Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0810 ELK HORN CONSTRUCTION CO.
Contract ID:1009
Estimate Number:0016
Pay Period End Date:01.18.2003
Contract Location:
PLYMOUTH SOUTHEstimate Type:PROG
Contractor:
ELK HORN CONSTRUCTION CO.Date Let:03.14.2002
2243 ANDREW AVEDate Awarded:04.01.2002
PO BOX 580Date Contract Executed:04.18.2002
Date Notice to Proceed:04.18.2002
SERGEANT BLUFF IA 51054Date Work Began:
Phone:Date Physical Work Completed:
(712)943-4430Date Accepted:
Escrow Agent:
Surety Co:
MERCHANTS BONDING COMPANY (MUTUAL)
Counties
JEFFERSON
Project Number PCT Fed State Project Number Description
12009 000  0.000 BR-3015(2)  GR CP BR GDRL
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$342,212.45$342,077.45$135.00
$490,407.70Stockpiled Materials$-.02$-.02$.00
Original Contract AmtGross Earnings$342,212.43$342,077.43$135.00
$490,101.70Retainage$-3,422.12$-3,420.77$-1.35
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
69.78%Net Earnings$338,790.31$338,656.66$133.65
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$107.67$107.67$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$107.67$107.67$.00
Payment$338,897.98$338,764.33$133.65
Project ManagerDiv. Head/Dist. Eng.
Kuper, Melvin01.21.2003Sklenar, Michael J01.21.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve01.21.2003
Controller Div. Processed
Burling, Laurie01.22.2003
Detailed breakdown of stockpiled materials
Est Nbr:0003
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00286080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Initial Payment1,974.670-216-C
substructural steel
00306131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment3,556.44501309
Epoxy reinforcing steel abut, bents, rail
00316210.12 HP 10"X42# STEEL PILING
S.P. Initial Payment7,322.600-216-C
HP10X42# steel piling
Total for estimate 0003:12,853.71
Est Nbr:0004
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00316210.12 HP 10"X42# STEEL PILING
S.P. Adjustment-2,648.600-216-C
HP10X42# steel piling
Total for estimate 0004:-2,648.60
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00316210.12 HP 10"X42# STEEL PILING
S.P. Adjustment-4,674.000-216-C
HP10X42# steel piling
Total for estimate 0005:-4,674.00
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00306131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-603.86501309
Epoxy reinforcing steel abut, bents, rail
Total for estimate 0006:-603.86
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00286080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Adjustment-987.340-216-C
substructural steel
00306131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-685.27501309
Epoxy reinforcing steel abut, bents, rail
Total for estimate 0007:-1,672.61
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00286080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Adjustment-582.500-216-C
substructural steel
00306131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-603.86501309
Epoxy reinforcing steel abut, bents, rail
Total for estimate 0008:-1,186.36
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00286080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Adjustment-404.840-216-C
substructural steel
00306131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-685.27501309
Epoxy reinforcing steel abut, bents, rail
Total for estimate 0009:-1,090.11
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00306131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-978.19501309
Epoxy reinforcing steel abut, bents, rail
Total for estimate 0011:-978.19
Total remaining for contract:-0.02
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 250.002.000500.00
COVER CROP SEEDING ACRE2.000500.00
0.0000.00
0.0000.00

0002                          0030.10 3,500.001.0003,500.00
MOBILIZATION LS 1.0003,500.00
1.0003,500.00
0.0000.00

0003                          1000.00 100.0056.0005,600.00
LARGE TREE REMOVAL EACH56.0005,600.00
26.0002,600.00
0.0000.00

0004                          1009.00 10,000.001.00010,000.00
GENERAL CLEARING AND GRUBBING LS 1.00010,000.00
0.9009,000.00
0.0000.00

0005                          1010.01 1.2311,220.00013,800.60
EXCAVATION (ESTABLISHED QUANTITY) CY 11,220.00013,800.60
9,699.80011,930.75
0.0000.00

0006                          1011.00 10.0024.000240.00
WATER MGAL24.000240.00
71.375713.75
0.0000.00

0007                          1102.00 2.102,411.0005,063.10
REMOVE ASPHALT SURFACE SY 2,411.0005,063.10
2,704.0005,678.40
0.0000.00

0008                          4050.01 6.00105.000630.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS CY 105.000630.00
105.000630.00
0.0000.00

0009                          4300.48 46.0068.0003,128.00
48" CULVERT PIPE LF 68.0003,128.00
66.7083,068.57
0.0000.00

0010                          4310.48 950.001.000950.00
48" FLARED-END SECTION EACH1.000950.00
1.000950.00
0.0000.00

GROUP 1 GRADINGContracted43,411.70
Current43,411.70
In place38,071.47
This Estimate0.00

GROUP 3 CONCRETE PAVEMENT
0011                          0030.30 15,000.001.00015,000.00
MOBILIZATION LS 1.00015,000.00
0.0000.00
0.0000.00

0012                          3075.32 34.502,640.00091,080.00
8" CONCRETE PAVEMENT, CLASS 47B-3500 SY 2,640.00091,080.00
0.0000.00
0.0000.00

0013                          8029.04 7.002,640.00018,480.00
AGGREGATE FOUNDATION COURSE 4" SY 2,640.00018,480.00
0.0000.00
0.0000.00

0014                          9111.00 10.0013.000130.00
WATER MGAL13.000130.00
0.0000.00
0.0000.00

0015                          9170.00 275.0021.8005,995.00
EARTH SHOULDER CONSTRUCTION STA 21.8005,995.00
0.0000.00
0.0000.00

0016                          9173.20 2.502,640.0006,600.00
SUBGRADE PREPARATION SY 2,640.0006,600.00
0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted137,285.00
Current137,285.00
In place0.00
This Estimate0.00

GROUP 6 BRIDGE AT STA. 201+72
0017                          0030.60 29,000.001.00029,000.00
MOBILIZATION LS 1.00029,000.00
1.00029,000.00
0.0000.00

0018                          1043.50 2.001,076.0002,152.00
RIPRAP FILTER FABRIC SY 1,076.0002,152.00
1,076.0002,152.00
0.0000.00

0019                          3050.15 200.00137.10027,420.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-4000 CY 137.10027,420.00
137.10027,420.00
0.0000.00

0020                          3051.10 0.5211,785.0006,128.20
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES LB 11,785.0006,128.20
11,785.0006,128.20
0.0000.00

0021                          6000.10 4,000.001.0004,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0004,000.00
1.0004,000.00
0.0000.00

0022                          6000.11 4,000.001.0004,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0004,000.00
1.0004,000.00
0.0000.00

0023                          6001.50 6,000.001.0006,000.00
BENT NO.1 EXCAVATION LS 1.0006,000.00
1.0006,000.00
0.0000.00

0024                          6001.51 6,000.001.0006,000.00
BENT NO.2 EXCAVATION LS 1.0006,000.00
1.0006,000.00
0.0000.00

0025                          6010.22 300.00201.70060,510.00
CLASS 47B-3000 CONCRETE FOR BRIDGE CY 201.70060,510.00
211.50063,450.00
0.0000.00

0026                          6010.26 300.00195.50058,650.00
CLASS 47BD-4000 CONCRETE FOR BRIDGE CY 195.50058,650.00
195.50058,650.00
0.0000.00

0027                          6040.00 15,000.001.00015,000.00
REMOVE STRUCTURE EACH1.00015,000.00
AT STA. 201+94 1.00015,000.00
0.0000.00

0028                          6080.00 2.001,695.0003,390.00
STRUCTURAL STEEL FOR SUBSTRUCTURE LB 1,695.0003,390.00
1,695.0003,390.00
0.0000.00

0029                          6105.02 25.00906.00022,650.00
ROCK RIPRAP, TYPE B TON 906.00022,650.00
907.86022,696.50
0.0000.00

0030                          6131.50 0.5249,610.00025,797.20
EPOXY COATED REINFORCING STEEL LB 49,610.00025,797.20
49,610.00025,797.20
0.0000.00

0031                          6210.12 17.001,400.00023,800.00
HP 10"X42# STEEL PILING LF 1,400.00023,800.00
1,400.00023,800.00
0.0000.00

GROUP 6 BRIDGE AT STA. 201+72Contracted294,497.40
Current294,497.40
In place297,483.90
This Estimate0.00

GROUP 7 GUARDRAIL
0032                          0030.70 500.001.000500.00
MOBILIZATION LS 1.000500.00
0.0000.00
0.0000.00

0033                          7020.00 1,000.004.0004,000.00
BRIDGE APPROACH SECTIONS EACH4.0004,000.00
0.0000.00
0.0000.00

0034                          7021.45 839.004.0003,356.00
BREAKAWAY CABLE TERMINAL EACH4.0003,356.00
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted7,856.00
Current7,856.00
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0035                          0001.10 1.501,752.0002,628.00
BARRICADE, TYPE III BDAY1,752.0002,628.00
3,022.0004,533.00
28.00042.00

0036                          0001.30 0.80292.000233.60
TYPE B HIGH INTENSITY WARNING LIGHT LDAY292.000233.60
88.00070.40
0.0000.00

0037                          0001.90 0.752,920.0002,190.00
SIGN DAY EACH2,920.0002,190.00
1,484.0001,113.00
124.00093.00

0038                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
0.0000.00
0.0000.00

0039                          0030.10 500.001.000500.00
MOBILIZATION LS 1.000500.00
1.000500.00
0.0000.00

4000                          0001.90 0.680.0000.00
SIGN DAY EACH450.000306.00
NCHRP 350 (TL-3) compliance 648.000440.64
0.0000.00

GROUP 10 GENERAL ITEMSContracted7,051.60
Current7,357.60
In place6,657.04
This Estimate135.00

Totals for contractContracted490,101.70
Current490,407.70
In place342,212.41
This Estimate135.00