVE CONCRETE MEDIAN SURFACING m2 113.000342.39
0.0000.00
0.0000.00

0014                          1125.00 505.001.000505.00
CLEAR TRACT EACH1.000505.00
AT STA. 519+11.81 TO STA. 519+98.71 RT. 0.0000.00
0.0000.00

0015                          1125.01 505.001.000505.00
CLEAR TRACT EACH1.000505.00
AT STA. 598+60 TO STA. 599+00 RT. 0.0000.00
0.0000.00

0016                          1701.24 50.50503.80025,441.90
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 503.80025,441.90
0.0000.00
0.0000.00

0017                          1701.30 75.75126.0009,544.50
750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 126.0009,544.50
0.0000.00
0.0000.00

0018                          3275.20 4.05101,663.000411,735.15
CRUSH CONCRETE PAVEMENT m2 101,663.000411,735.15
0.0000.00
0.0000.00

0019                          4018.00 564.792.0001,129.58
TAPPING EXISTING STRUCTURE EACH2.0001,129.58
0.0000.00
0.0000.00

0020                          4050.01 6.06150.000909.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 150.000909.00
0.0000.00
0.0000.00

0021                          4130.06 762.680.180137.28
CLASS 47B-20 OR AX-20 CONCRETE FOR PIPE CULVERT PLUG m3 0.180137.28
0.0000.00
0.0000.00

0022                          4310.60 1,212.001.0001,212.00
1500 mm FLARED-END SECTION EACH1.0001,212.00
0.0000.00
0.0000.00

0023                          7017.00 4.04188.000759.52
REMOVE GUARDRAIL m 188.000759.52
0.0000.00
0.0000.00

0024                          L006.00 202.0089.00017,978.00
COVER CROP SEEDING ha 89.00017,978.00
0.0000.00
0.0000.00

0025                          L006.50 1,363.502.2002,999.70
TEMPORARY SEEDING ha 2.2002,999.70
0.0000.00
0.0000.00

0026                          L020.00 1.439,954.00014,234.22
EROSION CONTROL m2 9,954.00014,234.22
0.0000.00
0.0000.00

0027                          L020.01 4.7551,532.000244,777.00
EROSION CONTROL, TYPE A m2 51,532.000244,777.00
0.0000.00
0.0000.00

0028                          L020.08 4.907,814.00038,288.60
EROSION CONTROL, TYPE AA m2 7,814.00038,288.60
0.0000.00
0.0000.00

0029                          L020.09 10.61760.0008,063.60
EROSION CONTROL, TYPE AAA m2 760.0008,063.60
0.0000.00
0.0000.00

0030                          L020.10 1.4634,270.00050,034.20
EROSION CONTROL, TYPE HV m2 34,270.00050,034.20
0.0000.00
0.0000.00

0031                          L021.00 11.622,613.00030,363.06
EROSION CHECKS BALE2,613.00030,363.06
0.0000.00
0.0000.00

0032                          L021.01 14.652,680.00039,262.00
EROSION CHECKS, TYPE A BALE2,680.00039,262.00
0.0000.00
0.0000.00

0033                          L021.06 13.131,309.00017,187.17
EROSION CHECKS, TYPE HV BALE1,309.00017,187.17
0.0000.00
0.0000.00

0034                          L021.10 14.65728.00010,665.20
EROSION CHECKS, TYPE ST BALE728.00010,665.20
0.0000.00
0.0000.00

0035                          L021.11 18.18219.0003,981.42
EROSION CHECKS, TYPE ST-A BALE219.0003,981.42
0.0000.00
0.0000.00

0036                          L021.15 16.16126.0002,036.16
EROSION CHECKS, TYPE ST-HV BALE126.0002,036.16
0.0000.00
0.0000.00

0037                          L021.21 15.15492.0007,453.80
EROSION CHECKS, TYPE AA BALE492.0007,453.80
0.0000.00
0.0000.00

0038                          L022.11 6.312,154.00013,591.74
FABRIC SILT FENCE-LOW POROSITY m 2,154.00013,591.74
304.0001,918.24
0.0000.00

0039                          L022.12 6.722,575.00017,304.00
FABRIC SILT FENCE-HIGH POROSITY m 2,575.00017,304.00
1,045.0007,022.40
0.0000.00

0040                          L032.80 1,414.008.60012,160.40
HYDROMULCH Mg 8.60012,160.40
0.0000.00
0.0000.00

0041                          P302.60 212.1017.5003,711.75
1500 mm CULVERT PIPE, TYPE 2,3 OR 5 m 17.5003,711.75
0.0000.00
0.0000.00

0042                          P302.66 237.3524.5005,815.08
1650 mm CULVERT PIPE, TYPE 2,3 OR 5 m 24.5005,815.08
0.0000.00
0.0000.00

0043                          P502.18 40.4027.6001,115.04
450 mm CULVERT PIPE, TYPE 2,3,5,7 OR 8 m 27.6001,115.04
0.0000.00
0.0000.00

0044                          P502.24 50.5010.600535.30
600 mm CULVERT PIPE, TYPE 2,3,5,7 OR 8 m 10.600535.30
0.0000.00
0.0000.00

GROUP 1 GRADINGContracted3,704,981.39
Current3,704,981.39
In place73,342.54
This Estimate50,261.90

GROUP 3 CONCRETE PAVEMENT
0045                          0030.30 330,000.001.000330,000.00
MOBILIZATION LS 1.000330,000.00
0.0000.00
0.0000.00

0046                          1020.02 10.61172.0001,824.92
DELINEATOR, TYPE II EACH172.0001,824.92
0.0000.00
0.0000.00

0047                          1020.03 12.1276.000921.12
DELINEATOR, TYPE III EACH76.000921.12
0.0000.00
0.0000.00

0048                          1020.20 16.8716.000269.92
INSTALL CHEVRONS EACH16.000269.92
0.0000.00
0.0000.00

0049                          2009.51 162.4119.4513,159.04
CRUSHED ROCK EMBEDMENT StaM19.4513,159.04
0.0000.00
0.0000.00

0050                          2010.03 13.347,258.00096,821.72
CRUSHED ROCK SURFACE COURSE Mg 7,258.00096,821.72
0.0000.00
0.0000.00

0051                          2021.00 40.4028.0001,131.20
MAILBOX POST EACH28.0001,131.20
0.0000.00
0.0000.00

0052                          3008.05 6.84283.0001,935.72
TIE BARS EACH283.0001,935.72
0.0000.00
0.0000.00

0053                          3012.04 40.9542.0001,719.90
CONCRETE CLASS 47B-25 MEDIAN CURB m 42.0001,719.90
0.0000.00
0.0000.00

0054                          3017.40 22.35110.0002,458.50
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 110.0002,458.50
0.0000.00
0.0000.00

0055                          3075.52 35.531,316.00046,757.48
255 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 1,316.00046,757.48
0.0000.00
0.0000.00

0056                          3075.56 24.39149,216.0003,639,378.24
255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 149,216.0003,639,378.24
0.0000.00
0.0000.00

0057                          3300.50 4,546.931.0004,546.93
PORTLAND CEMENT CONCRETE SMOOTHNESS TESTING LS 1.0004,546.93
0.0000.00
0.0000.00

0058                          4024.55 42.9710.260440.87
FLUME SPILLWAY m 10.260440.87
0.0000.00
0.0000.00

0059                          4024.70 2,675.451.0002,675.45
CONCRETE FLUME, TYPE I EACH1.0002,675.45
0.0000.00
0.0000.00

0060                          7550.03 1.0122,000.00022,220.00
100 mm YELLOW EPOXY PAVEMENT MARKING m 22,000.00022,220.00
0.0000.00
0.0000.00

0061                          7550.04 1.0138,000.00038,380.00
100 mm WHITE EPOXY PAVEMENT MARKING m 38,000.00038,380.00
0.0000.00
0.0000.00

0062                          8022.00 81.113,787.000307,163.57
HYDRATED LIME Mg 3,787.000307,163.57
0.0000.00
0.0000.00

0063                          8029.10 4.27189,327.000808,426.29
AGGREGATE FOUNDATION COURSE-D 100 mm m2 189,327.000808,426.29
0.0000.00
0.0000.00

0064                          8060.05 52.64655.00034,479.20
GRANULAR SUBDRAIN EACH655.00034,479.20
0.0000.00
0.0000.00

0065                          8101.50 1.10189,327.000208,259.70
STABILIZED SUBGRADE m2 189,327.000208,259.70
0.0000.00
0.0000.00

0066                          9000.75 21.47500.00010,735.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.00010,735.00
SP4(12.5) 0.0000.00
0.0000.00

0067                          9005.00 51.38100.0005,138.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0005,138.00
SP4(12.5) 0.0000.00
0.0000.00

0068                          9005.45 21.4714,350.000308,094.50
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 14,350.000308,094.50
0.0000.00
0.0000.00

0069                          9009.00 5.081,820.0009,245.60
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 1,820.0009,245.60
0.0000.00
0.0000.00

0070                          9009.86 12.7941,155.000526,372.45
SURFACING 150mm m2 41,155.000526,372.45
0.0000.00
0.0000.00

0071                          9020.94 230.0027.0006,210.00
PERFORMANCE GRADED BINDER (64-28) FOR STATE MAINTENANCEPATCHING Mg 27.0006,210.00
0.0000.00
0.0000.00

0072                          9021.08 230.00780.300179,469.00
PERFORMANCE GRADED BINDER (64-28) Mg 780.300179,469.00
0.0000.00
0.0000.00

0073                          9034.00 1.541,439.0002,216.06
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 1,439.0002,216.06
0.0000.00
0.0000.00

0074                          9053.00 0.2427,390.0006,573.60
TACK COAT L 27,390.0006,573.60
0.0000.00
0.0000.00

0075                          9111.00 2.334,051.0009,438.83
WATER kL 4,051.0009,438.83
0.0000.00
0.0000.00

0076                          9170.00 131.30390.47951,269.89
EARTH SHOULDER CONSTRUCTION StaM390.47951,269.89
0.0000.00
0.0000.00

0077                          9173.20 1.5222,314.00033,917.28
SUBGRADE PREPARATION m2 22,314.00033,917.28
0.0000.00
0.0000.00

0078                          9179.31 0.7814,944.00011,656.32
COLD MILLING, CLASS 1 m2 14,944.00011,656.32
0.0000.00
0.0000.00

0079                          9179.34 1.56101,663.000158,594.28
COLD MILLING, CLASS 4 m2 101,663.000158,594.28
0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted6,871,900.58
Current6,871,900.58
In place0.00
This Estimate0.00

GROUP 4 CULVERTS
0080                          0030.40 48,000.001.00048,000.00
MOBILIZATION LS 1.00048,000.00
1.00048,000.00
1.00048,000.00

0081                          1043.50 1.5010,153.00015,229.50
RIPRAP FILTER FABRIC m2 10,153.00015,229.50
0.0000.00
0.0000.00

0082                          4020.25 48.96425.00020,808.00
CONCRETE DITCH LINING m2 425.00020,808.00
0.0000.00
0.0000.00

0083                          4044.00 1,111.741.0001,111.74
PREPARATION OF STRUCTURE EACH1.0001,111.74
AT STA. 530+11.3 0.0000.00
0.0000.00

0084                          4044.01 1,931.171.0001,931.17
PREPARATION OF STRUCTURE EACH1.0001,931.17
AT STA. 585+75 0.0000.00
0.0000.00

0085                          4044.02 803.861.000803.86
PREPARATION OF STRUCTURE EACH1.000803.86
AT STA. 596+99.5 0.0000.00
0.0000.00

0086                          4045.00 3,994.151.0003,994.15
REMOVE STRUCTURE EACH1.0003,994.15
AT STA. 517+73.7 0.0000.00
0.0000.00

0087                          4045.01 3,720.991.0003,720.99
REMOVE STRUCTURE EACH1.0003,720.99
AT STA. 596+99.5 0.0000.00
0.0000.00

0088                          4045.02 2,333.031.0002,333.03
REMOVE STRUCTURE EACH1.0002,333.03
AT STA. 600+13 0.0000.00
0.0000.00

0089                          4045.03 2,716.701.0002,716.70
REMOVE STRUCTURE EACH1.0002,716.70
AT STA. 600+96 0.0000.00
0.0000.00

0090                          4045.04 2,620.341.0002,620.34
REMOVE STRUCTURE EACH1.0002,620.34
AT STA. 636+61 0.0000.00
0.0000.00

0091                          4045.05 2,333.031.0002,333.03
REMOVE STRUCTURE EACH1.0002,333.03
AT STA. 641+51 0.0000.00
0.0000.00

0092                          4045.06 5,260.081.0005,260.08
REMOVE STRUCTURE EACH1.0005,260.08
AT STA. 643+10 0.0000.00
0.0000.00

0093                          4045.07 7,230.641.0007,230.64
REMOVE STRUCTURE EACH1.0007,230.64
AT STA. 660+38.4 0.0000.00
0.0000.00

0094                          4045.08 7,408.351.0007,408.35
REMOVE STRUCTURE EACH1.0007,408.35
AT STA. 662+65 0.0000.00
0.0000.00

0095                          4050.01 9.956,761.00067,271.95
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 6,761.00067,271.95
605.5006,024.73
308.5003,069.58

0096                          4051.01 14.063,900.00054,834.00
EXCAVATION FOR BOX CULVERTS m3 3,900.00054,834.00
1,170.00016,450.20
0.0000.00

0097                          4100.06 729.7310.4007,589.19
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 10.4007,589.19
0.0000.00
0.0000.00

0098                          4101.06 311.251,586.090493,670.51
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 1,586.090493,670.51
331.154103,071.68
309.51496,336.23

0099                          4107.07 544.261.500816.39
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 1.500816.39
0.0000.00
0.0000.00

0100                          4130.06 871.150.07060.98
CLASS 47B-20 OR AX-20 CONCRETE FOR PIPE CULVERT PLUG m3 0.07060.98
0.0000.00
0.0000.00

0101                          4150.00 1.65592.000976.80
REINFORCING STEEL FOR HEADWALL kg 592.000976.80
0.0000.00
0.0000.00

0102                          4151.00 1.5395,550.000146,191.50
REINFORCING STEEL FOR BOX CULVERT kg 95,550.000146,191.50
17,109.00026,176.77
15,999.00024,478.47

0103                          4310.24 328.6325.0008,215.75
600 mm FLARED-END SECTION EACH25.0008,215.75
4.0001,314.52
2.000657.26

0104                          4310.30 381.6914.0005,343.66
750 mm FLARED-END SECTION EACH14.0005,343.66
1.000381.69
1.000381.69

0105                          4310.36 605.5113.0007,871.63
900 mm FLARED-END SECTION EACH13.0007,871.63
0.0000.00
0.0000.00

0106                          4310.42 753.2612.0009,039.12
1050 mm FLARED-END SECTION EACH12.0009,039.12
0.0000.00
0.0000.00

0107                          4310.48 847.854.0003,391.40
1200 mm FLARED-END SECTION EACH4.0003,391.40
1.000847.85
1.000847.85

0108                          4310.54 1,036.384.0004,145.52
1350 mm FLARED-END SECTION EACH4.0004,145.52
2.0002,072.76
0.0000.00

0109                          4310.60 1,271.274.0005,085.08
1500 mm FLARED-END SECTION EACH4.0005,085.08
0.0000.00
0.0000.00

0110                          4310.66 1,913.084.0007,652.32
1650 mm FLARED-END SECTION EACH4.0007,652.32
1.0001,913.08
1.0001,913.08

0111                          4320.36 786.042.0001,572.08
900 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.0001,572.08
0.0000.00
0.0000.00

0112                          6105.01 30.524,245.000129,557.40
ROCK RIPRAP, TYPE A Mg 4,245.000129,557.40
0.0000.00
0.0000.00

0113                          6105.02 30.522,788.00085,089.76
ROCK RIPRAP, TYPE B Mg 2,788.00085,089.76
0.0000.00
0.0000.00

0114                          P120.24 116.6321.0002,449.23
600 mm CULVERT PIPE, TYPE 2 m 21.0002,449.23
21.0002,449.23
21.0002,449.23

0115                          P120.42 267.25210.00056,122.50
1050 mm CULVERT PIPE TYPE 2 m 210.00056,122.50
0.0000.00
0.0000.00

0116                          P120.48 318.40124.10039,513.44
1200 mm CULVERT PIPE, TYPE 2 m 124.10039,513.44
53.50017,034.40
53.50017,034.40

0117                          P120.54 367.3475.00027,550.50
1350 mm CULVERT PIPE, TYPE 2 m 75.00027,550.50
47.50017,448.65
0.0000.00

0118                          P120.60 449.17156.50070,295.11
1500 mm CULVERT PIPE, TYPE 2 m 156.50070,295.11
0.0000.00
0.0000.00

0119                          P120.66 534.24209.500111,923.28
1650 mm CULVERT PIPE, TYPE 2 m 209.500111,923.28
64.60034,511.90
64.60034,511.90

0120                          P127.36 255.3823.5006,001.43
900 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 m 23.5006,001.43
0.0000.00
0.0000.00

0121                          P311.24 116.63314.50036,680.14
600 mm CULVERT PIPE, TYPE 2, 7 OR 8 m 314.50036,680.14
50.0005,831.50
0.0000.00

0122                          P311.30 173.40280.90048,708.06
750 mm CULVERT PIPE, TYPE 2,7 OR 8 m 280.90048,708.06
65.20011,305.68
65.20011,305.68

0123                          P311.36 203.90223.10045,490.09
900 mm CULVERT PIPE, TYPE 2,7 OR 8 m 223.10045,490.09
0.0000.00
0.0000.00

0124                          P400.18 275.911.000275.91
450 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 1.000275.91
0.0000.00
0.0000.00

6001                          4051.12 31.130.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 300.0009,339.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT 0.0000.00
0.0000.00

GROUP 4 CULVERTSContracted1,608,886.31
Current1,618,225.31
In place294,834.64
This Estimate240,985.37

GROUP 4A CULVERT AT STA. 226+42
0125                          0030.40 5,050.001.0005,050.00
MOBILIZATION LS 1.0005,050.00
0.0000.00
0.0000.00

0126                          4051.01 14.06633.0008,899.98
EXCAVATION FOR BOX CULVERTS m3 633.0008,899.98
0.0000.00
0.0000.00

0127                          4101.06 309.36247.45076,551.13
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 247.45076,551.13
0.0000.00
0.0000.00

0128                          4151.00 1.5315,454.00023,644.62
REINFORCING STEEL FOR BOX CULVERT kg 15,454.00023,644.62
0.0000.00
0.0000.00

0129                          6040.00 17,068.201.00017,068.20
REMOVE STRUCTURE EACH1.00017,068.20
AT STA. 226+42.9 0.0000.00
0.0000.00

GROUP 4A CULVERT AT STA. 226+42Contracted131,213.93
Current131,213.93
In place0.00
This Estimate0.00

GROUP 5 SEEDING
0130                          0030.50 505.001.000505.00
MOBILIZATION LS 1.000505.00
0.0000.00
0.0000.00

0131                          L001.01 1,520.0578.000118,563.90
SEEDING, TYPE A ha 78.000118,563.90
0.0000.00
0.0000.00

0132                          L001.02 1,060.5011.00011,665.50
SEEDING, TYPE B ha 11.00011,665.50
0.0000.00
0.0000.00

0133                          L020.07 2.933,372.0009,879.96
EROSION CONTROL, TYPE B-1 m2 3,372.0009,879.96
0.0000.00
0.0000.00

0134                          L032.75 78.78445.00035,057.10
MULCH Mg 445.00035,057.10
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted175,671.46
Current175,671.46
In place0.00
This Estimate0.00

GROUP 8B ELECTRICAL
0135                          0030.81 2,525.001.0002,525.00
MOBILIZATION LS 1.0002,525.00
0.0000.00
0.0000.00

0136                          A001.12 338.352.000676.70
PULL BOX, TYPE PB-5 EACH2.000676.70
0.0000.00
0.0000.00

0137                          A009.16 1,459.4513.00018,972.85
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.20 EACH13.00018,972.85
0.0000.00
0.0000.00

0138                          A020.10 1,080.702.0002,161.40
LIGHTING CONTROL CENTER, TYPE D EACH2.0002,161.40
0.0000.00
0.0000.00

0139                          A070.10 7.37487.0003,589.19
38 mm CONDUIT IN TRENCH m 487.0003,589.19
0.0000.00
0.0000.00

0140                          A072.10 11.62126.0001,464.12
38 mm CONDUIT UNDER ROADWAY m 126.0001,464.12
0.0000.00
0.0000.00

0141                          A074.12 51.5119.000978.69
38 mm CONDUIT, JACKED m 19.000978.69
0.0000.00
0.0000.00

0142                          A080.22 2.78632.0001,756.96
STREET LIGHTING CABLE, NO. 6 BARE m 632.0001,756.96
0.0000.00
0.0000.00

0143                          A080.24 2.981,264.0003,766.72
STREET LIGHTING CABLE, NO. 6 USE m 1,264.0003,766.72
0.0000.00
0.0000.00

0144                          A600.00 267.653.000802.95
REMOVE LIGHTING UNIT EACH3.000802.95
0.0000.00
0.0000.00

GROUP 8B ELECTRICALContracted36,694.58
Current36,694.58
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0145                          0001.08 0.501,450.000725.00
BARRICADE, TYPE II BDAY1,450.000725.00
0.0000.00
0.0000.00

0146                          0001.10 0.5133,420.00017,044.20
BARRICADE, TYPE III BDAY33,420.00017,044.20
312.000159.12
169.00086.19

0147                          0001.75 4.04100.000404.00
TEMPORARY SIGN DAY EACH100.000404.00
0.0000.00
0.0000.00

0148                          0001.90 0.3552,963.00018,537.05
SIGN DAY EACH52,963.00018,537.05
1,272.000445.20
689.000241.15

0149                          0001.99 0.5614,417.0008,073.52
CONTRACTOR FURNISHED SIGN DAY EACH14,417.0008,073.52
0.0000.00
0.0000.00

0150                          0002.44 1.014,500.0004,545.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT m 4,500.0004,545.00
0.0000.00
0.0000.00

0151                          0003.10 166.58140.00023,321.20
FLAGGING DAY 140.00023,321.20
0.0000.00
0.0000.00

0152                          0010.04 2,713.831.0002,713.83
FIELD OFFICE EACH1.0002,713.83
0.0000.00
0.0000.00

0153                          0030.00 10,100.001.00010,100.00
MOBILIZATION LS 1.00010,100.00
0.0000.00
0.0000.00

0154                          9110.01 58.56150.0008,784.00
RENTAL OF LOADER, FULLY OPERATED HOUR150.0008,784.00
0.0000.00
0.0000.00

0155                          9110.02 55.1710.000551.70
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR10.000551.70
0.0000.00
0.0000.00

0156                          9110.03 50.64150.0007,596.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR150.0007,596.00
0.0000.00
0.0000.00

0157                          9110.06 58.56140.0008,198.40
RENTAL OF BACKHOE, FULLY OPERATED HOUR140.0008,198.40
0.0000.00
0.0000.00

0158                          9110.07 37.33150.0005,599.50
RENTAL OF SKID LOADER, FULLY OPERATED HOUR150.0005,599.50
0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted116,193.40
Current116,193.40
In place604.32
This Estimate327.34

Totals for contractContracted12,645,541.65
Current12,654,880.65
In place368,781.50
This Estimate291,574.61