| | | 1. Contracted
|
|---|
| | | 2. Current
|
|---|
| | | 3. To date
|
|---|
| Item Nbr Item Code | Unit Price | | 4. This Est
|
|---|
| Item Description | Units | Qty | Amount
|
|---|
| GROUP 6 BRIDGE AT STA. 16+85 | | |
|
| 0001 L006.00 | 125.00 | 3.000 | 375.00
|
| COVER CROP SEEDING | ACRE | 3.000 | 375.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0002 0001.10 | 1.00 | 3,432.000 | 3,432.00
|
| BARRICADE, TYPE III | BDAY | 3,432.000 | 3,432.00
|
| | | 1,384.000 | 1,384.00
|
| | 280.000 | 280.00
|
| | |
|
| 0003 0001.90 | 0.65 | 5,720.000 | 3,718.00
|
| SIGN DAY | EACH | 5,720.000 | 3,718.00
|
| | | 1,038.000 | 674.70
|
| | 210.000 | 136.50
|
| | |
|
| 0004 0030.60 | 22,000.00 | 1.000 | 22,000.00
|
| MOBILIZATION | LS | 1.000 | 22,000.00
|
| | | 1.000 | 22,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0005 1000.00 | 150.00 | 1.000 | 150.00
|
| LARGE TREE REMOVAL | EACH | 1.000 | 150.00
|
| | | 8.000 | 1,200.00
|
| | 0.000 | 0.00
|
| | |
|
| 0006 1009.00 | 4,250.00 | 1.000 | 4,250.00
|
| GENERAL CLEARING AND GRUBBING | LS | 1.000 | 4,250.00
|
| | | 0.700 | 2,975.00
|
| | 0.000 | 0.00
|
| | |
|
| 0007 1010.01 | 1.85 | 11,226.000 | 20,768.10
|
| EXCAVATION (ESTABLISHED QUANTITY) | CY | 11,226.000 | 20,768.10
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0008 1011.00 | 30.00 | 14.000 | 420.00
|
| WATER | MGAL | 14.000 | 420.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0009 1043.50 | 2.00 | 2,407.000 | 4,814.00
|
| RIPRAP FILTER FABRIC | SY | 2,407.000 | 4,814.00
|
| | | 806.000 | 1,612.00
|
| | 806.000 | 1,612.00
|
| | |
|
| 0010 1300.24 | 17.01 | 166.000 | 2,823.66
|
| 24" DRIVEWAY CULVERT PIPE | LF | 166.000 | 2,823.66
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0011 2010.03 | 16.10 | 173.000 | 2,785.30
|
| CRUSHED ROCK SURFACE COURSE | TON | 173.000 | 2,785.30
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0012 4050.01 | 4.25 | 538.000 | 2,286.50
|
| EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | CY | 538.000 | 2,286.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0013 4300.24 | 17.10 | 180.000 | 3,078.00
|
| 24" CULVERT PIPE | LF | 180.000 | 3,078.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0014 4300.36 | 30.00 | 186.000 | 5,580.00
|
| 36" CULVERT PIPE | LF | 186.000 | 5,580.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0015 4310.24 | 152.60 | 3.000 | 457.80
|
| 24" FLARED-END SECTION | EACH | 3.000 | 457.80
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0016 4310.36 | 411.00 | 2.000 | 822.00
|
| 36" FLARED-END SECTION | EACH | 2.000 | 822.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0017 6000.10 | 3,000.00 | 1.000 | 3,000.00
|
| ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 3,000.00
|
| | | 1.000 | 3,000.00
|
| | 1.000 | 3,000.00
|
| | |
|
| 0018 6000.11 | 3,000.00 | 1.000 | 3,000.00
|
| ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 3,000.00
|
| | | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0019 6000.60 | 11,000.00 | 1.000 | 11,000.00
|
| PIER NO.1 EXCAVATION | LS | 1.000 | 11,000.00
|
| | | 1.000 | 11,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0020 6000.61 | 11,000.00 | 1.000 | 11,000.00
|
| PIER NO.2 EXCAVATION | LS | 1.000 | 11,000.00
|
| | | 1.000 | 11,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0021 6005.78 | 900.00 | 12.000 | 10,800.00
|
| EXPANSION BEARING, TFE TYPE | EACH | 12.000 | 10,800.00
|
| | | 12.000 | 10,800.00
|
| | 12.000 | 10,800.00
|
| | |
|
| 0022 6005.83 | 900.00 | 4.000 | 3,600.00
|
| FIXED BEARING | EACH | 4.000 | 3,600.00
|
| | | 4.000 | 3,600.00
|
| | 4.000 | 3,600.00
|
| | |
|
| 0023 6010.22 | 250.00 | 436.900 | 109,225.00
|
| CLASS 47B-3000 CONCRETE FOR BRIDGE | CY | 436.900 | 109,225.00
|
| | | 436.900 | 109,225.00
|
| | 76.700 | 19,175.00
|
| | |
|
| 0024 6010.26 | 290.00 | 153.400 | 44,486.00
|
| CLASS 47BD-4000 CONCRETE FOR BRIDGE | CY | 153.400 | 44,486.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0025 6020.00 | 0.55 | 57,465.000 | 31,605.75
|
| REINFORCING STEEL FOR BRIDGE | LB | 57,465.000 | 31,605.75
|
| | | 20,367.000 | 11,201.86
|
| | 4,272.000 | 2,349.60
|
| | |
|
| 0026 6040.00 | 7,000.00 | 1.000 | 7,000.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 7,000.00
|
| AT STA. 16+89 | | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0027 6071.12 | 75,000.00 | 1.000 | 75,000.00
|
| STEEL SUPERSTRUCTURE | LS | 1.000 | 75,000.00
|
| AT STA. 16+85 | | 1.000 | 75,000.00
|
| | 1.000 | 75,000.00
|
| | |
|
| 0028 6080.00 | 3.00 | 3,860.000 | 11,580.00
|
| STRUCTURAL STEEL FOR SUBSTRUCTURE | LB | 3,860.000 | 11,580.00
|
| | | 3,374.000 | 10,122.00
|
| | 1,750.000 | 5,250.00
|
| | |
|
| 0029 6105.02 | 24.00 | 2,221.000 | 53,304.00
|
| ROCK RIPRAP, TYPE B | TON | 2,221.000 | 53,304.00
|
| | | 1,132.710 | 27,185.04
|
| | 1,132.710 | 27,185.04
|
| | |
|
| 0030 6210.14 | 22.00 | 3,080.000 | 67,760.00
|
| HP 12"X53# STEEL PILING | LF | 3,080.000 | 67,760.00
|
| | | 3,080.000 | 67,760.00
|
| | 0.000 | 0.00
|
| | |
|
| 0031 6310.00 | 11.00 | 2,350.000 | 25,850.00
|
| STEEL SHEET PILING | SF | 2,350.000 | 25,850.00
|
| | | 2,350.000 | 25,850.00
|
| | 0.000 | 0.00
|
| | |
|
| 0032 7020.00 | 1,000.00 | 4.000 | 4,000.00
|
| BRIDGE APPROACH SECTIONS | EACH | 4.000 | 4,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0033 7021.48 | 1,250.00 | 4.000 | 5,000.00
|
| MELT, TYPE I | EACH | 4.000 | 5,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 4001 0001.99 | 0.79 | 0.000 | 0.00
|
| CONTRACTOR FURNISHED SIGN DAY | EACH | 624.000 | 492.96
|
| Contractor Furnished Sign Day | | 346.000 | 273.34
|
| | 318.000 | 251.22
|
| | |
|
| GROUP 6 BRIDGE AT STA. 16+85 | | Contracted | 554,971.11
|
| | Current | 555,464.07
|
| | In place | 405,862.94
|
| | This Estimate | 148,639.36
|
| | |
|
| Totals for contract | | Contracted | 554,971.11
|
|---|
| | Current | 555,464.07
|
|---|
| | In place | 405,862.94
|
|---|
| | This Estimate | 148,639.36
|
|---|