Paxton-Sutherland
Project #
STP-30-2(138)

C.N. 61461

Text Only

Project Contacts:

Toby Fierstein, NDOR Project Engineer, 402-479-4545
Efrain Quintanilla, NDOR Project Designer, 402-479-4440

PDF Map of Proposed Detour

Proposed Construction:

The proposed project begins west of the Paxton Link (NE-L51C, know locally as Oak Street), in Paxton, and continues east on US-30 (known as 2nd Street in Paxton) to the western city limits of Sutherland.  The project consists of resurfacing the existing roadway and shoulders.

Right-of Way:

none anticipated

Phasing:

A segment of the project will involve closure of US-30, from the east corporate limits of Paxton at Sarben St. to the Nebraska Highway 25 (NE-25) connection at Sutherland.  US-30 through traffic will be detoured onto Interstate 80 (I-80) using the L51C link (Elsie Road) at Paxton and Nebraska Highway 25 (NE-25) at Sutherland.  Local traffic will be maintained.

Schedule:

The project is scheduled to be Let in the spring of 2010.  Construction will take approximately one construction season to complete.

Cost:

The project is estimated to cost $6.9 million.  (2009 dollars)