Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:1742 HERBST CONSTRUCTION, INC.
Contract ID:1256
Estimate Number:0017
Pay Period End Date:03.15.2002
Contract Location:
REYNOLDS SOUTHEstimate Type:PROG
Contractor:
HERBST CONSTRUCTION, INC.Date Let:03.29.2001
16022 HWY 75Date Awarded:04.16.2001
PO BOX 728Date Contract Executed:05.11.2001
Date Notice to Proceed:07.16.2001
LE MARS IA 51031-0728Date Work Began:
Phone:Date Physical Work Completed:
(712)546-5653Date Accepted:
Escrow Agent:
Surety Co:
MERCHANTS BONDING COMPANY (MUTUAL)
Counties
JEFFERSON
Project Number PCT Fed State Project Number Description
12256 000  0.000 BR-2985(7)  CONCPAVE BR GDRL
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$462,292.82$433,972.27$28,320.55
$453,664.32Stockpiled Materials$-.01$-.01$.00
Original Contract AmtGross Earnings$462,292.81$433,972.26$28,320.55
$451,721.50Retainage$-4,622.93$-4,339.73$-283.20
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
101.90%Net Earnings$457,669.88$429,632.53$28,037.35
Liquidated Damages-$7,224.00-$6,622.00-$602.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$7,224.00-$6,622.00-$602.00
Payment$450,445.88$423,010.53$27,435.35
Project ManagerDiv. Head/Dist. Eng.
Kuper, Melvin03.15.2002Sklenar, Michael J03.18.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve03.18.2002
Controller Div. Processed
Burling, Laurie03.18.2002
Detailed breakdown of stockpiled materials
Est Nbr:0004
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00246080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Initial Payment4,525.000-216-C
substructure steel
Total for estimate 0004:4,525.00
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00266131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment8,191.05464535
Epoxy Coated Re-Steel
00276210.12 HP 250 mm X 62 kg STEEL PILING
S.P. Initial Payment16,008.180-216-C
HP 250 X 62 Steel Piling
Total for estimate 0005:24,199.23
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00276210.12 HP 250 mm X 62 kg STEEL PILING
S.P. Adjustment-10,992.950-216-C
HP 250 X 62 Steel Piling
Total for estimate 0006:-10,992.95
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00246080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Adjustment-4,171.000-216-C
substructure steel
00266131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-797.81464535
Epoxy Coated Re-Steel
Total for estimate 0007:-4,968.81
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00276210.12 HP 250 mm X 62 kg STEEL PILING
S.P. Adjustment-5,015.230-216-C
HP 250 X 62 Steel Piling
Total for estimate 0008:-5,015.23
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00266131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-948.17464535
Epoxy Coated Re-Steel
Total for estimate 0009:-948.17
Est Nbr:0010
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00246080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Adjustment-354.000-216-C
substructure steel
00266131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-1,807.35464535
Epoxy Coated Re-Steel
Total for estimate 0010:-2,161.35
Est Nbr:0015
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00266131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-4,637.73464535
Epoxy Coated Re-Steel
Total for estimate 0015:-4,637.73
Total remaining for contract:-0.01
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 3 CONCRETE PAVEMENT
0001                          L006.00 1,500.001.5002,250.00
COVER CROP SEEDING ha 1.5002,250.00
1.5002,250.00
0.0000.00

0002                          0030.30 6,000.001.0006,000.00
MOBILIZATION LS 1.0006,000.00
1.0006,000.00
0.0000.00

0003                          1009.00 4,000.001.0004,000.00
GENERAL CLEARING AND GRUBBING LS 1.0004,000.00
1.0004,000.00
0.0000.00

0004                          1010.01 6.003,637.00021,822.00
EXCAVATION (ESTABLISHED QUANTITY) m3 3,637.00021,822.00
3,637.00021,822.00
0.0000.00

0005                          1011.00 6.0045.000270.00
WATER kL 45.000270.00
0.0000.00
0.0000.00

0006                          1102.00 2.75910.0002,502.50
REMOVE ASPHALT SURFACE m2 910.0002,502.50
910.0002,502.50
0.0000.00

0007                          3075.31 52.00737.00038,324.00
205 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 0.0000.00
0.0000.00
0.0000.00

0008                          4050.01 9.00305.0002,745.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 305.0002,745.00
305.0002,745.00
0.0000.00

0009                          4300.24 72.0032.5002,340.00
600 mm CULVERT PIPE m 32.5002,340.00
32.5002,340.00
0.0000.00

0010                          4300.30 80.0048.0003,840.00
750 mm CULVERT PIPE m 48.0003,840.00
48.0003,840.00
0.0000.00

0011                          4310.24 250.001.000250.00
600 mm FLARED-END SECTION EACH1.000250.00
1.000250.00
0.0000.00

0012                          4310.30 275.002.000550.00
750 mm FLARED-END SECTION EACH2.000550.00
2.000550.00
0.0000.00

4004                          3075.31 50.480.0000.00
205 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 737.00037,203.76
(Revised) 936.80047,289.66
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted84,893.50
Current83,773.26
In place93,589.16
This Estimate0.00

GROUP 6 BRIDGE AT STA. 9+51.5
0013                          0030.60 15,000.001.00015,000.00
MOBILIZATION LS 1.00015,000.00
1.00015,000.00
0.0000.00

0014                          1043.50 2.301,578.0003,629.40
RIPRAP FILTER FABRIC m2 1,578.0003,629.40
1,578.0003,629.40
328.000754.40

0015                          3050.15 241.00104.50025,184.50
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 104.50025,184.50
104.50025,184.50
0.0000.00

0016                          3051.10 1.355,375.0007,256.25
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 5,375.0007,256.25
5,375.0007,256.25
0.0000.00

0017                          6000.10 1,000.001.0001,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0001,000.00
1.0001,000.00
0.0000.00

0018                          6000.11 1,000.001.0001,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0001,000.00
1.0001,000.00
0.0000.00

0019                          6001.50 2,000.001.0002,000.00
BENT NO.1 EXCAVATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0020                          6001.51 2,000.001.0002,000.00
BENT NO.2 EXCAVATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0021                          6010.22 316.00219.90069,488.40
CLASS 47B-20 CONCRETE FOR BRIDGE m3 219.90069,488.40
219.90069,488.40
0.0000.00

0022                          6010.26 340.00221.30075,242.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 221.30075,242.00
221.30075,242.00
14.9005,066.00

0023                          6040.00 5,000.001.0005,000.00
REMOVE STRUCTURE EACH1.0005,000.00
AT STA. 9+55.6 1.0005,000.00
0.0000.00

0024                          6080.00 4.851,710.0008,293.50
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 1,710.0008,293.50
1,710.0008,293.50
0.0000.00

0025                          6105.02 30.701,561.00047,922.70
ROCK RIPRAP, TYPE B Mg 1,561.00047,922.70
1,556.78347,793.24
306.7839,418.24

0026                          6131.50 1.3530,125.00040,668.75
EPOXY COATED REINFORCING STEEL kg 30,125.00040,668.75
30,125.00040,668.75
2,130.0002,875.50

0027                          6210.12 55.00859.60047,278.00
HP 250 mm X 62 kg STEEL PILING m 859.60047,278.00
766.78042,172.90
0.0000.00

0401                          1009.10 3,046.000.0000.00
REMOVAL OF FLOOD DEBRIS LS 0.0000.00
Removal of flood debris 1.0003,046.00
0.0000.00

0403                          6210.59 33.000.0000.00
PILE CUT-OFF m 68.8802,273.04
Pile Cut Off 68.8802,273.04
0.0000.00

0404                          6210.59 33.000.0000.00
PAY CUT-OFF m 8.700287.10
8.700287.10
0.0000.00

0405                          6210.59 33.000.0000.00
PAY CUT-OFF m 15.240502.92
15.240502.92
0.0000.00

GROUP 6 BRIDGE AT STA. 9+51.5Contracted350,963.50
Current354,026.56
In place351,838.00
This Estimate18,114.14

GROUP 7 GUARDRAIL
0028                          0030.70 400.001.000400.00
MOBILIZATION LS 1.000400.00
1.000400.00
1.000400.00

0029                          7020.00 1,270.004.0005,080.00
BRIDGE APPROACH SECTIONS EACH4.0005,080.00
4.0005,080.00
4.0005,080.00

0030                          7021.45 1,100.004.0004,400.00
BREAKAWAY CABLE TERMINAL EACH4.0004,400.00
4.0004,400.00
4.0004,400.00

GROUP 7 GUARDRAILContracted9,880.00
Current9,880.00
In place9,880.00
This Estimate9,880.00

GROUP 10 GENERAL ITEMS
0031                          0001.10 2.001,836.0003,672.00
BARRICADE, TYPE III BDAY1,836.0003,672.00
2,904.0005,808.00
144.000288.00

0032                          0001.30 2.25306.000688.50
TYPE B HIGH INTENSITY WARNING LIGHT LDAY306.000688.50
0.0000.00
0.0000.00

0033                          0001.90 0.403,060.0001,224.00
SIGN DAY EACH3,060.0001,224.00
1,944.000777.60
96.00038.40

0034                          0030.00 400.001.000400.00
MOBILIZATION LS 1.000400.00
1.000400.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted5,984.50
Current5,984.50
In place6,985.60
This Estimate326.40

Totals for contractContracted451,721.50
Current453,664.32
In place462,292.76
This Estimate28,320.54