Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0574 CONSTRUCTORS, INC.
Contract ID:1667
Estimate Number:0002
Pay Period End Date:08.30.2003
Contract Location:
N-2 @ 148TH STREET, LINCOLNEstimate Type:PROG
Contractor:
CONSTRUCTORS, INC.Date Let:04.17.2003
1815 Y STREETDate Awarded:04.24.2003
PO BOX 80268Date Contract Executed:05.06.2003
Date Notice to Proceed:05.06.2003
LINCOLN NE 68501Date Work Began:07.14.2003
Phone:Date Physical Work Completed:
(402)434-1764Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
LANCASTER
Project Number PCT Fed State Project Number Description
12667 000  0.000 RD-2-6(1024)  GR CP
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$174,515.72$167,127.72$7,388.00
$175,007.40Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$174,515.72$167,127.72$7,388.00
$175,007.40Retainage$-1,745.16$-1,671.28$-73.88
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
99.72%Net Earnings$172,770.56$165,456.44$7,314.12
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$172,770.56$165,456.44$7,314.12
Project ManagerDiv. Head/Dist. Eng.
Traudt, Bob09.02.2003Sklenar, Michael J09.02.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.02.2003
Controller Div. Processed
Burling, Laurie09.03.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.5321,596.00

0002                          1009.00 300.001.000300.00
GENERAL CLEARING AND GRUBBING LS 1.000300.00
1.000300.00
0.0000.00

0003                          1010.01 2.001,490.0002,980.00
EXCAVATION (ESTABLISHED QUANTITY) CY 1,490.0002,980.00
1,490.0002,980.00
0.0000.00

0004                          1011.00 16.007.000112.00
WATER MGAL7.000112.00
0.0000.00
0.0000.00

0005                          1012.00 70.002.000140.00
RIGHT-OF-WAY MARKERS EACH2.000140.00
1.00070.00
0.0000.00

0006                          1021.00 25.004.000100.00
REMOVE AND RESET DELINEATORS EACH4.000100.00
5.000125.00
0.0000.00

0007                          4035.25 120.002.000240.00
REMOVE AND SALVAGE FLARED-END SECTION EACH2.000240.00
2.000240.00
0.0000.00

0008                          4050.01 12.0016.000192.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS CY 16.000192.00
16.000192.00
0.0000.00

0009                          4107.07 400.000.420168.00
CLASS 47B-3000 OR AX-3000 CONCRETE FOR CONCRETE COLLARS CY 0.420168.00
0.0000.00
0.0000.00

0010                          4157.00 2.0038.00076.00
REINFORCING STEEL FOR COLLARS LB 38.00076.00
0.0000.00
0.0000.00

0011                          4362.36 245.001.000245.00
INSTALL 36" METAL FLARED-END SECTION EACH1.000245.00
1.000245.00
0.0000.00

0012                          4461.18 450.001.000450.00
INSTALL 18" CONCRETE FLARED-END SECTION EACH1.000450.00
1.000450.00
0.0000.00

0013                          L020.01 8.25200.0001,650.00
EROSION CONTROL, TYPE A SY 200.0001,650.00
200.0001,650.00
0.0000.00

0014                          L020.10 2.00996.0001,992.00
EROSION CONTROL, TYPE HV SY 996.0001,992.00
942.0001,884.00
0.0000.00

0015                          L021.06 15.5036.000558.00
EROSION CHECKS, TYPE HV BALE36.000558.00
36.000558.00
0.0000.00

0016                          P120.18 31.0022.000682.00
18" CULVERT PIPE, TYPE 2 LF 22.000682.00
22.000682.00
0.0000.00

0017                          P300.36 42.0028.0001,176.00
36" CULVERT PIPE, TYPE 3,4 OR 5 LF 28.0001,176.00
28.0001,176.00
0.0000.00

GROUP 1 GRADINGContracted14,061.00
Current14,061.00
In place13,552.00
This Estimate1,596.00

GROUP 3 CONCRETE PAVEMENT
0018                          0030.30 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0019                          1136.01 55.002.000110.00
REMOVE EACH2.000110.00
UNDERDRAIN HEADWALL 1.00055.00
0.0000.00

0020                          3008.05 6.50246.0001,599.00
TIE BARS EACH246.0001,599.00
358.0002,327.00
0.0000.00

0021                          3017.40 100.008.000800.00
CONCRETE CLASS 47B-3000 MEDIAN SURFACING SY 8.000800.00
6.540654.00
0.0000.00

0022                          3075.56 33.503,228.000108,138.00
10" DOWELED CONCRETE PAVEMENT, CLASS 47B-3500 SY 3,228.000108,138.00
3,181.490106,579.92
0.0000.00

0023                          4763.26 240.002.000480.00
UNDERDRAIN HEADWALL EACH2.000480.00
2.000480.00
0.0000.00

0024                          4764.34 12.0092.0001,104.00
4" NONPERFORATED PIPE UNDERDRAIN LF 92.0001,104.00
60.000720.00
0.0000.00

0025                          7502.14 2.401,300.0003,120.00
4" WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED LF 1,300.0003,120.00
1,290.4003,096.96
0.0000.00

0026                          7508.14 7.50500.0003,750.00
12" WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED LF 500.0003,750.00
432.1003,240.75
0.0000.00

0027                          8029.84 2.503,228.0008,070.00
BITUMINOUS FOUNDATION COURSE 4" SY 3,228.0008,070.00
3,181.4907,953.73
0.0000.00

0028                          8060.05 150.005.000750.00
GRANULAR SUBDRAIN EACH5.000750.00
5.000750.00
0.0000.00

0029                          9111.00 8.0013.000104.00
WATER MGAL13.000104.00
0.0000.00
0.0000.00

0030                          9170.00 200.0013.0272,605.40
EARTH SHOULDER CONSTRUCTION STA 13.0272,605.40
13.0272,605.40
0.0000.00

0031                          9173.20 2.003,228.0006,456.00
SUBGRADE PREPARATION SY 3,228.0006,456.00
3,181.4906,362.98
0.0000.00

0032                          9179.34 3.501,419.0004,966.50
COLD MILLING, CLASS 4 SY 1,419.0004,966.50
1,430.9955,008.48
0.0000.00

0033                          A009.14 1,710.002.0003,420.00
STREET LIGHTING UNIT, TYPE SL-BT-40-12-0.25 EACH2.0003,420.00
2.0003,420.00
2.0003,420.00

0034                          A070.10 2.90590.0001,711.00
1 1/2-INCH CONDUIT IN TRENCH LF 590.0001,711.00
595.0001,725.50
0.0000.00

0035                          A080.22 1.00710.000710.00
STREET LIGHTING CABLE, NO. 6 BARE LF 710.000710.00
715.000715.00
0.0000.00

0036                          A080.24 1.001,420.0001,420.00
STREET LIGHTING CABLE, NO. 6 USE LF 1,420.0001,420.00
1,430.0001,430.00
0.0000.00

0037                          A700.20 750.002.0001,500.00
RELOCATE STREET LIGHTING UNIT EACH2.0001,500.00
2.0001,500.00
0.0000.00

0038                          L001.02 2,100.000.9001,890.00
SEEDING, TYPE B ACRE0.9001,890.00
1.0202,142.00
1.0202,142.00

0039                          L032.75 100.002.000200.00
MULCH TON 2.000200.00
2.300230.00
2.300230.00

GROUP 3 CONCRETE PAVEMENTContracted157,903.90
Current157,903.90
In place155,996.72
This Estimate5,792.00

GROUP 10 GENERAL ITEMS
0040                          0001.08 0.50525.000262.50
BARRICADE, TYPE II BDAY525.000262.50
2,851.0001,425.50
0.0000.00

0041                          0001.10 2.00295.000590.00
BARRICADE, TYPE III BDAY295.000590.00
535.0001,070.00
0.0000.00

0042                          0001.75 3.00180.000540.00
TEMPORARY SIGN DAY EACH180.000540.00
0.0000.00
0.0000.00

0043                          0001.90 0.50600.000300.00
SIGN DAY EACH600.000300.00
1,285.000642.50
0.0000.00

0044                          0001.99 3.50100.000350.00
CONTRACTOR FURNISHED SIGN DAY EACH100.000350.00
64.000224.00
0.0000.00

0045                          0002.97 55.0015.000825.00
FLASHING ARROW PANEL DAY 15.000825.00
26.0001,430.00
0.0000.00

0046                          0030.00 175.001.000175.00
MOBILIZATION LS 1.000175.00
1.000175.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted3,042.50
Current3,042.50
In place4,967.00
This Estimate0.00

Totals for contractContracted175,007.40
Current175,007.40
In place174,515.72
This Estimate7,388.00