| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 6 BRIDGE AT STA. 20+87 | | |
|
0001 L006.00 | 100.00 | 5.000 | 500.00
|
COVER CROP SEEDING | ACRE | 5.000 | 500.00
|
| | 5.000 | 500.00
|
| | 0.000 | 0.00
|
| | |
|
0002 0001.10 | 1.10 | 2,109.000 | 2,319.90
|
BARRICADE, TYPE III | BDAY | 2,109.000 | 2,319.90
|
| | 2,184.000 | 2,402.40
|
| | 98.000 | 107.80
|
| | |
|
0003 0001.30 | 0.95 | 292.000 | 277.40
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 292.000 | 277.40
|
| | 0.000 | 0.00
|
| | -98.000 | -93.10
|
| | |
|
0004 0001.90 | 0.40 | 1,752.000 | 700.80
|
SIGN DAY | EACH | 1,752.000 | 700.80
|
| | 936.000 | 374.40
|
| | 0.000 | 0.00
|
| | |
|
0005 0030.60 | 20,300.00 | 1.000 | 20,300.00
|
MOBILIZATION | LS | 1.000 | 20,300.00
|
| | 1.000 | 20,300.00
|
| | 0.000 | 0.00
|
| | |
|
0006 1000.00 | 150.00 | 1.000 | 150.00
|
LARGE TREE REMOVAL | EACH | 1.000 | 150.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0007 1009.00 | 2,900.00 | 1.000 | 2,900.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 2,900.00
|
| | 1.000 | 2,900.00
|
| | 0.000 | 0.00
|
| | |
|
0008 1011.00 | 9.99 | 43.000 | 429.57
|
WATER | MGAL | 43.000 | 429.57
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0009 1030.00 | 1.35 | 11,876.000 | 16,032.60
|
EARTHWORK MEASURED IN EMBANKMENT | CY | 11,876.000 | 16,032.60
|
| | 11,876.000 | 16,032.60
|
| | 0.000 | 0.00
|
| | |
|
0010 1300.24 | 12.46 | 32.000 | 398.72
|
24" DRIVEWAY CULVERT PIPE | LF | 32.000 | 398.72
|
| | 32.000 | 398.72
|
| | 0.000 | 0.00
|
| | |
|
0011 1300.36 | 22.88 | 34.000 | 777.92
|
36" DRIVEWAY CULVERT PIPE | LF | 34.000 | 777.92
|
| | 34.000 | 777.92
|
| | 0.000 | 0.00
|
| | |
|
0012 1305.24 | 13.56 | 28.000 | 379.68
|
24" ROUND EQUIVALENT DRIVEWAY CULVERT PIPE | LF | 28.000 | 379.68
|
| | 28.000 | 379.68
|
| | 0.000 | 0.00
|
| | |
|
0013 2021.00 | 50.00 | 1.000 | 50.00
|
MAILBOX POST | EACH | 1.000 | 50.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0014 4040.00 | 101.00 | 2.000 | 202.00
|
REMOVE HEADWALLS FROM CULVERTS | EACH | 2.000 | 202.00
|
| | 2.000 | 202.00
|
| | 0.000 | 0.00
|
| | |
|
0015 4043.00 | 3.21 | 140.000 | 449.40
|
REMOVE CULVERT PIPE | LF | 140.000 | 449.40
|
| | 36.000 | 115.56
|
| | 0.000 | 0.00
|
| | |
|
0016 4050.01 | 6.99 | 707.000 | 4,941.93
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | CY | 707.000 | 4,941.93
|
| | 707.000 | 4,941.93
|
| | 0.000 | 0.00
|
| | |
|
0017 4300.24 | 14.83 | 198.000 | 2,936.34
|
24" CULVERT PIPE | LF | 198.000 | 2,936.34
|
| | 198.000 | 2,936.34
|
| | 0.000 | 0.00
|
| | |
|
0018 4305.24 | 15.43 | 36.000 | 555.48
|
24" ROUND EQUIVALENT CULVERT PIPE | LF | 36.000 | 555.48
|
| | 36.000 | 555.48
|
| | 0.000 | 0.00
|
| | |
|
0019 4305.60 | 82.50 | 120.000 | 9,900.00
|
60" ROUND EQUIVALENT CULVERT PIPE | LF | 120.000 | 9,900.00
|
| | 120.000 | 9,900.00
|
| | 0.000 | 0.00
|
| | |
|
0020 4310.24 | 125.12 | 2.000 | 250.24
|
24" FLARED-END SECTION | EACH | 2.000 | 250.24
|
| | 2.000 | 250.24
|
| | 0.000 | 0.00
|
| | |
|
0021 4320.24 | 122.00 | 2.000 | 244.00
|
24" ROUND EQUIVALENT FLARED-END SECTION | EACH | 2.000 | 244.00
|
| | 2.000 | 244.00
|
| | 0.000 | 0.00
|
| | |
|
0022 4320.60 | 866.41 | 6.000 | 5,198.46
|
60" ROUND EQUIVALENT FLARED-END SECTION | EACH | 6.000 | 5,198.46
|
| | 6.000 | 5,198.46
|
| | 0.000 | 0.00
|
| | |
|
0023 6000.10 | 2,000.00 | 1.000 | 2,000.00
|
ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 2,000.00
|
| | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
0024 6000.11 | 2,000.00 | 1.000 | 2,000.00
|
ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 2,000.00
|
| | 1.000 | 2,000.00
|
| | 0.500 | 1,000.00
|
| | |
|
0025 6001.00 | 8,000.00 | 1.000 | 8,000.00
|
BENT NO.1 EXCAVATION | LS | 1.000 | 8,000.00
|
| | 1.000 | 8,000.00
|
| | 0.000 | 0.00
|
| | |
|
0026 6001.01 | 8,000.00 | 1.000 | 8,000.00
|
BENT NO.2 EXCAVATION | LS | 1.000 | 8,000.00
|
| | 1.000 | 8,000.00
|
| | 0.500 | 4,000.00
|
| | |
|
0027 6010.22 | 270.00 | 298.400 | 80,568.00
|
CLASS 47B-3000 CONCRETE FOR BRIDGE | CY | 298.400 | 80,568.00
|
| | 298.400 | 80,568.00
|
| | 0.000 | 0.00
|
| | |
|
0028 6010.26 | 290.00 | 200.300 | 58,087.00
|
CLASS 47BD-4000 CONCRETE FOR BRIDGE | CY | 200.300 | 58,087.00
|
| | 200.300 | 58,087.00
|
| | 0.000 | 0.00
|
| | |
|
0029 6020.00 | 0.55 | 53,145.000 | 29,229.75
|
REINFORCING STEEL FOR BRIDGE | LB | 53,145.000 | 29,229.75
|
| | 53,145.000 | 29,229.76
|
| | 0.000 | 0.00
|
| | |
|
0030 6040.00 | 8,000.00 | 1.000 | 8,000.00
|
REMOVE STRUCTURE | EACH | 1.000 | 8,000.00
|
AT STA 20+88 | | 1.000 | 8,000.00
|
| | 0.000 | 0.00
|
| | |
|
0031 6080.00 | 2.50 | 3,270.000 | 8,175.00
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | LB | 3,270.000 | 8,175.00
|
| | 3,270.000 | 8,175.00
|
| | 0.000 | 0.00
|
| | |
|
0032 6105.02 | 33.00 | 729.000 | 24,057.00
|
ROCK RIPRAP, TYPE B | TON | 729.000 | 24,057.00
|
| | 722.170 | 23,831.61
|
| | 0.000 | 0.00
|
| | |
|
0033 6210.12 | 21.00 | 1,950.000 | 40,950.00
|
HP 10"X42# STEEL PILING | LF | 1,950.000 | 40,950.00
|
| | 1,950.000 | 40,950.00
|
| | 0.000 | 0.00
|
| | |
|
0034 7020.00 | 1,000.00 | 4.000 | 4,000.00
|
BRIDGE APPROACH SECTIONS | EACH | 4.000 | 4,000.00
|
| | 4.000 | 4,000.00
|
| | 0.000 | 0.00
|
| | |
|
0035 7021.45 | 950.00 | 4.000 | 3,800.00
|
BREAKAWAY CABLE TERMINAL | EACH | 4.000 | 3,800.00
|
| | 4.000 | 3,800.00
|
| | 0.000 | 0.00
|
| | |
|
0401 0001.99 | 0.68 | 0.000 | 0.00
|
CONTRACTOR FURNISHED SIGN DAY | EACH | 500.000 | 340.00
|
| | 624.000 | 424.32
|
| | 0.000 | 0.00
|
| | |
|
601 4051.12 | 27.32 | 0.000 | 0.00
|
GRANULAR MATERIAL FOR FOUNDATIONS OF BOX CULVERTS | CY | 103.000 | 2,813.96
|
GRANULAR MATERIAL FOR FOUNDATIONSGRANULAR MATERIAL FOR FOUNDATIONS | | 103.000 | 2,813.96
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 20+87 | | Contracted | 346,761.19
|
| | Current | 349,915.15
|
| | In place | 348,289.38
|
| | This Estimate | 5,014.70
|
| | |
|
Totals for contract | | Contracted | 346,761.19
|
---|
| | Current | 349,915.15
|
---|
| | In place | 348,289.38
|
---|
| | This Estimate | 5,014.70
|
---|