|
Project
Contacts: Some of the documents are in PDF. Many of the documents below are in DjVu format. Even though this format reduces file size dramatically, some of the files are still quite large. Please allow adequate time for download if you have a dial-up connection. If you do not have the DjVu reader, please download the FREE READER by clicking on the DjVu button on the sidebar to the left.
Narrative updated January 2008 Proposed Construction: (updated 1-2008) The existing four lane interstate facility between Lincoln and Omaha will be expanded to six lanes. The work will be split into eight projects starting west of Lincoln at the NW 56th Street overhead structure to the west side of Omaha at the N-370 Interchange. The proposed improvements will include:
Interchanges reconstructed to provide safer acceleration/deceleration access to I-80. Interchanges with accesses close to ramps will be moved to 660’ from ramp terminals. Lincoln to Omaha encompasses the following:
Related Studies: (updated 6-3-2005) There are three median types for the proposed six lane: The first two are a 76’ and 88' median with a depressed grass median. The third type is a 28' paved median with a concrete barrier rail separating the traffic. Phasing: Work shall be done under traffic with 2 lanes of traffic available throughout the entire construction.
The 28' median will build temporary pavement on the first phase, which will allow the traffic to be placed head-to-head. The other side will then be completely constructed. Traffic will be switched to the new pavement and allow the construction of the remaining pavement. Schedule: (updated 3-2007) The first project segment, Ruff Road to N370, was started in 2003 and completed by the end of 2005. Work on a project segment in the Lincoln area, US77 South to the I-180 Interchange, began in 2004, and was completed by the end of 2007. The Department, in 2005, let the project for the I-80 segment from Mahoney Interchange to Ruff Road. This project should be completed in 2008. The final I-80 segment, 56th Street Interchange to the Waverly Interchange, may be built in 2011-2013. However, if current funding levels do not increase, this project will move to 2013-2015. This would mean that the entire six-lane expansion from Lincoln to Omaha will not be completed by 2013, but would be extended to 2015. Estimated Cost: The cumulative projects from NW 48th Street Interchange to N-370 will cost $393 million (2007 dollars). |
|||||||||||||||||