NEBRASKA DEPARTMENT OF ROADS DATE : 03/13/03
PAGE : 2
VENDOR RANKING
CALL ORDER : F19 CONTRACT ID : 7843 COUNTIES : HAYES
LETTING DATE : 03/13/03 DISTRICT : 7
CONTRACT DESCRIPTION : PROJECT(S) : BRO-7043(5)
ON A COUNTY ROAD SOUTHEAST OF HAYES CENTER
--------------------------------------------------------------------------------------------------------------------------
VENDOR NO. BID NOTES
--------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------
TOTAL % OVER
RANK VENDOR NO./NAME BID LOW BID
--------------------------------------------------------------------------------------------------------------------------
1 0929 MIDLANDS CONTRACTING, INC. $ 120,826.55 100.0000%
2 2126 CEMENT PRODUCTS, INC. $ 121,180.65 100.2931%
3 1730 WILKE CONTRACTING CORPORATION $ 133,399.25 110.4056%
4 3606 DOBSON BROTHERS CONSTRUCTION COMPANY AND AFFILIATES $ 147,250.45 121.8693%
5 3485 COLORADO CONSTRUCTORS, INC. $ 150,770.85 124.7829%
NEBRASKA DEPARTMENT OF ROADS DATE : 03/13/03
PAGE : F19 -3
TABULATION OF BIDS
CALL ORDER : F19 CONTRACT ID : 7843 COUNTIES : HAYES
LETTING DATE : 03/13/03 1:30 PM DISTRICT : 7
====================================================================================================================================
|( 1 ) 0929 |( 2 ) 2126 |( 3 ) 1730
|MIDLANDS CONTRACTING, INC. |CEMENT PRODUCTS, INC. |WILKE CONTRACTING CORPORATION
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
SECTION 0001 GROUP 4 CONCRETE BOX CULVERT AT STA. 12+60 TRIPLE 10' X 14' X 50' CONCRETE BOX CULVERT
| | |
0001 0001.10 996.000 BDAY| 1.35000 1344.60| 1.30000 1294.80| 1.50000 1494.00
BARRICADE, TYPE III | | |
0002 0001.90 996.000 EACH| 0.75000 747.00| 0.75000 747.00| 1.00000 996.00
SIGN DAY | | |
0003 0001.99 498.000 EACH| 1.05000 522.90| 1.00000 498.00| 1.25000 622.50
CONTRACTOR FURNISHED SIGN DAY | | |
0004 0030.40 LUMP| 9120.00000 9120.00| 15000.00000 15000.00| 10000.00000 10000.00
MOBILIZATION | | |
0005 1009.00 LUMP| 2000.00000 2000.00| 1000.00000 1000.00| 1250.00000 1250.00
GENERAL CLEARING AND GRUBBING | | |
0006 1011.00 25.000 MGAL| 10.00000 250.00| 15.00000 375.00| 16.00000 400.00
WATER | | |
0007 1030.00 2361.000 CY | 2.30000 5430.30| 3.95000 9325.95| 4.15000 9798.15
EARTHWORK MEASURED IN EMBANKMENT | | |
0008 4043.00 86.000 LF | 15.00000 1290.00| 15.00000 1290.00| 15.00000 1290.00
REMOVE CULVERT PIPE | | |
0009 4050.01 616.000 CY | 5.00000 3080.00| 5.25000 3234.00| 6.50000 4004.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS | | |
AND HEADWALLS | | |
0010 4051.01 357.000 CY | 8.00000 2856.00| 15.00000 5355.00| 12.00000 4284.00
EXCAVATION FOR BOX CULVERTS | | |
0011 4101.06 264.650 CY | 283.00000 74895.95| 250.00000 66162.50| 308.00000 81512.20
CLASS 47B-3000 OR AX-3000 CONCRETE FOR | | |
BOX CULVERT | | |
0012 4151.00 26664.000 LB | 0.70000 18664.80| 0.60000 15998.40| 0.60000 15998.40
REINFORCING STEEL FOR BOX CULVERT | | |
0013 6040.00 1.000 EACH| 500.00000 500.00| 800.00000 800.00| 1500.00000 1500.00
REMOVE STRUCTURE AT STA. 12+56 | | |
0014 L006.00 1.000 ACRE| 125.00000 125.00| 100.00000 100.00| 250.00000 250.00
COVER CROP SEEDING | | |
SECTION TOTALS | $ 120,826.55| $ 121,180.65| $ 133,399.25
------------------------------------------+----------------------------+----------------------------+-------------------------------
CONTRACT TOTALS | $ 120,826.55| $ 121,180.65| $ 133,399.25
====================================================================================================================================
NEBRASKA DEPARTMENT OF ROADS DATE : 03/13/03
PAGE : F19 -4
TABULATION OF BIDS
CALL ORDER : F19 CONTRACT ID : 7843 COUNTIES : HAYES
LETTING DATE : 03/13/03 1:30 PM DISTRICT : 7
====================================================================================================================================
|( 4 ) 3606 |( 5 ) 3485 |( )
|DOBSON BROTHERS CONSTRUCTIO |COLORADO CONSTRUCTORS, INC. |
LINE NO / ITEM CODE / ALT | | |
ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT
------------------------------------------+----------------------------+----------------------------+-------------------------------
SECTION 0001 GROUP 4 CONCRETE BOX CULVERT AT STA. 12+60 TRIPLE 10' X 14' X 50' CONCRETE BOX CULVERT
| | |
0001 0001.10 996.000 BDAY| 1.37000 1364.52| 1.50000 1494.00|
BARRICADE, TYPE III | | |
0002 0001.90 996.000 EACH| 0.79000 786.84| 1.00000 996.00|
SIGN DAY | | |
0003 0001.99 498.000 EACH| 1.05000 522.90| 1.50000 747.00|
CONTRACTOR FURNISHED SIGN DAY | | |
0004 0030.40 LUMP| 14000.00000 14000.00| 17000.00000 17000.00|
MOBILIZATION | | |
0005 1009.00 LUMP| 1842.20000 1842.20| 1000.00000 1000.00|
GENERAL CLEARING AND GRUBBING | | |
0006 1011.00 25.000 MGAL| 10.50000 262.50| 9.00000 225.00|
WATER | | |
0007 1030.00 2361.000 CY | 2.36000 5571.96| 4.00000 9444.00|
EARTHWORK MEASURED IN EMBANKMENT | | |
0008 4043.00 86.000 LF | 15.75000 1354.50| 9.00000 774.00|
REMOVE CULVERT PIPE | | |
0009 4050.01 616.000 CY | 5.25000 3234.00| 4.25000 2618.00|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS | | |
AND HEADWALLS | | |
0010 4051.01 357.000 CY | 17.80000 6354.60| 4.25000 1517.25|
EXCAVATION FOR BOX CULVERTS | | |
0011 4101.06 264.650 CY | 330.45000 87453.59| 360.00000 95274.00|
CLASS 47B-3000 OR AX-3000 CONCRETE FOR | | |
BOX CULVERT | | |
0012 4151.00 26664.000 LB | 0.90000 23997.60| 0.65000 17331.60|
REINFORCING STEEL FOR BOX CULVERT | | |
0013 6040.00 1.000 EACH| 373.99000 373.99| 2000.00000 2000.00|
REMOVE STRUCTURE AT STA. 12+56 | | |
0014 L006.00 1.000 ACRE| 131.25000 131.25| 350.00000 350.00|
COVER CROP SEEDING | | |
SECTION TOTALS | $ 147,250.45| $ 150,770.85| $ 0.00
------------------------------------------+----------------------------+----------------------------+-------------------------------
CONTRACT TOTALS | $ 147,250.45| $ 150,770.85| $
====================================================================================================================================
Contracts Office Please contact the Contracts Section with your questions/comments. Contact Construction Divison regarding web content/problems/suggestions. |
||||