| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 6 BRIDGE AT STA. 25+20 | | |
|
0001 L006.00 | 120.00 | 3.000 | 360.00
|
COVER CROP SEEDING | ACRE | 3.000 | 360.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0002 0001.10 | 1.50 | 1,554.000 | 2,331.00
|
BARRICADE, TYPE III | BDAY | 1,554.000 | 2,331.00
|
| | 1,134.000 | 1,701.00
|
| | 294.000 | 441.00
|
| | |
|
0003 0001.30 | 1.15 | 222.000 | 255.30
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 222.000 | 255.30
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0004 0001.90 | 0.45 | 1,332.000 | 599.40
|
SIGN DAY | EACH | 1,332.000 | 599.40
|
| | 810.000 | 364.50
|
| | 210.000 | 94.50
|
| | |
|
0005 0030.60 | 26,000.00 | 1.000 | 26,000.00
|
MOBILIZATION | LS | 1.000 | 26,000.00
|
| | 1.000 | 26,000.00
|
| | 0.000 | 0.00
|
| | |
|
0006 1009.00 | 2,400.00 | 1.000 | 2,400.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 2,400.00
|
| | 0.300 | 720.00
|
| | 0.000 | 0.00
|
| | |
|
0007 1010.01 | 2.90 | 5,669.000 | 16,440.10
|
EXCAVATION (ESTABLISHED QUANTITY) | CY | 5,669.000 | 16,440.10
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0008 1011.00 | 9.99 | 26.000 | 259.74
|
WATER | MGAL | 26.000 | 259.74
|
| | 0.150 | 1.50
|
| | 0.000 | 0.00
|
| | |
|
0009 1043.50 | 2.00 | 1,010.000 | 2,020.00
|
RIPRAP FILTER FABRIC | SY | 1,010.000 | 2,020.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0010 1300.24 | 13.29 | 102.000 | 1,355.58
|
24" DRIVEWAY CULVERT PIPE | LF | 102.000 | 1,355.58
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0011 2009.51 | 60.00 | 10.476 | 628.56
|
CRUSHED ROCK EMBEDMENT | STA | 10.476 | 628.56
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0012 2010.03 | 14.10 | 303.000 | 4,272.30
|
CRUSHED ROCK SURFACE COURSE | TON | 303.000 | 4,272.30
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 4050.01 | 6.00 | 239.000 | 1,434.00
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | CY | 239.000 | 1,434.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0014 4300.24 | 16.95 | 68.000 | 1,152.60
|
24" CULVERT PIPE | LF | 68.000 | 1,152.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0015 4300.42 | 42.26 | 128.000 | 5,409.28
|
42" CULVERT PIPE | LF | 128.000 | 5,409.28
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0016 4310.24 | 114.12 | 1.000 | 114.12
|
24" FLARED-END SECTION | EACH | 1.000 | 114.12
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0017 4310.42 | 500.00 | 3.000 | 1,500.00
|
42" FLARED-END SECTION | EACH | 3.000 | 1,500.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0018 6000.10 | 3,000.00 | 1.000 | 3,000.00
|
ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 3,000.00
|
| | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
0019 6000.11 | 3,000.00 | 1.000 | 3,000.00
|
ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 3,000.00
|
| | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
0020 6001.50 | 6,000.00 | 1.000 | 6,000.00
|
BENT NO.1 EXCAVATION | LS | 1.000 | 6,000.00
|
| | 1.000 | 6,000.00
|
| | 0.000 | 0.00
|
| | |
|
0021 6001.51 | 6,000.00 | 1.000 | 6,000.00
|
BENT NO.2 EXCAVATION | LS | 1.000 | 6,000.00
|
| | 1.000 | 6,000.00
|
| | 0.000 | 0.00
|
| | |
|
0022 6010.22 | 265.00 | 168.900 | 44,758.50
|
CLASS 47B-3000 CONCRETE FOR BRIDGE | CY | 168.900 | 44,758.50
|
| | 136.450 | 36,159.25
|
| | 32.450 | 8,599.25
|
| | |
|
0023 6020.00 | 0.45 | 10,650.000 | 4,792.50
|
REINFORCING STEEL FOR BRIDGE | LB | 10,650.000 | 4,792.50
|
| | 8,280.000 | 3,726.00
|
| | 2,370.000 | 1,066.50
|
| | |
|
0024 6040.00 | 10,000.00 | 1.000 | 10,000.00
|
REMOVE STRUCTURE | EACH | 1.000 | 10,000.00
|
AT STA. 25+20.9 | | 1.000 | 10,000.00
|
| | 0.000 | 0.00
|
| | |
|
0025 6071.25 | 183,000.00 | 1.000 | 183,000.00
|
TIMBER SUPERSTRUCTURE | LS | 1.000 | 183,000.00
|
AT STA. 25+20 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0026 6080.00 | 2.50 | 7,750.000 | 19,375.00
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | LB | 7,750.000 | 19,375.00
|
| | 5,060.000 | 12,650.00
|
| | 2,447.200 | 6,118.00
|
| | |
|
0027 6105.02 | 31.00 | 798.000 | 24,738.00
|
ROCK RIPRAP, TYPE B | TON | 798.000 | 24,738.00
|
| | 1.000 | 31.00
|
| | 0.000 | 0.00
|
| | |
|
0028 6210.12 | 18.00 | 1,995.000 | 35,910.00
|
HP 10"X42# STEEL PILING | LF | 1,995.000 | 35,910.00
|
| | 1,875.620 | 33,761.16
|
| | 0.000 | 0.00
|
| | |
|
0029 6310.00 | 11.50 | 3,542.000 | 40,733.00
|
STEEL SHEET PILING | SF | 3,542.000 | 40,733.00
|
| | 3,523.040 | 40,514.96
|
| | 3,523.040 | 40,514.96
|
| | |
|
0030 7020.00 | 900.00 | 4.000 | 3,600.00
|
BRIDGE APPROACH SECTIONS | EACH | 4.000 | 3,600.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0031 7021.45 | 860.00 | 4.000 | 3,440.00
|
BREAKAWAY CABLE TERMINAL | EACH | 4.000 | 3,440.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0032 9005.30 | 138.00 | 70.000 | 9,660.00
|
ASPHALTIC CONCRETE, TYPE SP2(0.5) | TON | 70.000 | 9,660.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
4001 0001.99 | 0.85 | 0.000 | 0.00
|
CONTRACTOR FURNISHED SIGN DAY | EACH | 300.000 | 255.00
|
Contractor Furnished Sign | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
600 6210.59 | 10.80 | 0.000 | 0.00
|
PILE CUT-OFF | LF | 100.000 | 1,080.00
|
| | 103.380 | 1,116.50
|
| | 0.000 | 0.00
|
| | |
|
6003 6310.15 | 6.90 | 0.000 | 0.00
|
PAY CUT-OFF FOR STEEL SHEET PILING | SF | 100.000 | 690.00
|
Pay cut off for Steel Sheet Piling | | 43.640 | 301.12
|
| | 43.640 | 301.12
|
| | |
|
601 6210.61 | 90.00 | 0.000 | 0.00
|
PILE SPLICE | EACH | 3.000 | 270.00
|
| | 5.000 | 450.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 25+20 | | Contracted | 464,538.98
|
| | Current | 466,833.98
|
| | In place | 185,496.99
|
| | This Estimate | 57,135.33
|
| | |
|
Totals for contract | | Contracted | 464,538.98
|
---|
| | Current | 466,833.98
|
---|
| | In place | 185,496.99
|
---|
| | This Estimate | 57,135.33
|
---|