| | | 1. Contracted
|
|---|
| | | 2. Current
|
|---|
| | | 3. To date
|
|---|
| Item Nbr Item Code | Unit Price | | 4. This Est
|
|---|
| Item Description | Units | Qty | Amount
|
|---|
| GROUP 6 BRIDGE AT STA. 10+80.50 | | |
|
| 0001 L006.00 | 500.00 | 2.000 | 1,000.00
|
| COVER CROP SEEDING | ha | 2.000 | 1,000.00
|
| | | 2.000 | 1,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0002 0001.10 | 1.40 | 2,508.000 | 3,511.20
|
| BARRICADE, TYPE III | BDAY | 2,508.000 | 3,511.20
|
| | | 1,854.000 | 2,595.60
|
| | 0.000 | 0.00
|
| | |
|
| 0003 0001.30 | 1.00 | 418.000 | 418.00
|
| TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 418.000 | 418.00
|
| | | 412.000 | 412.00
|
| | 0.000 | 0.00
|
| | |
|
| 0004 0001.90 | 0.40 | 4,598.000 | 1,839.20
|
| SIGN DAY | EACH | 4,598.000 | 1,839.20
|
| | | 2,133.000 | 853.20
|
| | 0.000 | 0.00
|
| | |
|
| 0005 0030.60 | 30,000.00 | 1.000 | 30,000.00
|
| MOBILIZATION | LS | 1.000 | 30,000.00
|
| | | 1.000 | 30,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0006 1009.00 | 2,500.00 | 1.000 | 2,500.00
|
| GENERAL CLEARING AND GRUBBING | LS | 1.000 | 2,500.00
|
| | | 1.000 | 2,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0007 1011.00 | 2.80 | 124.000 | 347.20
|
| WATER | kL | 124.000 | 347.20
|
| | | 79.500 | 222.60
|
| | 0.000 | 0.00
|
| | |
|
| 0008 1030.00 | 4.80 | 7,084.000 | 34,003.20
|
| EARTHWORK MEASURED IN EMBANKMENT | m3 | 7,120.590 | 34,178.83
|
| | | 7,120.590 | 34,178.83
|
| | 0.000 | 0.00
|
| | |
|
| 0009 1043.50 | 2.00 | 1,132.000 | 2,264.00
|
| RIPRAP FILTER FABRIC | m2 | 1,132.000 | 2,264.00
|
| | | 1,530.458 | 3,060.92
|
| | 0.000 | 0.00
|
| | |
|
| 0010 1300.24 | 50.00 | 49.500 | 2,475.00
|
| 600 mm DRIVEWAY CULVERT PIPE | m | 49.500 | 2,475.00
|
| | | 49.500 | 2,475.00
|
| | 0.000 | 0.00
|
| | |
|
| 0011 2010.03 | 17.00 | 325.000 | 5,525.00
|
| CRUSHED ROCK SURFACE COURSE | Mg | 325.000 | 5,525.00
|
| | | 323.810 | 5,504.77
|
| | 0.000 | 0.00
|
| | |
|
| 0012 4050.01 | 5.30 | 231.000 | 1,224.30
|
| EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 231.000 | 1,224.30
|
| | | 231.000 | 1,224.30
|
| | 0.000 | 0.00
|
| | |
|
| 0013 4300.24 | 75.00 | 96.500 | 7,237.50
|
| 600 mm CULVERT PIPE | m | 96.500 | 7,237.50
|
| | | 96.500 | 7,237.50
|
| | 0.000 | 0.00
|
| | |
|
| 0014 4310.24 | 530.00 | 4.000 | 2,120.00
|
| 600 mm FLARED-END SECTION | EACH | 4.000 | 2,120.00
|
| | | 4.000 | 2,120.00
|
| | 0.000 | 0.00
|
| | |
|
| 0015 6000.10 | 3,000.00 | 1.000 | 3,000.00
|
| ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 3,000.00
|
| | | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0016 6000.11 | 3,000.00 | 1.000 | 3,000.00
|
| ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 3,000.00
|
| | | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0017 6001.50 | 8,000.00 | 1.000 | 8,000.00
|
| BENT NO.1 EXCAVATION | LS | 1.000 | 8,000.00
|
| | | 1.000 | 8,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0018 6001.51 | 8,000.00 | 1.000 | 8,000.00
|
| BENT NO.2 EXCAVATION | LS | 1.000 | 8,000.00
|
| | | 1.000 | 8,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0019 6010.22 | 330.00 | 170.200 | 56,166.00
|
| CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 170.200 | 56,166.00
|
| | | 170.200 | 56,166.00
|
| | 0.000 | 0.00
|
| | |
|
| 0020 6010.26 | 320.00 | 212.700 | 68,064.00
|
| CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 212.700 | 68,064.00
|
| | | 212.700 | 68,064.00
|
| | 0.000 | 0.00
|
| | |
|
| 0021 6020.00 | 1.30 | 27,650.000 | 35,945.00
|
| REINFORCING STEEL FOR BRIDGE | kg | 27,650.000 | 35,945.00
|
| | | 27,650.000 | 35,945.00
|
| | 0.000 | 0.00
|
| | |
|
| 0022 6040.00 | 12,000.00 | 1.000 | 12,000.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 12,000.00
|
| AT STA. 10+82.9 | | 1.000 | 12,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0023 6080.00 | 5.00 | 1,040.000 | 5,200.00
|
| STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 1,040.000 | 5,200.00
|
| | | 1,040.000 | 5,200.00
|
| | 0.000 | 0.00
|
| | |
|
| 0024 6105.02 | 24.00 | 1,113.000 | 26,712.00
|
| ROCK RIPRAP, TYPE B | Mg | 1,113.000 | 26,712.00
|
| | | 1,476.522 | 35,436.53
|
| | 0.000 | 0.00
|
| | |
|
| 0025 6210.12 | 56.00 | 192.600 | 10,785.60
|
| HP 250 mm X 62 kg STEEL PILING | m | 192.600 | 10,785.60
|
| | | 154.480 | 8,650.88
|
| | 0.000 | 0.00
|
| | |
|
| 0026 6210.14 | 64.00 | 271.400 | 17,369.60
|
| HP 310 mm X 79 kg STEEL PILING | m | 271.400 | 17,369.60
|
| | | 249.590 | 15,973.76
|
| | 0.000 | 0.00
|
| | |
|
| 0027 6251.40 | 320.00 | 101.200 | 32,384.00
|
| ROCK SOCKET | m | 101.200 | 32,384.00
|
| | | 101.200 | 32,384.00
|
| | -1.280 | -409.60
|
| | |
|
| 0028 7020.00 | 1,300.00 | 4.000 | 5,200.00
|
| BRIDGE APPROACH SECTIONS | EACH | 4.000 | 5,200.00
|
| | | 4.000 | 5,200.00
|
| | 0.000 | 0.00
|
| | |
|
| 0029 7021.45 | 1,200.00 | 4.000 | 4,800.00
|
| BREAKAWAY CABLE TERMINAL | EACH | 4.000 | 4,800.00
|
| | | 4.000 | 4,800.00
|
| | 0.000 | 0.00
|
| | |
|
| 0601 6210.32 | 33.60 | 0.000 | 0.00
|
| PAY CUT-OFF FOR 250 mm X 62 kg STEEL PILING | m | 20.000 | 672.00
|
| | | 38.120 | 1,280.83
|
| | 0.000 | 0.00
|
| | |
|
| 0602 6210.34 | 38.40 | 0.000 | 0.00
|
| PAY CUT-OFF FOR 310 mm X 79 kg STEEL PILING | m | 10.000 | 384.00
|
| | | 21.810 | 837.50
|
| | 0.000 | 0.00
|
| | |
|
| 0603 6003.00 | 31.85 | 0.000 | 0.00
|
| GRANULAR MATERIAL FOR BRIDGE FOUNDATIONS | m3 | 10.000 | 318.50
|
| | | 6.064 | 193.14
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 6 BRIDGE AT STA. 10+80.50 | | Contracted | 391,090.80
|
| | Current | 392,640.93
|
| | In place | 397,516.36
|
| | This Estimate | -409.60
|
| | |
|
| Totals for contract | | Contracted | 391,090.80
|
|---|
| | Current | 392,640.93
|
|---|
| | In place | 397,516.36
|
|---|
| | This Estimate | -409.60
|
|---|