Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0751 JENSEN CO., INC./IRVING F.
Contract ID:1341X
Estimate Number:0013
Pay Period End Date:12.07.2002
Contract Location:
GREENWOOD EASTEstimate Type:PROG
Contractor:
JENSEN CO., INC./IRVING F.Date Let:12.06.2001
2220 HAWKEYE DRDate Awarded:12.20.2001
PO BOX 1618Date Contract Executed:02.06.2002
Date Notice to Proceed:02.06.2002
SIOUX CITY IA 51102Date Work Began:
Phone:Date Physical Work Completed:
(712)252-1891Date Accepted:
Escrow Agent:
Surety Co:
FEDERAL INSURANCE COMPANY
Counties
CASS
Project Number PCT Fed State Project Number Description
11341 000B  0.000 EACSTPE-3730(2)  GRAD CONCPAVE CULV SEED
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$2,141,164.54$2,083,105.82$58,058.72
$2,215,990.21Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$2,141,164.54$2,083,105.82$58,058.72
$2,188,707.29Retainage$-21,411.65$-20,831.06$-580.59
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
96.62%Net Earnings$2,119,752.89$2,062,274.76$57,478.13
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$1,602.96$1,602.96$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$1,602.96$1,602.96$.00
Payment$2,121,355.85$2,063,877.72$57,478.13
Project ManagerDiv. Head/Dist. Eng.
Sidiqi, Abdul12.11.2002Sklenar, Michael J12.12.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve12.13.2002
Controller Div. Processed
Burling, Laurie12.13.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 145.0020.8003,016.00
COVER CROP SEEDING ha 20.8003,016.00
0.0000.00
0.0000.00

0002                          0030.10 15,000.001.00015,000.00
MOBILIZATION LS 1.00015,000.00
1.00015,000.00
0.0000.00

0003                          1000.00 300.0026.0007,800.00
LARGE TREE REMOVAL EACH26.0007,800.00
46.00013,800.00
0.0000.00

0004                          1009.00 22,000.001.00022,000.00
GENERAL CLEARING AND GRUBBING LS 1.00022,000.00
1.00022,000.00
0.0000.00

0005                          1010.00 1.70106,739.000181,456.30
EXCAVATION m3 106,739.000181,456.30
106,739.000181,456.30
0.0000.00

0006                          1011.00 3.002,664.0007,992.00
WATER kL 2,664.0007,992.00
0.0000.00
0.0000.00

0007                          1300.18 25.00486.00012,150.00
450 mm DRIVEWAY CULVERT PIPE m 486.00012,150.00
513.00012,825.00
0.0000.00

0008                          1300.24 35.0022.000770.00
600 mm DRIVEWAY CULVERT PIPE m 22.000770.00
33.0001,155.00
0.0000.00

0009                          1300.30 45.0011.000495.00
750 mm DRIVEWAY CULVERT PIPE m 11.000495.00
0.0000.00
0.0000.00

0010                          1300.42 85.0011.000935.00
1050 mm DRIVEWAY CULVERT PIPE m 11.000935.00
11.000935.00
0.0000.00

4001                          L022.11 10.820.0000.00
FABRIC SILT FENCE-LOW POROSITY m 915.0009,900.30
Fabric Silt Fence - Low Porosity 585.0006,329.70
0.0000.00

4002                          9110.03 72.000.0000.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR10.000720.00
Rental of Dump Truck, Fully Operated 0.0000.00
0.0000.00

4003                          9110.07 121.000.0000.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR10.0001,210.00
Rental of Skid Loader, Fully Operated 3.000363.00
3.000363.00

4004                          2011.05 19.200.0000.00
CRUSHED ROCK FOR TEMPORARY SURFACING Mg 500.0009,600.00
Crushed Rock for Temp. Surfacing 1,905.56036,586.75
58.5901,124.93

GROUP 1 GRADINGContracted251,614.30
Current273,044.60
In place290,450.75
This Estimate1,487.93

GROUP 3 CONCRETE PAVEMENT
0011                          0030.30 73,000.001.00073,000.00
MOBILIZATION LS 1.00073,000.00
1.00073,000.00
0.0000.00

0012                          2010.03 20.00229.7404,594.80
CRUSHED ROCK SURFACE COURSE Mg 229.7404,594.80
484.3309,686.60
197.2803,945.60

0013                          2020.00 10.50200.0002,100.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 200.0002,100.00
190.0001,995.00
190.0001,995.00

0014                          2021.00 60.0010.000600.00
MAILBOX POST EACH10.000600.00
0.0000.00
0.0000.00

0015                          3020.26 31.051,337.55041,530.93
CONCRETE CLASS 47B-25 DRIVEWAY m2 1,337.55041,530.93
1,526.49047,397.51
676.26020,997.87

0016                          3075.41 21.5055,927.0001,202,430.50
230 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 55,927.0001,202,430.50
54,108.2501,163,327.39
69.5701,495.76

0017                          3300.50 3,400.001.0003,400.00
PORTLAND CEMENT CONCRETE SMOOTHNESS TESTING LS 1.0003,400.00
1.0003,400.00
0.0000.00

0018                          8029.75 1.9055,927.000106,261.30
BITUMINOUS FOUNDATION COURSE m2 55,927.000106,261.30
40,804.00077,527.60
0.0000.00

0019                          9111.00 2.501,212.0003,030.00
WATER kL 1,212.0003,030.00
0.0000.00
0.0000.00

0020                          9170.00 175.00150.50026,337.50
EARTH SHOULDER CONSTRUCTION StaM150.50026,337.50
150.50026,337.50
150.50026,337.50

0021                          9173.20 0.8557,264.55048,674.87
SUBGRADE PREPARATION m2 57,264.55048,674.87
57,473.33048,852.34
745.830633.96

0022                          9179.24 1,250.0075.25094,062.50
COLD MILLING, CLASS 4 StaM75.25094,062.50
75.25094,062.50
0.0000.00

4006                          3075.41 43.250.0000.00
230 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 72.0003,114.00
230 mm Concrete Pavement, 47B-25 for block out sections 0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted1,606,022.40
Current1,609,136.40
In place1,545,586.44
This Estimate55,405.69

GROUP 4 CULVERTS
0023                          0030.40 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
1.00010,000.00
0.0000.00

0024                          4044.00 2,000.001.0002,000.00
PREPARATION OF STRUCTURE EACH1.0002,000.00
AT STA 2+48.36 1.0002,000.00
0.0000.00

0025                          4044.01 2,000.001.0002,000.00
PREPARATION OF STRUCTURE EACH1.0002,000.00
AT STA. 8+06.87 1.0002,000.00
0.0000.00

0026                          4045.00 7,000.001.0007,000.00
REMOVE STRUCTURE EACH1.0007,000.00
AT STA. 17+98.04 1.0007,000.00
0.0000.00

0027                          4050.01 8.002,585.00020,680.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 2,585.00020,680.00
2,585.00020,680.00
0.0000.00

0028                          4051.01 16.00673.00010,768.00
EXCAVATION FOR BOX CULVERTS m3 673.00010,768.00
754.75012,076.00
0.0000.00

0029                          4101.06 335.00194.25065,073.75
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 194.25065,073.75
194.25065,073.75
0.0000.00

0030                          4151.00 1.5014,130.00021,195.00
REINFORCING STEEL FOR BOX CULVERT kg 14,130.00021,195.00
14,130.00021,195.00
0.0000.00

0031                          4450.24 111.0063.5007,048.50
600 mm REINFORCED CONCRETE PIPE m 63.5007,048.50
63.1307,007.43
0.0000.00

0032                          4450.30 155.0021.5003,332.50
750 mm REINFORCED CONCRETE PIPE m 21.5003,332.50
21.3403,307.70
0.0000.00

0033                          4450.36 203.0059.50012,078.50
900 mm REINFORCED CONCRETE PIPE m 59.50012,078.50
59.13012,003.39
0.0000.00

0034                          4450.42 235.00120.20028,247.00
1050 mm REINFORCED CONCRETE PIPE m 120.20028,247.00
118.66027,885.10
0.0000.00

0035                          4450.48 288.0026.2007,545.60
1200 mm REINFORCED CONCRETE PIPE m 26.2007,545.60
25.8807,453.44
0.0000.00

0036                          4450.54 344.0043.50014,964.00
1350 mm REINFORCED CONCRETE PIPE m 43.50014,964.00
43.20014,860.80
0.0000.00

0037                          4450.60 413.0031.50013,009.50
1500 mm REINFORCED CONCRETE PIPE m 31.50013,009.50
29.87012,336.31
0.0000.00

0038                          4450.66 485.0039.50019,157.50
1650 mm REINFORCED CONCRETE PIPE m 39.50019,157.50
39.00018,915.00
0.0000.00

0039                          4460.24 397.006.0002,382.00
600 mm CONCRETE FLARED-END SECTION EACH6.0002,382.00
6.0002,382.00
0.0000.00

0040                          4460.30 453.002.000906.00
750 mm CONCRETE FLARED END SECTION EACH2.000906.00
2.000906.00
0.0000.00

0041                          4460.36 730.006.0004,380.00
900 mm CONCRETE FLARED-END SECTION EACH6.0004,380.00
6.0004,380.00
0.0000.00

0042                          4460.42 850.008.0006,800.00
1050 mm CONCRETE FLARED-END SECTION EACH8.0006,800.00
8.0006,800.00
0.0000.00

0043                          4460.48 940.002.0001,880.00
1200 mm CONCRETE FLARED-END SECTION EACH2.0001,880.00
2.0001,880.00
0.0000.00

0044                          4460.54 1,144.004.0004,576.00
1350 mm CONCRETE FLARED-END SECTION EACH4.0004,576.00
5.0005,720.00
0.0000.00

0045                          4460.60 1,406.002.0002,812.00
1500 mm CONCRETE FLARED-END SECTION EACH2.0002,812.00
2.0002,812.00
0.0000.00

0046                          4460.66 1,777.002.0003,554.00
1650 mm CONCRETE FLARED-END SECTION EACH2.0003,554.00
2.0003,554.00
0.0000.00

0047                          4500.48 418.0017.0007,106.00
1200 mm ROUND EQUIVALENT REINFORCED CONCRETE PIPE m 17.0007,106.00
18.0007,524.00
0.0000.00

0048                          4510.48 1,661.002.0003,322.00
1200 mm ROUND EQUIVALENT CONCRETE FLARED-END SECTION EACH2.0003,322.00
2.0003,322.00
0.0000.00

0049                          6105.01 34.4022.100760.24
ROCK RIPRAP, TYPE A Mg 22.100760.24
21.845751.47
0.0000.00

0050                          6105.02 33.0056.5001,864.50
ROCK RIPRAP, TYPE B Mg 56.5001,864.50
52.7101,739.43
0.0000.00

4005                          4051.12 33.500.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 81.7502,738.63
Granular Material for Structure Foundations, 702.05, 6A 81.7502,738.63
0.0000.00

GROUP 4 CULVERTSContracted284,442.59
Current287,181.21
In place288,303.45
This Estimate0.00

GROUP 5 SEEDING
0051                          L001.01 1,120.0020.80023,296.00
SEEDING, TYPE A ha 20.80023,296.00
0.0000.00
0.0000.00

0052                          L032.75 75.00104.0007,800.00
MULCH Mg 104.0007,800.00
0.0000.00
0.0000.00

0053                          0030.50 200.001.000200.00
MOBILIZATION LS 1.000200.00
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted31,296.00
Current31,296.00
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0054                          0001.10 1.504,000.0006,000.00
BARRICADE, TYPE III BDAY4,000.0006,000.00
7,441.00011,161.50
675.0001,012.50

0055                          0001.30 2.001,120.0002,240.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY1,120.0002,240.00
219.000438.00
0.0000.00

0056                          0001.90 0.204,960.000992.00
SIGN DAY EACH4,960.000992.00
6,872.0001,374.40
763.000152.60

0057                          0003.10 300.0010.0003,000.00
FLAGGING DAY 10.0003,000.00
2.500750.00
0.0000.00

0058                          0010.04 3,000.001.0003,000.00
FIELD OFFICE EACH1.0003,000.00
1.0003,000.00
0.0000.00

0059                          0030.00 100.001.000100.00
MOBILIZATION LS 1.000100.00
1.000100.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted15,332.00
Current15,332.00
In place16,823.90
This Estimate1,165.10

Totals for contractContracted2,188,707.29
Current2,215,990.21
In place2,141,164.54
This Estimate58,058.72