Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:1742 HERBST CONSTRUCTION, INC.
Contract ID:1204X
Estimate Number:0012
Pay Period End Date:02.08.2003
Contract Location:
OTOE WESTEstimate Type:PROG
Contractor:
HERBST CONSTRUCTION, INC.Date Let:08.16.2001
16022 HWY 75Date Awarded:08.23.2001
PO BOX 728Date Contract Executed:09.10.2001
Date Notice to Proceed:09.10.2001
LE MARS IA 51031-0728Date Work Began:08.26.2002
Phone:Date Physical Work Completed:
(712)546-5653Date Accepted:
Escrow Agent:
Surety Co:
MERCHANTS BONDING COMPANY (MUTUAL)
Counties
OTOE
Project Number PCT Fed State Project Number Description
12204 000  0.000 EACSTPD-S66C(103)  GR CULV BR GDRL
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$480,832.31$420,942.36$59,889.95
$530,529.57Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$480,832.31$420,942.36$59,889.95
$506,418.96Retainage$-4,808.32$-4,209.42$-598.90
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
90.63%Net Earnings$476,023.99$416,732.94$59,291.05
Liquidated Damages-$3,269.00$.00-$3,269.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$120.53$.00$120.53
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$3,148.47$.00-$3,148.47
Payment$472,875.52$416,732.94$56,142.58
Project ManagerDiv. Head/Dist. Eng.
Sidiqi, Abdul02.10.2003Sklenar, Michael J02.11.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve02.11.2003
Controller Div. Processed
Burling, Laurie02.11.2003
Detailed breakdown of stockpiled materials
Est Nbr:0001
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00356011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Initial Payment55,275.0097828600
Precast/Prestressted IT700 Girders (15)
Total for estimate 0001:55,275.00
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00356011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Adjustment-55,275.0097828600
Precast/Prestressted IT700 Girders (15)
Total for estimate 0009:-55,275.00
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L001.02 1,102.001.0001,102.00
SEEDING, TYPE B ha 1.0001,102.00
0.0000.00
0.0000.00

0002                          L006.50 525.000.300157.50
TEMPORARY SEEDING ha 0.300157.50
0.0000.00
0.0000.00

0003                          L020.00 2.00401.000802.00
EROSION CONTROL m2 401.000802.00
0.0000.00
0.0000.00

0004                          L022.11 8.00177.0001,416.00
FABRIC SILT FENCE-LOW POROSITY m 177.0001,416.00
159.0001,272.00
0.0000.00

0005                          L022.75 20.00115.0002,300.00
TEMPORARY SILT CHECK m 115.0002,300.00
0.0000.00
0.0000.00

0006                          L032.75 85.005.000425.00
MULCH Mg 5.000425.00
0.0000.00
0.0000.00

0007                          P406.96 520.0025.50013,260.00
2400 mm CULVERT PIPE, TYPE 2,3,4 OR 5 m 25.50013,260.00
29.52015,350.40
1.100572.00

0008                          0030.10 6,000.001.0006,000.00
MOBILIZATION LS 1.0006,000.00
1.0006,000.00
0.0000.00

0009                          1009.00 1,200.001.0001,200.00
GENERAL CLEARING AND GRUBBING LS 1.0001,200.00
1.0001,200.00
0.500600.00

0010                          1010.01 4.502,135.0009,607.50
EXCAVATION (ESTABLISHED QUANTITY) m3 2,135.0009,607.50
1,385.0006,232.50
1,385.0006,232.50

0011                          1011.00 2.00120.000240.00
WATER kL 120.000240.00
0.0000.00
0.0000.00

0012                          1012.00 75.007.000525.00
RIGHT-OF-WAY MARKERS EACH7.000525.00
7.000525.00
7.000525.00

0013                          1030.00 8.753,187.00027,886.25
EARTHWORK MEASURED IN EMBANKMENT m3 3,187.00027,886.25
3,187.00027,886.26
1,035.0009,056.25

0014                          1101.00 5.00233.0001,165.00
REMOVE PAVEMENT m2 233.0001,165.00
446.1042,230.53
213.1041,065.52

0015                          7017.00 5.00106.700533.50
REMOVE GUARDRAIL m 106.700533.50
88.000440.00
0.0000.00

0016                          9009.75 20.002,060.00041,200.00
TEMPORARY SURFACING m2 2,060.00041,200.00
2,136.82642,736.52
0.0000.00

GROUP 1 GRADINGContracted107,819.75
Current107,819.75
In place103,873.21
This Estimate18,051.27

GROUP 4 CULVERT
0017                          P300.42 150.0024.1003,615.00
1050 mm CULVERT PIPE, TYPE 3,4 OR 5 m 24.1003,615.00
24.1003,615.00
24.1003,615.00

0018                          P402.24 85.0020.7001,759.50
600 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 20.7001,759.50
20.7001,759.50
20.7001,759.50

0019                          P402.36 120.0023.6002,832.00
900 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 23.6002,832.00
23.6002,832.00
23.6002,832.00

0020                          0030.40 1,000.001.0001,000.00
MOBILIZATION LS 1.0001,000.00
1.0001,000.00
1.0001,000.00

0021                          1043.50 3.00216.000648.00
RIPRAP FILTER FABRIC m2 216.000648.00
0.0000.00
0.0000.00

0022                          4050.01 7.00139.000973.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 139.000973.00
139.000973.00
139.000973.00

0023                          4100.06 900.001.8001,620.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 1.8001,620.00
1.8001,620.00
1.8001,620.00

0024                          4150.00 3.00101.000303.00
REINFORCING STEEL FOR HEADWALL kg 101.000303.00
101.000303.00
101.000303.00

0025                          6105.02 26.00111.0002,886.00
ROCK RIPRAP, TYPE B Mg 111.0002,886.00
0.0000.00
0.0000.00

GROUP 4 CULVERTContracted15,636.50
Current15,636.50
In place12,102.50
This Estimate12,102.50

GROUP 6 BRIDGE AT STA. 35+46.00
0026                          0030.30 25,000.001.00025,000.00
MOBILIZATION LS 1.00025,000.00
1.00025,000.00
0.0000.00

0027                          1010.01 6.50800.0005,200.00
EXCAVATION (ESTABLISHED QUANTITY) m3 800.0005,200.00
800.0005,200.00
800.0005,200.00

0028                          1043.50 4.00560.0002,240.00
RIPRAP FILTER FABRIC m2 560.0002,240.00
560.0002,240.00
257.4741,029.90

0029                          3050.15 240.00124.70029,928.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 124.70029,928.00
124.70029,928.00
0.0000.00

0030                          3051.10 1.337,995.00010,633.35
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 7,995.00010,633.35
7,995.00010,633.36
0.0000.00

0031                          6000.10 5,000.001.0005,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0032                          6000.11 5,000.001.0005,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0033                          6010.22 450.0044.40019,980.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 44.40019,980.00
44.40019,980.00
0.0000.00

0034                          6010.26 400.0063.80025,520.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 63.80025,520.00
63.80025,520.00
0.0000.00

0035                          6011.11 78,000.001.00078,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.00078,000.00
AT STA. 35+46.00 1.00078,000.00
0.0000.00

0036                          6040.00 15,000.001.00015,000.00
REMOVE STRUCTURE EACH1.00015,000.00
AT STA. 35+44.80 1.00015,000.00
0.0000.00

0037                          6080.00 5.002,085.00010,425.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 2,085.00010,425.00
2,085.00010,425.00
0.0000.00

0038                          6104.00 15.0028.000420.00
BROKEN CONCRETE RIPRAP Mg 28.000420.00
28.000420.00
28.000420.00

0039                          6105.02 26.00498.00012,948.00
ROCK RIPRAP, TYPE B Mg 498.00012,948.00
493.43512,829.31
131.1573,410.08

0040                          6131.50 1.3510,950.00014,782.50
EPOXY COATED REINFORCING STEEL kg 10,950.00014,782.50
10,950.00014,782.50
0.0000.00

0041                          6210.14 70.00553.80038,766.00
HP 310 mm X 79 kg STEEL PILING m 553.80038,766.00
433.41830,339.26
0.0000.00

0042                          6310.00 115.90356.20041,283.58
STEEL SHEET PILING m2 356.20041,283.58
337.02639,061.31
0.0000.00

0043                          8091.00 35.00230.0008,050.00
GRANULAR BACKFILL m3 230.0008,050.00
133.5544,674.39
0.0000.00

4004                          3075.36 77.350.0000.00
205 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 213.10416,483.59
205mm Doweled Concrete Pavement, 47B-25 Sta. 35+07.07 - Sta. 35+18.67 & Sta. 35+73.33 - Sta.35+93.44 213.10416,483.59
213.10416,483.59

4005                          0003.51 45.950.0000.00
INSTALLING CONCRETE PROTECTION BARRIER m 36.6001,681.77
Install and Remove Concrete Protection Barriers (Temporary Bridge Protection) 36.6001,681.77
36.6001,681.77

6001                          6210.14 42.000.0000.00
HP 310 mm X 79 kg STEEL PILING m 120.3825,056.04
Authorized Pay Cut Off ( HP 310mm x 79kg, Steel Piling) 120.3825,056.04
0.0000.00

GROUP 6 BRIDGE AT STA. 35+46.00Contracted348,176.43
Current371,397.84
In place357,254.53
This Estimate28,225.34

GROUP 7 GUARDRAIL
0044                          0030.70 400.001.000400.00
MOBILIZATION LS 1.000400.00
0.0000.00
0.0000.00

0045                          7011.20 48.0022.8601,097.28
W-BEAM GUARDRAIL m 22.8601,097.28
0.0000.00
0.0000.00

0046                          7020.00 1,300.004.0005,200.00
BRIDGE APPROACH SECTIONS EACH4.0005,200.00
0.0000.00
0.0000.00

0047                          7024.27 1,700.004.0006,800.00
GUARDRAIL END TREATMENT, TYPE II EACH4.0006,800.00
0.0000.00
0.0000.00

0048                          9188.50 30.00330.0009,900.00
SURFACING UNDER GUARDRAIL m2 330.0009,900.00
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted23,397.28
Current23,397.28
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0049                          0001.10 2.60860.0002,236.00
BARRICADE, TYPE III BDAY860.0002,236.00
1,292.0003,359.20
492.0001,279.20

0050                          0001.30 2.00236.000472.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY236.000472.00
0.0000.00
0.0000.00

0051                          0001.90 0.253,024.000756.00
SIGN DAY EACH3,024.000756.00
3,654.000913.50
316.00079.00

0052                          0002.38 1.001,400.0001,400.00
TEMPORARY PAVEMENT MARKING, TYPE I m 0.0000.00
0.0000.00
0.0000.00

0053                          0010.04 4,000.001.0004,000.00
FIELD OFFICE EACH1.0004,000.00
0.0000.00
0.0000.00

0054                          0030.10 1,000.001.0001,000.00
MOBILIZATION LS 1.0001,000.00
1.0001,000.00
0.0000.00

0055                          9110.01 100.005.000500.00
RENTAL OF LOADER, FULLY OPERATED HOUR5.000500.00
0.0000.00
0.0000.00

0056                          9110.03 150.005.000750.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR5.000750.00
0.0000.00
0.0000.00

0057                          9110.07 55.005.000275.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR5.000275.00
0.0000.00
0.0000.00

4001                          0001.08 0.530.0000.00
BARRICADE, TYPE II BDAY1,800.000954.00
Barricade, Type II 2,376.0001,259.28
288.000152.64

4002                          0002.44 0.510.0000.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT m 2,000.4161,020.21
Temporary Pavement Marking, Type Paint 2,000.4161,020.21
0.0000.00

4003                          0002.30 1.050.0000.00
PAVEMENT MARKING REMOVAL m 300.000315.00
Pavement Marking Removal 47.50049.88
0.0000.00

GROUP 10 GENERAL ITEMSContracted11,389.00
Current12,278.21
In place7,602.07
This Estimate1,510.84

Totals for contractContracted506,418.96
Current530,529.58
In place480,832.31
This Estimate59,889.95